1 projects update ATLANTA district
Northeast Texas Transportation Summit November 1, 2018

2 Projects Under Construction Atlanta District Funded (Blue)
# Roadway Limits 1 LP 375 Bob Hope to US 62 (Montana) 2 I-10 Zaragoza to Eastlake 3 SH 20 LP 375 to Padres 4 LP 375 Zaragoza POE to North Loop 5 Old Hueco Tanks North Loop to I-10 6 I-10 Mesa Park Frontage Road 7 US 54 Hondo Pass to LP Main Lanes 8 US 54 Hondo Pass to LP Frontage Roads 9 LP 375 State Park Entrance to US 54-Rehab 10 LP 375 Zaragoza to Montwood Intersection Partially Funded (Green) 11 LP 375 Direct SPUR 601 12 LP 375 Zaragoza POE to Bob Hope 13 FM North Loop to I-10 14 I-110/US 54 Direct Connectors: I-10 to LP 375 Unfunded (Red) 15 LP 375 Dyer to US 62(Montana) 16 US 62 Global Reach to LP375 17 US 62 LP 375 to Zaragoza 18 FM 659 Sunfire to US 62 19 FM 659 North Loop to I-10 20 FM 659 I-10 to LP 375 SPUR 601 Airport Road to LP 375 Northeast Parkway LP 375 to New Mexico 404 I-10 Airway to Viscount

3 US 259 at the Red River Scope: Replace bridge and approaches (Joint project with Oklahoma) Construction Cost: $11.8M Project Length: 1.2 mi. Construction Let Date: August 2014 Estimated Completion Date: Spring 2019

4 Titus County – US 271/FM 3417 Interchange South of Mt. Pleasant
Limits: 0.7 mi N of FM 3417 to 0.3 mi S of FM 3417 Scope: Construct grade separation and approaches on 4-lane highway Construction Cost: $12.2M Project Length: 1.1 mi. Construction Let Date: May 2017 Anticipated Completion Date: Jan 2019

5 Titus County – US 271 Bridges at Ripley Creek and Ripley Creek Relief
Limits: At Ripley Creek and Relief Scope: Replace Bridges and Approaches Construction Cost: $8.9M Project Length: 1.1 mi. Let Date: June 2017 Anticipated Completion Date: Fall 2019

6 Rural Projects Under Development Atlanta District Funded (Blue)
# Roadway Limits 1 LP 375 Bob Hope to US 62 (Montana) 2 I-10 Zaragoza to Eastlake 3 SH 20 LP 375 to Padres 4 LP 375 Zaragoza POE to North Loop 5 Old Hueco Tanks North Loop to I-10 6 I-10 Mesa Park Frontage Road 7 US 54 Hondo Pass to LP Main Lanes 8 US 54 Hondo Pass to LP Frontage Roads 9 LP 375 State Park Entrance to US 54-Rehab 10 LP 375 Zaragoza to Montwood Intersection Partially Funded (Green) 11 LP 375 Direct SPUR 601 12 LP 375 Zaragoza POE to Bob Hope 13 FM North Loop to I-10 14 I-110/US 54 Direct Connectors: I-10 to LP 375 Unfunded (Red) 15 LP 375 Dyer to US 62(Montana) 16 US 62 Global Reach to LP375 17 US 62 LP 375 to Zaragoza 18 FM 659 Sunfire to US 62 19 FM 659 North Loop to I-10 20 FM 659 I-10 to LP 375 SPUR 601 Airport Road to LP 375 Northeast Parkway LP 375 to New Mexico 404 I-10 Airway to Viscount

7 Bowie County – SH 8 Bridge Replacement at Lake Wright Patman
Limits: At Sulphur River and Relief Scope: Replace two existing 2-lane bridges across Lake Wright Patman to meet current standards Design Status: Finalizing design plans Estimated Construction Cost: $25.8M (funded) Project Length: 1.9 mi. Current Letting: June 2021 (requesting to move to April 2019)

8 Titus County – US 271 Bridge Replacements
Limits: At Dickson, Big Slough, White Oak Creek and White Oak Creek Relief Scope: Replace bridges and approaches Design Status: Finalizing design plans Estimated Construction Cost: $17.8M (funded) Project Length: 1.8 mi. Current Letting: April 2020

9 Titus County – US 271 Widening North of Mt Pleasant
Limits: From Red River County Line To FM 1734 Scope: Reconstruct 2 lane roadway to 4 lane divided (Interim Super 2) Design Status: Planning Estimated Construction Cost: $50M Project Length: 15.3 mi. Proposed Ready to Let: September

10 Bowie County – US 82 Widening From IH 30 to DeKalb
Segment One: SH 98 to east of IH 30 Project Cost $ 8.0M mi. Segment Two: FM 1840 to SH Project Cost $18.6M 8.7 mi. Segment Three: US 259 to FM Project Cost $19.2M mi. Scope: Widen existing 2-lane highway to 4-lane divided Design Status: Schematic & Environmental Proposed Ready to Let: September 2022; Segment One funded

11 Bowie County – US 82 From Red River County Line to US 259
Limits: From Red River County Line to US 259 Scope: Widen existing 2-lane highway to 4-lane divided (Interim Super 2) Design Status: Schematic & Environmental Estimated Construction Cost: $22.2M Project Length: 6.5 mi. Proposed Ready to Let: September

12 Texarkana MPO Projects Under Development Atlanta District
Funded (Blue) # Roadway Limits 1 LP 375 Bob Hope to US 62 (Montana) 2 I-10 Zaragoza to Eastlake 3 SH 20 LP 375 to Padres 4 LP 375 Zaragoza POE to North Loop 5 Old Hueco Tanks North Loop to I-10 6 I-10 Mesa Park Frontage Road 7 US 54 Hondo Pass to LP Main Lanes 8 US 54 Hondo Pass to LP Frontage Roads 9 LP 375 State Park Entrance to US 54-Rehab 10 LP 375 Zaragoza to Montwood Intersection Partially Funded (Green) 11 LP 375 Direct SPUR 601 12 LP 375 Zaragoza POE to Bob Hope 13 FM North Loop to I-10 14 I-110/US 54 Direct Connectors: I-10 to LP 375 Unfunded (Red) 15 LP 375 Dyer to US 62(Montana) 16 US 62 Global Reach to LP375 17 US 62 LP 375 to Zaragoza 18 FM 659 Sunfire to US 62 19 FM 659 North Loop to I-10 20 FM 659 I-10 to LP 375 SPUR 601 Airport Road to LP 375 Northeast Parkway LP 375 to New Mexico 404 I-10 Airway to Viscount

13 Bowie County – IH 30 Added Capacity Project
Limits: From 0.6 mi W of FM 989 to Arkansas State Line Scope: Widen existing Interstate from 4 lanes to 6 lanes Design Status: Finalizing design plans Estimated Construction Cost: $61.3M (Funded) Project Length: 5.9 mi. Current Scheduled Letting: May 2020

14 Bowie County – IH 30 Frontage Roads
Limits: From FM 3419 to FM 989 Scope: Construct One-Way Frontage Roads, Entrance & Exit Ramps & Turnarounds Design Status: Finalizing design plans Estimated Construction Cost: $20.4M (funded) Project Length: 3.0 Mi. Current Scheduled Letting: May 2020

15 Bowie County – US 82 and FM 989 Added Capacity Projects
US 82 from IH 369 to FM 989 Scope: Widen existing 2-lane highway to 4-lane divided highway Design Status: Schematic & Environmental Estimated Construction Cost: $29.5M Project Length: 2.5 Mi. Proposed Ready to Let: September (partially funded) FM 989 from IH 30 to US 82 Scope: Widen existing 4-lane undivided highway to 4-lane divided highway Design Status: Schematic & Environmental Estimated Construction Cost: $10.8M Project Length: 0.8 Mi. Proposed Ready to Let: September 2022 (funded)

16 Bowie County – US 67 Added Capacity Project
Limits: From FM 989 to FM 2148 (S) Scope: Widen existing 2-lane divided highway to 4-lane divided Design Status: Schematic & Environmental Estimated Construction Cost: $23.4M Project Length: 3.1 mi. Proposed Ready to Let: September (partially funded)

17 Bowie and Cass Counties – IH 369 From Texarkana to Queen City
Scope: Route Study to upgrade US 59 to Interstate Standards from Texarkana to Queen City Status: Route Study completed in September 2018 Moving Forward: Two projects/planning phase US 59 from I-369 to FM 2148 (4.6 mi) Estimated Construction Cost: $328M US 59 from FM 2148 to FM 2327 (11.3 mi) Estimated Construction Cost: $263M

18 Questions