Status at CERN and commissioning

Similar presentations


Presentation on theme: "Status at CERN and commissioning"— Presentation transcript:

1 Status at CERN and commissioning
Jalal ABDALLAH

2 Overview Commissioning and refurbishment evolution status
LVPS insertion status ROD status in USa15 New fibers routing of USa15 crates Summary of Team 4 developments

3 Commissioning status 2 partitions fully connected Finishing LBC
LVPS insertion Good progress for the refurbishment process

4 Evolution of the status since March 12th, 2007

5 LVPS Status (not updated as work continues) L. Price, S
LVPS Status (not updated as work continues) L. Price, S. Nemecek 24 May 2007 fLVPS ver.6.5.4: LBA = 64 Boxes LBC = 36 Boxes EBA = 64 Boxes EBC = 8 Boxes Total = 172

6 Schedule of LVPS insertion
LVPS Installations (v6.5.4)

7 ROD status All ROD crates are now connected and operational.
No problems observed except the bad soldering of some optical receivers, 2 cases up to now: One ROD was already replaced (LBA) Fourth input channel of RODF07 is broken (LBC) and will be replaced

8 Old fibers routing

9 New routing No more TTC or ROD fiber problem!

10 Team 4 developments: summary
Independent partitions across 4 computers for EBA, LBA, LBC and EBC. Switching between physics and calibration is now trivial It guarantees good data taking by avoiding human mistakes Boost the DDC project Getting the status of the slow control in TDAQ (showed by a panel) and sending back the status of the data taking. DVS upgrades: DVS “quick”, to verify the data taking (timing, pulses ...) DVS “Enhanced” a powerful tool for investigation Further on: Ttcrx register test Speed up ROD boot and configuration transitions People involved: Ali, Bruno, Carlos, Jalal, Luciano and Tiago