Presentation is loading. Please wait.

Presentation is loading. Please wait.

Connecting small renewable energy generators to the grid in Thailand: case studies & technical requirements Renewable Energy Forum Thursday, 28 October.

Similar presentations


Presentation on theme: "Connecting small renewable energy generators to the grid in Thailand: case studies & technical requirements Renewable Energy Forum Thursday, 28 October."— Presentation transcript:

1 Connecting small renewable energy generators to the grid in Thailand: case studies & technical requirements Renewable Energy Forum Thursday, 28 October 2004 BITEC Bangna, Bangkok Chris Greacen Palang Thai

2 Outline Very Small Power Producer (VSPP) examples
Solar Wind Biogas Technical requirements for interconnection

3 VSPP As Khun Rangsima has discussed, SPP and VSPP regulations allow small renewable energy power producers to sell electricity to the grid. Generators have to use renewable energy and must be less than 1 MW.

4 Grid interconnection of small scale renewable energy
Here’s the way it works, using solar electricity as an example. Renewable energy source produces electricity. Equipment processes that electricity so that it is suitable for interconnection to the grid. Some electricity is used inside the facility for building loads. Other electricity produced goes to the grid

5 Biogas from Pig Farms Reduces air and water pollution
Produces fertilizer Produces electricity Biogas from Pig Farms

6 Biogas from Pig Farms As of Jan 2004: 4 farms legally connected
Potential for hundreds of farms 5000 pigs  $31 / day elec.

7 Grid interconnection at pig farm

8 100 kW Wind turbine Part of environmental training center
ReCycle Engineering, Chonburi

9 ReCycle Engineering

10 Community micro-hydro
Mae Kam Pong village, Chiang Mai 40 kW Community cooperative Expected gross revenues: 30,000 baht/month

11 40 kW micro-hydro generator at Mae Kam Pong

12 Korat Waste to Energy - biogas
Uses waste water from cassava Removes 99% of COD Produces gas for all factory heat + 5 MW of electricity

13 Korat Waste to Energy - biogas
3 x 1 MW Jenbacher gas generators

14 Technical requirements – why?
Utility is responsible for ensuring reliable, safe electricity for customers. Safety for workers. System designed for one-way flow of electricity. …but should also not impose unreasonable costs or other barriers to interconnection

15 Technical requirements – what?
Must not island Voltage (PEA): 19.8kV – 24.2kV (nominal = 22 kV) Frequency: 50 Hz +/ Disconnect within 0.1 sec Power factor: >0.85 (This list not complete.)

16 Technical requirements – relays
59/ Overvoltage and undervoltage 50/51, 50N/51N Phase & ground overcurrent 59N Zero sequence overvoltage 67/67N Directional & gnd overcurrent Over/under frequency Synchronizing check

17

18 Price of high voltage breaker – 1. 7 million baht
Price of high voltage breaker – 1.7 million baht. Low side only 450,000 baht.

19 Integrated digital relay
BE1-GPS100 BASLER ELECTRIC BECKWITH ELECTRIC

20 Typical interconnection with integrated relay

21 Resources for VSPP www.netmeter.org
VSPP regulations (Thai) Interconnection application form Sample tariff calculations

22 For more information Contact: Tel. 02-674-2533 chris@palangthai.org

23 Aggregate Net Metering
Utility’s responsibility Village’s responsibility One of the unique features of the Thai regulations is that it allows for aggregate net metering. That is, an entire village can be metered as a single customer. This provision provides a mechanism for cooperatives like those in the microhydro villages I have studied to continue to play a role in electricity generation and distribution if the village chooses to connect. Village is metered as a single customer Collection of tariffs from individual households and maintenance of local lines is the responsibility of the REE.

24 Objectives of Power Purchase from VSPPs
To promote efficient use of domestic natural resources and reduce dependency on the use of commercial fuels To open up an opportunity for remote areas to participate in electricity generation To alleviate the government’s budgetary burden to invest in electricity generation and distribution systems

25 Applications received (as of 20 Jan 2004)
MEA PEA # of projects kW Solar PV 25 71.1 5 15.4 Biogas 1 1048 6 >750 Biomass 4 5000 Total 26 1119.1 15 >5765

26 Contracts signed (as of 20 Jan 2004)
MEA PEA # of projects kW Solar PV 1 3.1 Biogas 4 ? Biomass 3 4000 Total 8 >4000

27 Sticking points… Expensive interconnection requirements
VAT tax issue unresolved Concession by Department of Energy Business, Ministry of Energy Lack of awareness among potential customer generators

28 Today's Central Utility Tomorrow's Distributed Utility?
Central Generation Central Generation Wind Remote Loads Genset Fuel Cell Battery Customer Efficiency PV Customers 28 © Distributed Utility Associates, Used with Permission


Download ppt "Connecting small renewable energy generators to the grid in Thailand: case studies & technical requirements Renewable Energy Forum Thursday, 28 October."

Similar presentations


Ads by Google