A15-08 Badger Tunnel Ranger
AS Automaatio- ja systeemitekniikan projektityöt Petri Manninen, Andreas Müller, Sami Talka Kon Mechatronics Project Ville Hiltunen, Jouni Ilves, Sami Puustinen, Quinton Weaver Project Plan | Badger Tunnel Ranger
2
Introduction - Motivation
YLE wants to make a nature document about badgers Ulos luontoon -series Around viewers Robot for filming badgers’ nest and tunnels Mechatronics team: mechanical and electronical design Automation team: software design Video material has scientific value No video material before from inside nest Badgers ->outside the den have already been filmed -> are mainly unexplored Nobody knows the real size of the den Trying to keep the disturbance for the badger very low expose badger -> create awareness of these animals in publis Project Plan | Badger Tunnel Ranger
3
Introduction - Requirements
Badger tunnels Narrow (around 30x30cm) Can be 6 meters deep Have many floors Steep slopes Rough terrain (roots, wet dirt) Recorded and live view outputs HD TV quality Mapping system Robust Retrievable Cannot damage badger tunnel Robust to withstand environment and attacks from the badgers Project Plan | Badger Tunnel Ranger
4
Project goals Remote controlled robot
Able to navigate and document badger tunnels Design system to control navigation and filming of the tunnels Keep the device small enough to navigate the tightest tunnels Utilize a cable to tether, power, and recover the robot Design extensible robot platform for multipurpose use 3D modelling of the badger tunnel Project Plan | Badger Tunnel Ranger
5
Schedule Project Plan | Badger Tunnel Ranger
Listing requirements and goals -> System analysis -> Software, Hardware, Mechanical requirements analysis Milestone: Mission statement = List of Systemrequirenments Concepting -> Software, Hardware, Mechanical concepts Final concept = Complete system architecture Designing ->Software, Hardware, Mechanical design Manufacturing & Implementation -> Software, Hardware, Mechanical consturction -> Software, Hardware, Mechanical integration -> Software, Hardware, Mechanical test -> System integration Milestone: Prototyp ready for testing Testing and fixing -> System test -> check up with requirenments continous documentation Project Plan | Badger Tunnel Ranger
6
What kind of problems might occure?
Robot or cable can get stuck We don’t know what there is inside the tunnels How to get it back without damaging tunnels? We might disturb a badger It can attack and break the robot Field testing might be difficult Badgers sleep in their tunnels during winter Lighting for good quality filming Reducing the size Cable: friction of the cable increases robot should be powerful enough to pull the cable recovering the robot might damage the den just say: What problems have we encountered yet? -> different deadlines of the project -> define the responsibilities -> structuring the teamwork Project Plan | Badger Tunnel Ranger