Download presentation
Presentation is loading. Please wait.
Published bySherilyn Logan Modified over 6 years ago
1
Lincoln Common Redevelopment Construction Update
2
Project Team Developers Architects GENERAL contractor
3
AGENDA - UPDATE CURRENT PROGRESS OF LINCOLN COMMON
- PROVIDE NOTICE OF SCHEDULE DELAY IN ACCORDANCE WITH THE COMMUNITY AGREEMENT - SOLUTION MOVING FORWARD
6
Current Construction Status
- Building enclosure in progress - Sidewalk re-Installation in progress - Plaza areas (Sitework) in progress - Residential interior build-out in progress TO DATE THE SCHEDULE OF THE ABOVE TASKS HAVE BEEN DELAYED BY 43 DAYS OF INCLEMENT WEATHER. Current 8am start time has resulted in loss of manpower on-site.
7
Current Logistics and Planning
Trucks and Deliveries: restricted to truck routes Current Logistics Require Site Access Via Orchard St. Site will be secured at all times Communication: Website showing schedules, extended work hours or street closures Be
8
Phasing Plan Phase 9 - Site Work Sidewalks and Curb North Side of Lincoln 10.1.1
9
Estimated Time Frame
10
Current Construction Status
PLAN MOVING FORWARD CONSISTENT WITH THE COMMUNITY AGREEMENT: Interior building construction activities will begin at 7:00am with manpower access to the buildings via the exterior hoists. Exterior metal panel work will start at 7:00am to get back on schedule. Site work construction behind the construction fence will begin at 7:00am to get back on schedule. Work schedule for the above will be Monday thru Sunday. No excessive noise generating activities to begin prior to 8:00am. No deliveries prior to 8am.
11
Questions Questions? Schedule needs approval from Belmont Village, per Denice
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.