CITE tests for and HMA-T Phase 2 Progress Meeting

Similar presentations


Presentation on theme: "CITE tests for and HMA-T Phase 2 Progress Meeting"— Presentation transcript:

1 CITE tests for 06-131 and 07-038 HMA-T Phase 2 Progress Meeting
26 November 2008, Hoeilaart Marie-Lise VAUTIER, IGN Slide 1

2 Toc Work performed Work planned Schedule Issues and concerns Slide 2

3 Work performed WP0 – Management WP1 – Improve P&P
Meetings & telecons: KO meeting, September telecon Reporting WP1 – Improve P&P HMAT-TN-0001-IGN HMA-T Phase 2 Testing Policy, Issue 1, 25/08/2008 Defines the ATS and ETS development process for HMA-T Catalogue protocols Specifies input, output, context, resources of the process Slide 3

4 ATS and ETS development process
Slide 4

5 Work has not started yet
Work performed WP2 – CITE Tests for OGC WP3 – CITE Tests for OGC Work has not started yet Slide 5

6 Work planned WP0 – Management WP1 – Improve P&P WP 2 & 3 – CITE tests
Attend meetings and telecons WP1 – Improve P&P Initiate discussions with Infoterra on how to proceed with IGN’s Testing Policy and Infoterra’s Guidance on defining ATS Develop an ATS template based on the other partners’ ATS layout WP 2 & 3 – CITE tests Develop ATS and CTL test scripts for OGC and OGC Submit ATS to EO EP and CIM EP SWG in OGC Submit ETS to OGC CITE SC Slide 6

7 Proposed schedule WP0 – Management WP1 – Improve P&P
Next meetings, telecons : ??? WP1 – Improve P&P Discussions with Infoterra Next week in OGC TC ? Telecon ? 30/12/2008 – Updated Testing Policy document with ATS template and incorporating Infoterra document Slide 7

8 Proposed schedule WP2 & 3 Constraint : the ATS must be ready for inclusion into EO EP and CIM EP standards by March 2009 30/01/2009 (AR1) - ATS for OGC and OGC 30/03/2009 (AR2) – CTL test scripts for OGC and OGC 30/03/2009 – 30/04/2009 (telecon) – Deployment 30/04/2009 – end 2009 – Support Slide 8

9 Initial schedule Kick-off meeting Final presentation AR 2 AR 1
2008 2009 July August Sept. October Nov. Dec. January February March April May June July August Sept. Oct. Kick-off meeting Final presentation AR 2 AR 1 WP0 – Technical Management WP1 – Test P&P 2.4 Support 3.4 Support WP2 – Conformance tests for OGC 2.1 ATS 2.2 ETS WP3 – Conformance tests for OGC 3.1 ATS 2.3 Deployment and validation 3.2 ETS 2.3 Deployment and validation Slide 9

10 Proposed schedule WP2 – Conformance tests for OGC 06-131
WP0 – Technical Management 2.1 ATS 2.2 ETS 3.2 ETS 3.3 Deployment and validation 2.3 Deployment and validation July June May April March February January Dec. Nov. October Sept. August 2008 2009 WP1 – Test P&P 2.4 Support 3.4 Support Kick-off meeting Final presentation AR 2 AR 1 …. 3.1 ATS Slide 10

11 Issues Delays in WP2 & WP3 Reason : temporary lack of resource till the end of January 09 Need to formalize this delay ? Slide 11

12 RIDs YC-71 : Section to be added with template to be followed by all ATS documents from subcontractors. Should be an identical template for all. To be included in next version (end of Dec 08) YC-72 : "reference source not found": correct link in document on page 11 and 12. To be corrected in next version (end of Dec 08) YC-78 and 79 : The content of the Infoterra "Guidance on defining ATS" should be merged with the current document. See also YC-71. To be discussed with Infoterra Outcome in next version (end of Dec 08) Slide 12