Construction Engineering Change Order - 2 Prof. Ralph V. Locurcio, PE
CVE 4070 Construction Engineering Change Order - 2 Prof. Ralph V. Locurcio, PE
2
Change order cost estimate…
Study the plans Organize your estimate Determine critical dimensions Determine critical materials & methods Determine take off quantities Calculate the cost of each quantity Add overhead & profit Negotiate with the contractor
3
Determine dimensions…
4
Foundation excavation-1…
5
Foundation-2… Excav
6
Masonry walls… W8 12”CMU 8” CMU Insul Brick W9 W1 W7 W4 W2 W3/W6 W5
7
Floor slab… FS-1 FS-2