Download presentation
Presentation is loading. Please wait.
Published byHector Parrish Modified over 6 years ago
1
450 GeV Initial Commissioning with Pilot Beam - Beam Instrumentation
LHCCWG 5th April 2006 Rhodri Jones (CERN – AB/BI)
2
Instrumentation – the essentials
From Chamonix 2006 Sector test & first turn Screens, BPMs, fast BCT, BLMs Circulating beams at 450 GeV BPMs, DC BCT & lifetime (fast BCT) , BLMs Tune, chromaticity & coupling Emittance: wire scanners. Snapback and Ramp Continuous Tune, Chromaticity & Coupling Orbit (+ feedback) BLMs to beam interlock controller etc. Continuous emittance monitoring: synchrotron light LHCCWG, April Rhodri Jones (CERN - AB/BI)
3
BPM System at 450GeV Already commissioned (injection & first 200 turns) acquisition chain asynchronous mode most polarity errors found during threading & first turn measurements Steps after RF capture “time-in” the BPM system for bunch tagging Set phase with respect to bunch for each monitor Set turn clock with respect to end of dump gap for each monitor is the pilot always in slot 1? Requires BST start orbit acquisition at 10Hz Verify coherence of orbit, multi-turn and post mortem data Estimate ~4hrs if all goes well! LHCCWG, April Rhodri Jones (CERN - AB/BI)
4
BPM System at 450GeV Next Steps calibrate the BPM system
All monitors & orbit correctors - a la TI8 ~30secs per COD (530 CODs per plane) ~9hrs for all Accuracy will depend on accuracy of optics model! Pre-requisite for orbit feedback Finer calibration for interlock BPMs in LSS6 & BPMs at injection Pts. Required to accurately set TCDQ etc. First attempt at orbit feedback? Required before we start to use collimators? Controller tested without beam Optimise closed loop gain (~1hr beam time) LHCCWG, April Rhodri Jones (CERN - AB/BI)
5
BLM System at 450GeV Already Commissioned
Hardware functionality & detector availability First Adjustment of Thresholds Initially set as factor 3 below estimated quench level at 450GeV Based on simulations lab heating test measurements (SM18) possible sector test data Thresholds adjusted either on a Quench & learn basis if too high Dump & learn basis if too low Threshold change procedure under discussion in MPWG At 450GeV fast loss damage level is factor 1000 above quench level No risk of damaging components LHCCWG, April Rhodri Jones (CERN - AB/BI)
6
BLM Threshold Level Estimation
LHCCWG, April Rhodri Jones (CERN - AB/BI)
7
BCT System Commissioning
Already commissioned BCTFR (fast BCT) response to single pass (injection) and circulating non-captured beam Circulating beam at 450GeV First check of DCCT response Cross calibration between the 2 DCCTs & 2 BCTFRs Beam presence flag and beam safe flag for early running Beam presence detected using simple comparator on BCTFR Safe Beam flag derived 1Hz intensity measurements of BCTDC (software) Commissioned at this stage Fast Beam Loss Rate Monitoring MPWG require measurement of loss of protons within a ms BCTFR response will depend on % of bunch intensity lost Loss of for 43 nominal bunches 7% change in bunch intensity (OK) Loss of for 2808 nominal bunches 0.1% change (below noise limit) NOT commissioned at this stage LHCCWG, April Rhodri Jones (CERN - AB/BI)
8
Early LHC BCT System Performance
Measurement Mode Beam type Accuracy/ Resolution Fast BCT (BCTFR) DC BCT (BCTDC) Injection Pilot bunch ±20% / ±20% ±109 (OK) N/A Nominal bunch ±3% / ±1% ±3·109 / ±109 Circulating Beam (>200 turns) ±10% / ±10% ±0.5·109 1mA (on 10mA) (resolution ~2-10mA) ±1% / ±1% 2mA (on 180mA) (limit for short int time) 43 pilot bunches 2mA (on 390mA) Lifetime 10% (10hrs/1min) 10% (30hrs/10sec) LHCCWG, April Rhodri Jones (CERN - AB/BI)
9
Tune, Chromaticity & Coupling
Day 1 with kicked beams and classical motion analysis Commission MKQ Base Band Tune (BBQ) system for tune & coupling Optimisation of gains & time constants Head-tail system for chromaticity Verification of chromaticity with dp/p variation Commission chirp excitation using the transverse damper Allows faster rep rate if required BBQ system + chirp generation will replace BOSC as Standard Tune measurement for SPS in 2006 All hardware & analysis software should therefore be operational in the LHC as soon as we have beam LHCCWG, April Rhodri Jones (CERN - AB/BI)
10
Tune, Chromaticity & Coupling
PLL tune tracking (US-LARP) Also based on BBQ acquisition Separate system from standard kicked tune system Set-up in parallel to single kick Requires dedicated kicker BQK (if installed) or Damper Question: Do we go all out for tune and coupling feedbacks? If so, then this is the time to commission them Coupling control is critical for orbit & tune feedbacks Spending some time here to commission these systems early on may significantly reduce the time required for ramp development LHCCWG, April Rhodri Jones (CERN - AB/BI)
11
Coupling Feedback at RHIC (2006)
LHCCWG, April Rhodri Jones (CERN - AB/BI)
12
Tune & Coupling Feedback at RHIC (2006)
LHCCWG, April Rhodri Jones (CERN - AB/BI)
13
Feedback using the PLL tune system
Tune feedback requirements Stable PLL tune measurement system Knowledge of correction quad transfer functions already known from initial tune corrections Implementation of feedback controller Coupling feedback requirements Knowledge of skew quad transfer functions Chromaticity feedback requirements RF frequency modulation All of these will require dedicated beam time for testing the control loop response and the final closing of the loop. LHCCWG, April Rhodri Jones (CERN - AB/BI)
14
Measuring Beam Size at 450GeV
Wire Scanners (BWS) Operational Synchrotron light monitor (BSRT) Requires undulator to be ON Cross calibration with wirescanner Requires “stable” beams Ionisation profile monitor (BGI) Verification of bump closure of BGI compensators Should be negligible even at 450GeV Requires pressure bump for pilot bunches if nominal vacuum LHCCWG, April Rhodri Jones (CERN - AB/BI)
15
Abort Gap Monitor (BSRA)
Requirement – detect at 10% of quench level At 450GeV : detection of 4×109 charges/100ns within 100 ms At 7TeV : detection of 6×106 charges/100ns within 100 ms Protons Gated photomultiplier will look at synchrotron light using same light source as synchrotron light monitor Either gated over entire 3ms abort gap or in 30, 100ns time slots Single pilot bunch will allow verification and calibration of photon production to proton number Estimate ~300 photons / 100ns / turn at 450Gev May require tunnel intervention to change light splitting ratio between BSRT and BSRA Should be commissioned before we increase intensity Check of threshold Check of timing Check of interlock (BIC?) LHCCWG, April Rhodri Jones (CERN - AB/BI)
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.