Department Of Human Settlements Annual Performance Report For The Financial Year 2015/16 Director-General Mr. M.Tshangana
2
Structure Of The Presentation
Overview of the Departmental Performance Progress on Qualitative Outputs MTSF- Sector Performance Grants Expenditure Report Financial Matters Response and Action Plan on Audit Outcomes
3
Overall Departmental Performance Per the Tabled Plan: 74 Annual Targets 56 Targets Achieved 14 Targets Partially Achieved 4 Targets Not Achieved
4
Qualitative Outputs Achieved as at March 2016
Consolidation of the Human Settlements Development Finance Institutions has commenced - The relevant directives have been issued by Minister Sisulu and being actioned by the Department in conjunction with the NHFC, RHLF and NURCHA A tax amendment is pending that will allow for the transfer of assets and liabilities of RHLF and Nurcha into the NHFC. This allows for the operational intergation. A policy foundation for the creation of a single DFI was developed, allowing for the development of a draft business case and commencement of the process to draft a bill
5
Qualitative Outputs Achieved as at March 2016
The following policies and programme frameworks were revised for consultation and adoption and also inform the content of the White Paper currently being drafted for adoption and publication for comment: Beneficiary Allocations Policy Revision of the Pre-emptive Clause on the Sale of Subsidised Houses CRU Policy The Review of programmes in the Housing Code commenced An evaluation of the Social Housing Programme was completed An investment framework to guide human settlements development was completed for consultation and adoption.
6
Qualitative Outputs Achieved as at March 2016
A proto-type of the business intelligence dash-board developed to improve monitoring and reporting on programme A central intervention to fast track the issuing of title deeds commenced A consumer education programme was implemented with provinces and municipalities to curb illegal property sales and ensuring that consumers apprecaited socio-economic benefits and value of owning the property A programme ensured that the NHBRC enrolled all subsidised projects and monitored their construction
7
Qualitative Outputs Acheived as at March 2016
An interspherical package of support was developed, concluded and implemented in Nelson Mandela Bay Municipality A training support and incubation programme for youth and women implemented by the Department with the NHBRC, EAAB and HDA
8
Qualitative Outputs Acheived as at March 2016
The Implementation Guidelines for PHP was tabled for approval The strategy for human settlements in mining town towns developed to support the current programme interventions The revision of the guidelines for human settlements development commenced Programme and institutional support to allow for accreditation of the housing function was provided to municipalities
9
MTSF Outputs Progress as at 31 March 2016
additional households provided with adequate housing additional households upgraded Assessment and analysis of 101 catalytic projects was completed and recommended for due diligence and implementation loans issues by the Human Settlements DFI’s Three (3) municipalities pre-assessed for accreditation 463 feasibilities in informal settlements were completed in various municipalities
10
MTSF Implementation Progress as at 31 March 2016
additional affordable rental opportunities were delivered comprising: 3 480 Social Housing 21 52 CRU 6 565 through NHFC loans provided Various Provincial PHP initiatives yielded PHP units
11
Progress On Implementation of the MTSF as at 31 March 2016
MTSF TARGET 2019 ANNUAL TARGET 2015/2016 PROGRESS 2015/2016 TOTAL DELIVERED FROM 2014-MARCH 2016 households living in adequate housing through the subsidy and affordable housing segments households living in adequate housing households living in adequate housing through the subsidy and affordable housing segments households living in adequate housing through the subsidy and affordable housing segments Shortfall for 2 years : 750 000 households in informal settlements upgraded households in informal settlements upgraded households in informal settlements upgraded: HSDG: households USDG: households households in informal settlements upgraded Shortfall from : households 563 000 individual units for subsidy housing submarket provided individual units for subsidy housing submarket individual units provided for subsidy market – subsidy housing units provided Shortfall from March 2016:
12
Progress On The Implementation Of The MTSF As At 31 March 2016
MTSF TARGET 2019 ANNUAL TARGET 2015/16 PROGRESS 2015/16 TOTAL DELIVERED FROM 2014-MARCH 2016 900 Title deeds backlog eradicated pre- and post 1994 title deeds issued title deeds issued new title deeds issued to home owners new title deeds issued to home owners title deeds issued to new home owners Title deeds issued . subsidy housing units delivered between March 2016 Shortfall of Affordable housing loans for new houses in the affordable-gap housing market 110 000 loans ( FLISP and DFI supported) loans granted units produced through loans new units in the affordable housing market produced through loans granted by the DFI’s
13
Progress On The Implementation Of The MTSF As At 31 March 2016
MTSF TARGET 2019 ANNUAL TARGET 2015/16 PROGRESS 2015/16 TOTAL DELIVERED FROM 2014-MARCH 2016 50 catalytic projects implemented demonstrating spatial, social and economic integration 10 catalytic projects implemented 101 catalytic projects recommended for approval by the Minister Number of informal settlements assessed 460 informal settlements assessed In collaboration with the HDA, the National Upgrading Support Programme (NUSP) completed the assessment of 816 informal settlements in 62 municipalities. Of these 503 detailed settlement plans are being developed. The relevant appointments have been concluded and additional feasibilities and settlement plans are being undertaken.
14
Progress On The Implementation Of The MTSF As At 31 March 2016
MTSF TARGET 2019 ANNUAL TARGET 2015/2016 PROGRESS 2015/2016 TOTAL DELIVERED MARCH 2016 of hectares of well-located land rezoned and released for new developments 2000 hectares of well-located land rezoned and released for new developments 4 622 hectares of land released for new developments hectares of land released for new development s
15
Overview Of Provincial Non-Financial Performance Housing And Human Settlement Delivery Trends For The Period For The Human Settlements Development Grant 01 April 2015 – 31 March 2016 Ver: 01 June 2016
16
Delivery For April 2015 – March 2016 in relation to HSDG Targets for the Year
Note: 2015/16 delivery figures are up to end March 2016 and are preliminary. Annual Targets for 2015/16 (as per DG Memo, Planning Unit, ) 1 224 Discount Benefit Scheme outputs excluded from WC Houses/Units (Refer to Alignment slide).
17
April 2015 – March 2016 Deficit in Relation to Targets
Note: 2015/16 delivery figures are up to end March 2016 and are preliminary. Annual Targets for 2015/16 (as per DG Memo, Planning Unit, ) 1 224 Discount Benefit Scheme outputs excluded from WC Houses/Units (Refer to Alignment slide).
18
Numerical Targets and Deficits on Delivery April ‘15 – March ‘16
Note: 2015/16 delivery figures are up to end March 2016 and are preliminary. Annual Targets for 2015/16 (as per DG Memo, Planning Unit, ) 1 224 Discount Benefit Scheme outputs excluded from WC Houses/Units (Refer to Alignment slide).
19
Delivery in relation to Annual Target and Expenditure Performance
Note: 2015/16 delivery figures are up to end March 2016 and are preliminary. Annual Targets for 2015/16 (as per DG Memo, Planning Unit, ) 1 224 Discount Benefit Scheme outputs excluded from WC Houses/Units (Refer to Alignment slide).
20
Audit Improvements on the HSS Data
The figures up to March 2016 are 100% aligned with what is captured on the HSS by the Provincial Depts. Net Capture: Sites: 100% Houses: 100% Overall: 100% ( sites + houses captured)
21
Audit Improvements on the HSS Data
The figures up to March 2016 are 100% aligned with what is captured on the HSS by the Provincial Depts. 1 224 Discount Benefit Scheme outputs excluded from WC Houses/Units (Refer to Alignment slide). Net Capture: Sites: 100% Houses: 100% Overall: 100% ( sites + houses captured)
22
Comment on Partially Achieved Targets
The DFI Consolidation process is a multi-year process hence completion of a target overlaps over reporting periods The in year target on the issuing of title deeds performed poorly and measures are being put in place to allow for recovery The drafting of the policy for coherent and inclusive approach to land and regulations for land use management The evaluation of the access to the city evaluation was cancelled due to non performance by the service provider
23
Comment on Partially Achieved Targets
The upgrading of households in informal settlements - annual target was not met and required intervention measures are being considered and in place including the ring-fencing of grants for The accreditation of municipalities was partially achieved due to the fact that the approach to accreditation accreditation required revision based on practical implementation difficulties.
24
Comment on Targets Not Achieved
The bi-annual reports on property trends was not disseminated- and it was resolved that the department is collating the information through the research and policy unit and will be published accordingly The capacity building programme in programme 3 was not implemented ad the target has been re-prioritised
25
Expenditure Report For The 2015/16 Financial Year
26
Expenditure by Programme: 31 March 2016
Total Allocation R' 000 Commitments Expenditure Variance % Spent 1. Administration 8 697 24 177 94% 2. Human Settlements Policy, Strategy and Planning 77 493 203 75 738 1 755 98% 3. Programme Delivery Support 1 239 45 894 72% 4. Housing Development Finance 2 99% Total 10 141
27
Operational Expenditure by Programme: 31/03/2016
Total Allocation R' 000 Commitments Expenditure Variance % Spent 1. Administration 8 697 24 168 94% 2. Human Settlements Policy, Strategy and Planning 75 884 203 74 129 1 755 98% 3. Programme Delivery Support 1 239 44 468 72% 4. Housing Development Finance 21 400 2 20 999 401 Total 10 141 70 791 90%
28
Transfer Payments: 31 March 2016
Total Allocation Expenditure Variance % Spent Grants - 100% Human Settlements Development Grant Urban Settlements Development Grant Municipal Human Settlements Capacity Grant Entities 51% Social Housing Regulatory Authority: Operational 34 560 Social Housing Regulatory Authority: Institutional Investment Grant 41 936 0% Social Housing Regulatory Authority: Restructuring Capital Grant 25% Community Schemes Ombuds Services 39 521 National Housing Finance Corporation National Urban Reconstruction and Housing Agency 61 000 Housing Development Agency 71 568 59% Departmental Transfers 11 966 9 154 2 812 76% Bursaries Scheme 8 792 7 374 1 418 84% UN Habitat 1 368 Households 1 806 1 780 26 99% Total
29
HSDG Expenditure Performance: 31 March 2016
Provinces Voted Funds Reallocated Funds Adjustment Roll Overs Total Available Year to date (1 April March 2016 Transferred Funds Spent by Provinces Variance Spent vs Total Available Spent as % of Total Available R'000 Eastern Cape - 4 192 100% Free State 47 Gauteng 23 388 99% KwaZulu-Natal Limpopo 71% Mpumalanga 70 380 56 Northern Cape 3 849 North West 2 Western Cape Total 97%
30
Milestones Which Did Not Yield New Opportunities as at 31 March 2016
Programmes Annual Targets Delivery Performance Sites Units Funds Allocated Expenditure R'000 EEDBS - 1 262 76 462 6 395 42 547 Rectification 5 739 8 251 OPSCAP Land Hectares 513 483 Disaster Relief Fund 374 3 413 Total 7 514 15 129
31
Outputs Upgrading of Informal Settlements in Mining Towns
Province Mining Towns Area Annual Targets Delivery Performance Sites Units Funds Allocated (Gazetted) Funds Allocated (As per BP Expenditure R'000 Free State Matjhabeng - 780 75 337 1 342 Total Gauteng Merafong City 615 50 000 53 009 Randfontein 136 52 000 27 508 Westonaria 1 683 1 000 60 900 1 751 Limpopo Thabazimbi 195 16 400 32 785 Greater Tubatse 610 740 36 500 398 39 394 Elias Motsoaledi 800 294 16 600 44 052 91 12 378 Lephalale 3 089 677 77 100 86 191 523 42 512 Fetakgomo 192 7 600 20 856 102 8 893 4 499 2 098 1 114
32
Outputs Upgrading of Informal Settlements in Mining Towns
Province Mining Towns Area Annual Targets Delivery Performance Sites Units Funds Allocated (Gazetted) Funds Allocated (As per BP Expenditure R'000 Mpumalanga Emalahleni 3 990 2 809 51 400 4 000 1 503 Steve Tshwete - 36 300 39 542 311 151 38 016 Thaba- Chweu 180 26 800 27 970 202 25 448 Total 2 989 4 311 1 856 Northern Cape Tsantsabane 390 22 140 37 133 16 644 Ga-Segonyana 50 13 600 15 130 218 13 150 Gamagara 43 9 800 4 923 38 4 162 Kgatelopele 4 500 2 114 3 885 Joe Morolong 238 19 544 93 50 040 59 300 494 57 385 North West Kgetleng Rivier 866 61 600 477 59 281 Madibeng 847 456 37 504 Moses Kotane 484 44 000 713 Rustenburg 2 417 1 211 1 435 915 Matlosana 966 722 73 200 1 815 3 383 4 130 4 376 Grand Total 13 945 11 841 5 746 9 182
33
Outputs Finance Linked Individual Subsidy Programme
Report as at 31 March 2016 Province Annual Targets Delivery Performance Sites Units Funds Allocated Expenditure R'000 Eastern Cape - 200 12 442 247 11 382 Free State 37 5 100 13 461 Gauteng 90 1 293 906 9 018 KwaZulu-Natal 2 000 350 81 750 458 27 062 Limpopo 300 24 900 43 25 594 Mpumalanga 100 8 700 32 1 350 Northern Cape 30 2 182 42 North West 277 23 359 Western Cape 145 6 250 411 23 901 Total 2 090 2 732 2 110 98 810
34
Outputs Rectification Programme
Report as at 31 March 2016 Province Annual Targets Delivery Performance Sites Units Funds Allocated Expenditure R'000 Eastern Cape - 2 487 3 520 Free State 370 Gauteng KwaZulu-Natal 2 273 3 102 Limpopo 500 43 500 940 Mpumalanga 37 Northern Cape 11 019 66 5 944 North West 44 998 880 19 087 Western Cape 479 11 200 276 8 064 Total 5 739 8 251
35
Provincial Operational Capital Budget
Report as at 31 March 2016 Province Annual Targets Delivery Performance 5% allocation Units Funds Allocated Sites Expenditure R'000 Eastern Cape 98 119 - 88 373 50 732 Free State 52 864 52 641 Gauteng KwaZulu-Natal Limpopo 64 194 30 938 31 617 Mpumalanga 63 258 60 344 65 049 Northern Cape 19 020 95 285 North West 51 908 52 530 Western Cape 98 756 66 773 Total
36
Outputs Disaster Relief
Disaster Relief Programme Province Annual Targets Delivery Performance Sites Units Funds Allocated Expenditure R'000 Eastern Cape - 374 470 42 974 Gauteng 40 000 KwaZulu-Natal 1 926 Limpopo 34 332 34 182 Mpumalanga 34 098 408 40 716 North West 38 507 609 44 941 Western Cape 5 077 Total 3 413
37
USDG Expenditure Performance : 31 March 2016
USDG EXPENDITURE (01 JULY MARCH 2016) Municipality Voted Funds 1 Rollover from 2014/ Total Available Funds (1+2) Actual Transfer from Voted funds 4 Spent by Metros 5 % Spent against Total Available funds (5÷3) % Spent against Transferred funds (5÷4) Unspent from Total Available Funds (3-5) % Unspent against Total Available Funds (8÷3) R'000 Buffalo City 42 403 64.6 68.5 35.4 Nelson Mandela Bay - 63.5 36.5 Mangaung 77 536 55.2 61.4 44.8 Ekurhuleni 42.9 54.3 57.1 City of Johannesburg 63.4 36.6 City of Tshwane 36 868 57.9 59.3 42.1 eThekwini 47.4 52.6 City of Cape Town 43.2 48.3 56.8 Total 52.7 56.7 47.3
38
USDG Consolidated - Financial Performance 31 March 2016
Description Allocated Budget % of Total Allocated Budget Spent by Metros % Spent Unspent funds % Unspent R'000 Land acquisition 2.8 36.5 63.5 Housing 26.6 54.2 45.8 Roads and Stormwater 13.2 50.6 49.4 Transport 10.7 55.7 44.3 Water and Sanitation 27.5 53.0 47.0 Electricity 6.0 59.6 40.4 Waste Management 3.0 67.0 33.0 Social Amenities 5.4 42.2 57.8 EPMO-Project Management Funding 21 942 0.2 17 546 80.0 4 396 20.0 Economic and Rural Development 4 232 - 100 Planning 25 835 6 694 25.9 19 141 74.1 Re Aga Tshwane 1.4 94 368 61.2 59 850 38.8 Economic Development and Planning 64 518 0.6 37 386 57.9 27 132 42.1 Office of City Manager 93 104 0.8 4 960 5.3 88 144 94.7 Spatial Planning and Urban Design 7 022 0.1 100.0 Safety and Security - Law enforcement 1 006 VAT 1.5 74 032 42.8 98 968 57.2 Total 52.7 47.3
39
MHSCG Performance - Expenditure 31 March 2016
MHSCG EXPENDITURE (01 JULY MARCH 2016) Municipality Voted Funds 1 Rollover from 2014/15 2 Total Available Funds (1+2) Actual Transfer from Voted funds 4 Spent by Municipality 5 % Spent against Total Available funds (5÷3) % Spent against Transferred funds 7 (5÷4) Unspent from Total Available Funds 8 (3-5) % Unspent against Total Available Funds 9 (8÷3) R'000 Buffalo City 9 253 - 2 328 25.2 6 925 74.9 Nelson Mandela Bay 9 847 23 235 33 082 11 943 36.1 121.3 21 139 63.9 Mangaung 9 206 954 10.4 8 252 89.7 Ekurhuleni 14 313 50 818 65 131 4 457 6.8 31.1 60 674 93.2 City of Johannesburg 16 505 59 573 76 078 4 026 5.3 24.4 72 052 94.7 City of Tshwane 12 831 16 420 29 251 2 466 8.4 19.2 26 785 91.6 eThekwini 14 342 39 980 54 322 11 359 20.9 79.2 42 963 79.1 City of Cape Town 13 703 31 580 45 283 14 216 31.4 103.7 31 067 68.6 Total 51 749 16.1 51.7 83.9
40
MHSCG – Non-Financial Performance: 31 March 2016
Category Description Voted Funds Spent By Municipalities Unspent Funds % Spent R'000 Capacity Compensation of Employees/ Salaries 36 572 79 384 31.5 Training of Staff 21 417 1 761 19 656 8.2 Workshops 400 14 386 3.5 Consultants 35 607 10 360 25 247 29.1 Professional / Technical Services 20 545 - Professional Project Management Services 3 262 Pre-Planning Mega Projects 4 415 303 4 112 6.9 Interim Capacity (Fixed term contracts) 13 336 1 151 12 185 8.6 Research 10 701 - Support Rental - External / Buildings 852 479 373 56.2 Risk Management 17 028 Management plan/business processes 1 769 Functional Planning 23 442 Operational Costs 435 83 352 19.1 Office Equipment 16 203 1 023 15 180 6.3 Systems 36 238 3 36 235 Total 51 749 16.1
41
5. Responses To Audited Outcomes 2015-16
42
Matters Raised in the Audit Opinion
Material under spending of the vote The Department materially underspent on Programme 3: Programme Delivery Support to the amount of R Adjustment of material misstatements There were material misstatements in the annual performance report which were subsequently corrected
43
Matters Raised in the Audit Opinion
Financial statements not prepared in accordance with the prescribed reporting framework as required by section 40 (1) (b) of the PFMA Contractual obligations and money owed by the department were not settled within the PFMA stipulated thirty (30) days
44
ACCOUNTING OFFICERS REPONSE REGARDING AUDIT OUTCOME
In order to address the misstatements of the performance information submitted, the management effected the required corrections and will review and conduct an internal verification process prior to submission for auditing. The department is reviewing its processes and procedures to improve quality and content control in the preparation and submission of financial statements Corrective and oversight measures have been put in place to address the stipulated thirty (30) day turn around of processing and payment of invoices – this includes the activation of receipt of invoice registers The material under spending in the National Upgrading Support Programme (NUSP) has been attended to through by improving SCM planning of programme and project planning
45
Current Initiatives To Improve Audit and Strategic Outcomes
Technical and operational capacity for programme and project planning is being improved by ensuring the organisational structure is aligned to the strategic focus areas and availability of funding The Department will through it strategic alignment process remove duplications of capacity and funding within the Department, Provinces, Municipalities and Entities, allowing for improved and increased capacity to meet key targets and outputs Improving monitoring and oversight of the sector delivery supply chain ensuring improved efficiencies and value for money Overall improvement of monitoring, evaluation and enforcement of policy and programme compliance focusing on norms and standards.
46
Current Initiatives To Improve Audit and Strategic Outcomes
The Departments is in consultation with National Treasury to improve the operational and grant funding frameworks to mitigate operational and capital budget outcomes. The Department has implemented a robust and interrogative pre and post planning and monitoring protocol with Sector Departments, Departmental Entities, Provinces, Municipalities. A series of governance, compliance and adminitsrative frameworks and monitoring tools have been implemented, in process and/or improved and includes the management performance assessment tool (MPAT), entities stakeholder compacts, audit action plan, SCM review and programme, project readiness matrix, responsive planning, implementation and monitoring structure and progressive grant frameworks.
47
“We have come a long way – Celebrating 20 Years of Freedom!”
THANK YOU “We have come a long way – Celebrating 20 Years of Freedom!”