26. January 2013 Erik Skjelbred, Snr VP Statnett

Similar presentations


Presentation on theme: "26. January 2013 Erik Skjelbred, Snr VP Statnett"— Presentation transcript:

1 26. January 2013 Erik Skjelbred, Snr VP Statnett
The Norwegian experience of interconnectors to Europe - the future is uncertain, but electric 26. January 2013 Erik Skjelbred, Snr VP Statnett

2 Established 1992 - Norwegian Transmission System Operator (TSO)
Owns and operates the Norwegian main grid 950 employees Owns and operate all major interconnections from Norway to five countries including 4 HVDC subsea cables

3 Our mission Security of supply Value creation
Support climate solutions

4 CAPEX 50-70 bill NOK in coming 10 years period
The next generation national grid - and further development of market design 2013 2030 420 kV 300 kV <300 kV CAPEX bill NOK in coming 10 years period

5 The Nordic power system - Co-operation and exploiting the value of differences
hydro thermal/ nuclear wind wet Seasonally dry hydro thermal/ nuclear wind MUCH WIND LESS WIND Situations hydro thermal/ nuclear wind RESERVES Operational reserves Security of supply Climate Value creation

6 Trade is the base for interconnectors

7 Trade is the base for interconnectors

8 Balanced development of interconnectors
NO SE Fenno-Skan 1-2 Samnanger Sima Kvilldal NorthConnect Tonstad Feda Kristiansand Peterhead NSN Sk 1-3 Eastern Link Sk 4 Kontiskan Lindome V. Hastings Nybro Stämö Hunterston NorNed Tjele Germany DK Hawthorn Pit Moyle Esbjerg NordBalt Storebælt Blyth Kruseberg SwePol IE Western Link Baltic Kontek Slupsk Wierzbleçion Rush East-West Cobra Deeside Herrenwyk Bentwisch GB Brunsbüttel Produksjonsmiks er hentet fra Eurelectrics 2010 Wilhelmshaven Eemshaven PL NL DE BritNed Maasvlakte Isle of Grain Nemo Sellindge IFA Zeebrugge Mandarins BE FR CZ

9 Large increase in interconnector capacity
Production capacity [MW] Transfer capacity [MW]

10 Challenging operational situations to be handled
Large power flows to be switched daily Import in low load situations to be handled operationally A strong grid and flexible production capacity to be in place ahead of interconnector operation

11 Project anchoring necessary
Germany in 2018 Great Britain in 2020

12 Key aspect - a balanced development
Environmental issues Climate Environment and settlements Security of supply Daily operations Energy/hydro balance Value creation Grid cost/tariff Producers Consumers National economy

13 Harmonised European Regulation
More harmonized European regulations Market design will be further developed Market coupling - one common auction will determines prices and flows

14 Norwegian interconnectors has…
improved security of supply gained national value improved climate solutions - the future is uncertain, but electric