The Rossway Safeway Roof Safety Protection system is installed on top of roof purlins. The Rossway Safeway system consists of a platform deck with handrail and toe board to one side, the leading edge and fall protection frames to the other working edge Roof Plan Roof section Rossway Safeway system
2
The first roof tier is placed with crane or other suitable lifting device. Access to de-sling and fix panel is gained from Rossway Safeway system Roof Plan Roof section
3
The Rossway SafeEdge roof perimeter edge protection system is fitted on the first composite panel installed. This provides perimeter fall protection for operatives working at roof level. Rossway SafeEdge Roof Plan Roof section
4
Rossway SafeEdge The Rossway Safeway system is moved on purlin trolleys the width of a roof panel Roof Plan Roof section
5
Rossway SafeEdge The next tier of roof panels are laid Roof Plan Roof section
6
Rossway SafeEdge Crane slings removed with access from Rossway Safeway system Roof Plan Roof section
7
Rossway SafeEdge The Rossway Safeway system is moved on purlin trolleys the width of a roof panel Roof Plan Roof section
8
The next tier of roof panels are laid Roof Plan Roof section
9
Rossway SafeEdge Crane slings removed with access from Rossway Safeway system Roof Plan Roof section
10
Rossway SafeEdge A pack of roof panels can be landed on the completed roof area. Edge protection is provided to all edges with the Rossway Safeway Roof Safety protection system to the leading edge and the Rossway SafeEdge to the perimeter Roof Plan Roof section
11
Rossway SafeEdge The Rossway Safeway system is moved on purlin trolleys the width of a roof panel Roof Plan Roof section
12
Rossway SafeEdge The next tier of roof panels are laid panels can be taken from the pack landed at roof level. Roof Plan Roof section
13
Rossway SafeEdge The Rossway Safeway system is moved on purlin trolleys the width of a roof panel Roof Plan Roof section
14
Rossway SafeEdge The next tier of roof panels are laid Roof Plan Roof section
15
Rossway SafeEdge The Rossway Safeway system is moved on purlin trolleys the width of a roof panel Roof Plan Roof section
16
Rossway SafeEdge The next tier of roof panels are laid Roof Plan Roof section
17
Rossway SafeEdge At the end of the roof the fall protection frames are removed by removing the fixing brackets on one side which enables the frames to rotate on the other side. The other side can then be released and the frame taken off with access from the platform deck. Roof Plan Roof section
18
Rossway SafeEdge With access from the completed roof…… Roof Plan Roof section
19
Rossway SafeEdge …..the platform deck and handrail can be moved on to the completed roof providing edge protection……. Roof Plan Roof section
20
Rossway SafeEdge …from the platform deck…… Roof Plan Roof section
21
Rossway SafeEdge …the final tier of roof panels are installed Roof Plan Roof section