Microsoft Project 2007 Demo Part 1

Similar presentations


Presentation on theme: "Microsoft Project 2007 Demo Part 1"— Presentation transcript:

1 Microsoft Project 2007 Demo Part 1

2 Project: Initial Screen
You may wish to x (delete) window at left. Click Project/Project Information. Add start date.

3 Problem 1.1: Entering Activities & Times
Enter activities and times. Gantt chart will show up on right.

4 Activity (Task) Information
Double click on task to get window. Click on Predecessors tab.

5 Entering Predecessors
Enter ID number of all predecessor tasks. Use FS type and 0 lag to start.

6 Completing Data Entry Complete entering predecessors. Arrows for predecessors will show on Gantt Chart.

7 Showing the Critical Path
Click Format/Gantt Chart Wizard/Critical Path/Dates. Critical Path will show in red. You can manually move activity on Gantt Chart by left clicking and dragging on center of activity bar. Left click on right and drag extends duration of activity. Left click on left and drag changes percent completion.

8 Showing Slack Clicking Format/Gantt Chart Wizard/Critical Path/Custom task information allows you to show start time, finish time, slack.

9 Showing Slack To show total slack and free slack on table, click View, then Table, and then Schedule.

10 Network Diagram To see AON diagram click View/Network Diagram

11