Monitoring Prompt Payment and Return of Retainage
Christine Thorkildsen, FHWA Civil Rights Program Manager
2
Presentation Objective
Review the Federal requirements of prompt payment and return of retainage (49 CFR 26.29) Provide methods of administration and oversight Share examples of challenges, solutions and best practices Lots of audience interaction!
3
What is Prompt Payment and Return of Retainage?
The DBE regulations require Recipients to ensure prime contractors pay all subcontractors: Promptly (no later than 30* days of receipt) and, Prompt and full payment of retainage 30 days after the subcontractor’s work is satisfactorily completed. *30-day limit is fed requirement – STA might have shorter timeframe which is great! So if the prime is paid for work the sub has completed then the sub must be paid NLT 30 days later
4
Why Prompt Payment & Return of Retainage?
To address the barriers created by delays in payment to subcontractors Slow payment is a problem affecting many subcontractors, not just DBEs Prompt payment provisions are an important race-neutral mechanism that can benefit DBEs and all other small businesses Need to support small businesses which include DBEs It is clear that DBE subcontractors are significantly—and, to the extent that they tend to be smaller than non-DBEs, disproportionately—affected by late payments from prime contractors. Lack of prompt payment constitutes a very real barrier to the ability of DBEs to compete in the marketplace.
5
Which Subcontractors Does PP Apply?
All subcontractors! On and off site DBEs and non-DBEs Truckers, suppliers, engineering services, etc, etc All firms associated with the project Why is this confusing? The Prompt Pay provision is included in 49 CFR 26 State’s define “subcontractor” differently Tiering of subcontracting All subcontractors??
6
More Talk on Tiering For each tier of subcontracting another NTE 30-days for payment is added Example: 3 Tiers of subcontracting: Prime – Paid 1st Tier – NTE 30 days 2nd Tier – NTE 30 days of when 1st tier was paid 3rd Tier – NTE 30 days of when 2nd tier was paid From when prime is paid could take up to 90 days to pay 3rd tier sub
7
Who is responsible for Prompt Payment?
FHWA State Transportation Agency Non-traditional recipients of Federal funding Developers Prime contractors Subcontractors
8
DBE Program Plan DBE Program Plan Should include:
Affirmation that recipient has contract clauses for prompt payment and return of retainage Method used for return of retainage Description of monitoring mechanism and staff responsibilities Description of dispute resolution mechanism Description of contract remedies and sanctions applicable to prompt payment How prompt payment complaints will be investigated
9
Contract Clause Obligates the contractor to pay the subcontractor for satisfactory completion of their work No later than 30 days of when the prime or upper tier has been paid Must be included in every DOT-assisted contract How does STA assure the clause is in their federal contracts?
10
What is retainage? Withholding a certain percentage of payment until all work is satisfactorily completed Benefit: motivates sub to complete work faster and completely – including submittal of documentation such as certified payrolls Challenge: more oversight
11
Return of Retainage There are 3 options for retainage:
Recipient does not hold retainage from prime Recipient does not hold retainage from prime – but prime can withhold from subcontractor Recipient can hold retainage from prime and pay retainage based on payment for portions of work (incremental acceptance) Once work is accepted, prime must pay all retainage owed within 30 days. The STA must state in their DBE PP and in their standard specifications and contract language with the prime if the STA is allowing either 2 or 3 above
12
When should retainage be returned?
The prime withholding a subcontractor’s retainage until the end of the project is not permitted Primes must release retainage when the subcontractor’s work (according to their contract) is completed Incremental or monthly progress payments may constitute incremental acceptance by the recipient To assure accepted work, subcontractors must submit acceptable documentation to the prime.
13
Monitoring Mechanisms
Recipient must have procedures to assure compliance by all program participants How will Recipient know: PP clause is in contract language Date prime is paid Date when subcontractor is paid When a contract is under dispute What is being asked of the prime/sub for data collection What if they don’t comply
14
Why accurate/timely data is important
If recipient does not have a way to provide oversight of all firms on the project then monitoring is really based on complaints Contract language must require the prime to submit information on all subcontractors The firms are responsible for verifying they have been paid What if they don’t verify their payments? Is there a cure period?
15
Dispute Resolution Process (DRP)
DBE Program Plan should describe the process the recipient uses to resolve disputes Having a DRP process that is enforced resolves the disputes effectively and efficiently Disputed work does not fall under the PP provisions since it represents work which not yet accepted Drawn out disputes puts small businesses out of business!
16
Contract Remedies or Sanctions
Enforcement is expected since non-compliance with PP is considered a breach of contract Examples of penalties: Terminating the contract Withholding progress payments Assessing sanctions Disqualifying contractor on future federal contracts Withholding compliance points (P3 multi year contract) When – who – cure period? -
17
Relying on Complaints Recipients oversight process and assurance of compliance with PP CANNOT rely solely on complaints or notifications from subcontractors Unpaid subcontractors are reluctant to complain for fear of retaliation Recipient must take affirmative steps to monitor and enforce prompt payment and retainage requirements Must be proactive – waiting for complaint is reactive Significant problem in the field
18
Processing Complaints
All firms on the project should be aware how to file a complaint (with the public agency) Recipient must investigate (doesn’t mean ask the prime to resolve) Recipient must provide a timely response – no more than the time to promptly pay sub If the recipient does not respond to the unpaid sub, the sub can contact the FHWA. (this is not a good sign!)
19
What is acceptable work?
Payment is required only for satisfactory completion of the subcontractor’s work Check your standard specifications to see the definition of acceptable/completed work If work has been paid for by the recipient to the prime then the work has been accepted If the prime has been paid, then the subcontractors providing any work under that payment must be paid
20
Advice to Recipients Review your DBE Program Plan and assure all provisions of PP/Retainage requirements are included Assure the elements of your DBE Program Plan are reflected in Standard Specifications and in contract language Assure internal oversight procedures are aligned with DBE PP Include training on PP in your DBE Supportive Services program Provide training to oversight staff Reach out to subcontractors – be assessable Perform PP audits on larger projects Go back to slide 7
21
Advice to Prime Contractors
Compliance with PP will save time and money Assure all subs understand their responsibility of acknowledging payments Execute DRP as soon as dispute is evident Major projects (>$500M) contracted under D-B typically allows for tiering of subcontracting – make sure all subs know their responsibility under PP
22
Advice to Subcontractors
Read your contract before signing! How/when you are paid is super important Make sure you understand how to submit payment data Make sure you understand the dispute resolution process Make sure it contains the prompt payment/release of retainage clause that binds the prime to pay at the sub at most 30 days after they are paid Know who the oversight agency is
23
Real Life! Goethals Bridge Replacement (NY/NJ)
D/B, P3, multiple layers of subcontracting (tiering) Web-based electronic system for data Recipients procedures of oversight – appeared to be great Contract language – weak (comply with 49 CFR 26) What could go wrong?? Web-based system Flags Disputed work was beginning After resolution payments still not made Not all firms were entered into database Firms were confused on system – (were you paid??) Firms waited until they had to get a loan to stay solvent Work
24
Yikes! 3 significant events of non-compliance of prompt payment
All started with disputed work Significant number of firms were not in database Recipient was not aware of late payments Tiering is very difficult for recipient to monitor Tiering is very difficult for prime to monitor Prompt payment issues threatened delay of the project Sanctions included with holding TIFIA dispursement
25
Solutions! Recipient changed their oversight procedures
Checked for PP clause in all contracts they were aware of Created an outreach to known subcontractors Asked known subcontractors if they have subcontracted and the names of those firms list grew On-site reviews (CUF and wages) also asked if firm was subcontracting and if they have heard of any issues with payments Prompt payment audits
26
More Solutions! Prime Contractor
Gave training on electronic data collection system to all subcontractors once PP issues were discovered Made Improvements to standard subcontract provisions relating to prompt payment Required subcontractors and suppliers to acknowledge that they are aware of their prompt payment obligations Improved prompt payment project controls
27
Watch out for…. Project civil rights data collection is not just for DBEs The term “subcontractor” – could mean for some STAs just on-site firms No relationship between recipient and subcontractor… Doesn’t matter Reluctance of Prime or subcontractor to share project/contract information (see 49 CFR (c)) Tiering of subcontracting Issues grow exponentially on major projects
28
Best Practices Use electronic system on larger projects
Flags of late payments If contract language is clear and well thought out, onus is put on contractor(s) Payment data is accurate, timely and complete Good relationship between recipient and subcontractors Training! By STA to oversight staff By prime to subs
29
Resources 49 CFR 26 – specifically 26.29 USDOT DBE Q&As
February 2, 1999 DBE Final Rule USDOT DBE Q&As Clarification issued in 2016 “Prompt Payment Section Sample Template” (posted 4/5/18) – Issued by USDOT A fill in the blanks template But specific details for monitoring mechanisms, issuing
30
Christine Thorkildsen
Thank You! Christine Thorkildsen FHWA New York Division FHWA Civil Rights HQ