ISPA Measure 2002 BG 16 P PE 009 WWTP Bourgas – Meden Rudnik
2
Works Contract Commencement Date: 15th May 2007
Completion Date: 31st Dec. 2009 Physical Execution: 100 % Financial Execution: 100 % WWTP became operational on 21st Dec. 2009 1 year DNP expired on 27th Dec. 2010 Performance Certificate was issued on 27th Dec. 2010 Final Payment was made on 27th Dec. 2010
3
WWTP Meden Rudnik - Completed
4
WWTP Meden Rudnik (during DNP and operation)
5
WWTP Meden Rudnik (during DNP and operation)
6
Reconstruction of the Main Collector (implemented by Final Beneficiary)
7
Reconstruction of effluent channel (implemented by ViK Bourgas)
8
Site visit by reporters of TV France 3
9
WWTP Meden Rudnik Publicity
10
Supervision Contract Commencement Date: 24th April 2007
Completion Date: 31st March 2011 Time elapsed: 100 % Financial Execution: 100 %
11
Compliance with Article 8 of the Financing Memorandum
All other conditions under Article 8 of the FM are considered fulfilled.
12
Thank you for your attention!