Download presentation
Presentation is loading. Please wait.
1
Barry Barish JSPS - Sendai 12-Sept-11
Global Design Effort ILC R&D and Technical Design Energy stability over 3hrs with 4.5mA ~0.02% pk-pk 9 Feb 2011 Grooved Insert for CesrTA Wiggler Barry Barish JSPS - Sendai 12-Sept-11 FLASH Stability Tests 12-Sept JSPS - Sendai Global Design Effort
2
Outline Update on ILC accelerator R&D Plans and Scope of for the TDR
TDR Baseline TDR Phase 2 plans Scope and Contents of the TDR Future beyond 2012 12-Sept JSPS - Sendai Global Design Effort
3
R&D Progress global program focused on major test facilities
R&D Progress global program focused on major test facilities *** systems tests *** 12-Sept JSPS - Sendai Global Design Effort
4
Major R&D Goals for Technical Design
SCRF High Gradient R&D - globally coordinated program to demonstrate gradient by 2010 with 50%yield; improve yield to 90% by TDR (end 2012) Manufacturing: plug compatible design; industrialization, etc. Systems tests: FLASH; plus NML (FNAL), STF2 (KEK) post-TDR Test Facilities ATF2 - Fast Kicker tests and Final Focus design/performance EARTHQUAKE RECOVERY CesrTA - Electron Cloud tests to establish damping ring parameters/design and electron cloud mitigation strategy FLASH – Study performance using ILC-like beam and cryomodule 12-Sept JSPS - Sendai Global Design Effort Global Design Effort 4
5
SCRF Status/Progress high gradient cavities system tests industrialization
12-Sept JSPS - Sendai Global Design Effort
6
The ILC SCRF Cavity Achieve high gradient (35MV/m); develop multiple
vendors; make cost effective, etc Focus is on high gradient; production yields; cryogenic losses; radiation; system performance 12-Sept JSPS - Sendai Global Design Effort
7
Global Plan for ILC Gradient R&D
New baseline gradient: Vertical acceptance: 35 MV/m average, allowing ±20% spread (28-42 MV/m) Operational: 31.5 MV/m average, allowing ±20% spread (25-38 MV/m) 12-Sept JSPS - Sendai Global Design Effort
8
Cavity Gradient Milestone Achieved
TDR Goal 2010 Milestone Toward TDR goal Field emission; mechanical polishing Other progress 12-Sept JSPS - Sendai Global Design Effort
9
S1-Global: Systems Tests
19-May Pac Mtg - Taiwan Global Design Effort
10
Test Facilities: FLASH SCRF accelerator tests
12-Sept JSPS - Sendai Global Design Effort
11
12-Sept JSPS - Sendai Global Design Effort
12
Example Experimental Results
Beam Current (mA) 1 2 3 4 5 Gradient change over 400us (%) -3 -5 +3 +5 Gradient Tilts vs Beam Current (ACC7) Intended working point ~2.5% Characterisation of solution by scanning beam current model benchmarking Flat gradient solution achieved 4.5 mA beam 12-Sept JSPS - Sendai Global Design Effort
13
FLASH: Stability 15 consecutive studies shifts (120hrs), and with no downtime Time to restore 400us bunch-trains after beam-off studies: ~10mins Energy stability with beam loading over periods of hours: ~0.02% Individual cavity “tilts” equally stable Energy stability over 3hrs with 4.5mA ~0.02% pk-pk 9 Feb 2011 12-Sept JSPS - Sendai Global Design Effort
14
Test Facilities: Cesr-TA eCloud broad accelerator applications
12-Sept JSPS - Sendai Global Design Effort
15
eCloud R&D Mitigating Electron Cloud
Simulations – electrodes; coating and/or grooving vacuum pipe Demonstration at CESR critical tests 12-Sept JSPS - Sendai Global Design Effort
16
Mitigation - Simulation Studies
12-Sept JSPS - Sendai Global Design Effort
17
12-Sept JSPS - Sendai Global Design Effort
18
CesrTA - Wiggler Observations
0.002” radius Electrode a best performance 12-Sept JSPS - Sendai Global Design Effort IWLC CERN, Geneva, Switzerland
19
Proposed ILC Mitigation Scheme
Field Region Baseline Mitigation Recommendation Alternatives for Further Investigation Drift* TiN Coating Solenoid Windings NEG Coating Dipole Grooves with TiN Coating Antechambers for power loads and photoelectron control R&D into the use of clearing electrodes. Quadrupole* R&D into the use of clearing electrodes or grooves with TiN coating Wiggler Clearing Electrodes 12-Sept JSPS - Sendai Global Design Effort
20
Test Facilities: ATF-2 large international collaboration
12-Sept JSPS - Sendai Global Design Effort
21
ATF2 – Beam size/stability and kicker tests
IP Shintake Monitor Final Doublet 12-Sept JSPS - Sendai Global Design Effort
22
12-Sept JSPS - Sendai Global Design Effort
23
Design Update Global design and decision making
12-Sept JSPS - Sendai Global Design Effort
24
RDR Complete Reference Design Report (4 volumes) Physics Executive
Summary Physics at the ILC Detectors Accelerator 12-Sept JSPS - Sendai Global Design Effort
25
RDR Design Parameters Max. Center-of-mass energy 500 GeV
Peak Luminosity ~2x1034 1/cm2s Beam Current 9.0 mA Repetition rate 5 Hz Average accelerating gradient 31.5 MV/m Beam pulse length 0.95 ms Total Site Length 31 km Total AC Power Consumption ~230 MW 12-Sept JSPS - Sendai Global Design Effort
26
Establishing Baseline for the TDR
12-Sept JSPS - Sendai Global Design Effort
27
Proposed Design changes for TDR
RDR SB2009 Single Tunnel for main linac Move positron source to end of linac *** Reduce number of bunches factor of two (lower power) ** Reduce size of damping rings (3.2km) Integrate central region Single stage bunch compressor 12-Sept JSPS - Sendai Global Design Effort
28
Technical Design Phase and Beyond
change control process AAP PAC Physics TDP Baseline Technical Design TDR RDR Baseline SB2009 evolve TDP-2 TDP-1 Beijing Workshop CERN Workshop Change Request RDR ACD concepts R&D Demonstrations AD&I studies 2009 2010 2011 2012 2013 12-Sept JSPS - Sendai Global Design Effort 28
29
Plans through 2012 -------------- Technical Design Report (TDR)
12-Sept JSPS - Sendai Global Design Effort
30
Project Implementation Plan
Five Themes to Develop Remains special case Project Implementation Plan Industrialisation in-kind contribution models Site requirements Project Schedule Remaining Technical activities Regional expertise, global Industrialisation Average accelerating gradient Cost (cryomodule, mass-production models) SCRF Technology Sources DR (e-cloud) BDS / MDI R&D (General) Consolidation of baseline(s) Design choices (parameters, layout etc.) Design work (documentation) AD&I (CFS) ICET (schedule tool) Traceable, defendable Justification Cost & Schedule R&D (and engineering) beyond 2012 Impact (design, cost, schedule) Mitigation (fall-back solutions) TDR Risk >2012 12-Sept JSPS - Sendai Global Design Effort Global Design Effort 30 30 30
31
Technical Design Phase 2
Timescale: Produce final reports end of 2012 Technical Design (TDR) Project Implementation (PIP) (included) First goal: Technical Design (TDR) SCRF – S0 gradient; S1 Global Tests continue past 2012 Detailed technical design studies from new baseline Updated VALUE estimate and schedule. Remaining critical R&D and technology demonstration complete CesrTA; ATF-2; FLASH; etc. Second Goal: Project Implementation Plan (PIP) Studies of governance; siting solicitation and site preparations; manufacturing; etc. 12-Sept JSPS - Sendai Global Design Effort
32
Impact of Baseline Changes
12-Sept JSPS - Sendai Global Design Effort
33
Starting Point is the RDR Costs
12-Sept JSPS - Sendai Global Design Effort
34
OECD PPP (Yen/USD)-annual average by year
EX-exchange rate GDP: PPP based on all goods/services in GDP of each region M&E: PPP based on machinery and equipment Const: PPP based on civil construction Full PPP determinations were done for 2005 and 2008; other year points based on GDP inflation rates 12-Sept JSPS - Sendai Global Design Effort
35
Project Implementation Planning
12-Sept JSPS - Sendai Global Design Effort
36
(Global) Mass Production (SCRF)
Cost Effective Mass-Production Cavity Specs. / Yield Plug Compatible Interfaces Vendor Models Production process models In-kind contribution models PIP Governance TLCC-1 Global S1 TDP-2 Critically important TDP2 activity Learn from XFEL experience 5% ILC Learn from LHC experience Develop realistic models on which to base cost estimate With industry SCRF 12-Sept JSPS - Sendai Global Design Effort
37
12-Sept JSPS - Sendai Global Design Effort
38
KEK Industrial R&D Pilot Plant
Chemical Polish room 19m x 14m ISO class-5 clean room Electron Beam Welder Press machine work together with industry to develop cost-effective cavity production techniques Triming machine 12-Sept JSPS - Sendai Global Design Effort
39
ILC: Future after 2012 preserving GDE assets post-TDR pre-construction program
12-Sept JSPS - Sendai Global Design Effort
40
Technical design & R&D program
ILC possible timeline CY 2010 2011 2012 2013 2014 2015 2016 2017 2018 Technical Design Report complete Baseline established Decision to proceed TDR reviews ILC Technical design & R&D program Site/host established Site EOI’s Cost Estimating SRF system tests Project Implementation Plan complete XFEL operation Physics Run 1 Interconnect repair Physics Run 2 LHC Existence of low-lying SUSY known Higgs energy scale known timegap 12-Sept JSPS - Sendai Global Design Effort
41
Technical design & R&D program
ILC possible timeline CY 2010 2011 2012 2013 2014 2015 2016 2017 2018 Technical Design Report complete Baseline established Decision to proceed TDR reviews ILC Technical design & R&D program Site/host established Site EOI’s Cost Estimating SRF system tests Project Implementation Plan complete XFEL operation Physics Run 1 Interconnect repair Physics Run 2 LHC Existence of low-lying SUSY known Higgs energy scale known timegap 12-Sept JSPS - Sendai Global Design Effort
42
Post-2012 ILC Interim Goals & Organization
GDE will have successfully completed its mandate after TDR & PIP delivered + reviewed (mid-2013 at latest) What should follow GDE (mandate and organization) for an interim 3-5 year period? GDE position paper submitted to ILCSC Aug The paper addresses: Technical Goals proposed for program? Continued system demonstrations; Increasing energy reach Organizational Issues for post GDE? What are primary GDE assets that should be preserved? What are the primary GDE weaknesses that should be improved? 12-Sept JSPS - Sendai Global Design Effort
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.