Presentation is loading. Please wait.

Presentation is loading. Please wait.

NEC - Compensation Events Programme & Delay Issues

Similar presentations


Presentation on theme: "NEC - Compensation Events Programme & Delay Issues"— Presentation transcript:

1 NEC - Compensation Events Programme & Delay Issues
Kings College Conference July 2005 NEC - Compensation Events Programme & Delay Issues Richard Bayfield BSc., MSc., CEng., FICE, FCIArb 18/01/2019 Richard Bayfield 1 1

2 Kings College Conference July 2005
Original Brief CE’s - Programme and Delay Issues Compensation, Delay (i.e. analysis) Analysis – examination, investigation, scrutiny… Synthesis – creation, making, fusion……. NEC – predicated on “synthesis” Traditional Contracts – emphasis on “analysis” Synthesis – pro-active – pre-empting Analysis – re-active – history (delay) 18/01/2019 Richard Bayfield 4

3 Introductory Question
Kings College Conference July 2005 Introductory Question What is the purpose of a programme? What is the purpose of a programme under the NEC? 18/01/2019 Richard Bayfield 4

4 Kings College Conference July 2005
History of Construction in 3 Slides 18/01/2019 Richard Bayfield

5 Kings College Conference July 2005
18/01/2019 Richard Bayfield

6 Industry Context and NEC
Kings College Conference July 2005 Industry Context and NEC Complexity - technical Complexity – people / organisations – intrinsic need for improved communications Fragmentation of industry Different interests Disputes arises from poor communication NEC addresses these issues at a strategic level 18/01/2019 Richard Bayfield

7 Back to Programme – who is programme for?
Kings College Conference July 2005 Back to Programme – who is programme for? Client? Contractor? Project Manager? Designer? Some one else – the delay analyst? THE PROJECT 18/01/2019 Richard Bayfield

8 Kings College Conference July 2005
Programme – purpose? Project Management – Martin Barnes – 2 rules 1. "It is only possible to manage the future". 2. "All decisions must be directed towards meeting the clients' objectives". Programme - As a tool to help manage the project / the remaining activities (the future) Programme - Encourage “what if” scenarios Programme - Pre-empting – if decision for x is delayed what is effect? 18/01/2019 Richard Bayfield

9 Kings College Conference July 2005
Programme Management. Many industries including construction have success stories going back decades - Not a new invention “….the traditional standard forms are weak on programme techniques……” Prof Capper – SCL Paper Sept 1994 “Contract” is a tool for managing risk (Prof Capper) No real difference whether programme is under NEC or not (strategically) Proper Programme Management adds value and reduces risk whatever the contract form 18/01/2019 Richard Bayfield 14

10 Kings College Conference July 2005
Programme Management There is no reason why these techniques (critical path programming) should not be applied in a consensual manner within the contract and on a real-time basis in order to generate a regularly updated analysis of employer and contractor delay periods.” - Professor John Uff QC – Are we all in the wrong job? – SCL Paper July 2001” SCL Delay & Disruption Protocol – 18/01/2019 Richard Bayfield

11 NEC Programme Clauses – 3 Time
Kings College Conference July 2005 NEC Programme Clauses – 3 Time Cl 30 – Starting & Completion Cl 31 – The Programme – requirements (31.3) CL32 – Revising the Programme Cl 33 – Possession Cl 34 – Instructions to stop / start Cl 35 – Take over Cl 36 – Acceleration 18/01/2019 Richard Bayfield

12 NEC Programme Philosophy – Accepted Programme
Kings College Conference July 2005 NEC Programme Philosophy – Accepted Programme “The programme is an important document for administering the Contract. It enables the PM and Contractor to monitor progress and to assess the time effects of compensation events including changes to the completion date.” - from Guidelines to Cl 31 i.e it is a methodology for management of the overall project - Implications? Accepted Programme – base document for assessing time and cost of CE’s 18/01/2019 Richard Bayfield

13 Assessing Compensation Event (CE)
Kings College Conference July 2005 Assessing Compensation Event (CE) Cl 63.3 – A delay to the Completion Date is assessed as the length of time that, due to the compensation event, planned completion is later than Planned Completion as shown on the accepted programme. 18/01/2019 Richard Bayfield 14

14 NEC Programme update for Compensation Event (CE)
Kings College Conference July 2005 NEC Programme update for Compensation Event (CE) Objective is anticipate the effect of the CE on the programme before it happens Completion date is then revised via the accepted programme Associated costs dealt with in advance as a a quote, not as part of an audit 18/01/2019 Richard Bayfield 14

15 NEC Programme update for Compensation Event (CE)
Kings College Conference July 2005 NEC Programme update for Compensation Event (CE) Forecasting – prospective - quotation Allows Choice (but not always) What if? Subjectivity Synergy Fair “Acceptable” 18/01/2019 Richard Bayfield 14

16 Kings College Conference July 2005
HONDA NEP PROJECT 18/01/2019 Richard Bayfield

17 Case Study – Major Client
Kings College Conference July 2005 Case Study – Major Client 2 Similar Projects on same site Built 10 years apart 40% Financial improvement on second project Positive Global comparison British Construction Industry Award 2002 NEC “philosophy and methodology” project 18/01/2019 Richard Bayfield

18 Case Study – Major Client
Kings College Conference July 2005 Case Study – Major Client “Compensation Events” dealt with on a contemporaneous basis – “managed not audited”. Final Accounts resolved within 3 months of PC Same methods for construction and process contractors Transparent programme updates every week. 18/01/2019 Richard Bayfield

19 BRITISH CONSTRUCTION INDUSTRY AWARDS 2002
Kings College Conference July 2005 BRITISH CONSTRUCTION INDUSTRY AWARDS 2002 Honda's new European plant at Swindon took the Building Award. The "one team one goal" culture of openness and transparency at Honda's New European Plant, and the company's refusal to accept the status quo, has been rewarded with a building cost of only £701/sq m - a 40% improvement on the cost of the original plant at Swindon completed nine years earlier. 18/01/2019 Richard Bayfield

20 Kings College Conference July 2005
Programme Management Transparency / visibility Emphasis on Communications Emphasis on Pre-planning Emphasis on detailed Programmes Weekly updates for actual progress Standard software (MS Project) Compliance by all trade Contractors. 18/01/2019 Richard Bayfield

21 Kings College Conference July 2005
Programme meeting using whiteboard 18/01/2019 Richard Bayfield

22 Kings College Conference July 2005
18/01/2019 Richard Bayfield

23 Kings College Conference July 2005
Whiteboard Meetings Consensual + Visible Identify potential conflict early No where to hide Instant record + Saves Management time Synthesis not Analysis Meeting Minutes – see example 18/01/2019 Richard Bayfield

24 Kings College Conference July 2005
18/01/2019 Richard Bayfield

25 Kings College Conference July 2005
Overview Methodology works - Addresses some of the industry failings BUT Synthesis is harder than analysis Needs strong Client commitment (more than just words – needs resources as well!) Needs a competent TEAM with adequate specialist support 18/01/2019 Richard Bayfield

26 Kings College Conference July 2005
18/01/2019 Richard Bayfield

27 Kings College Conference July 2005
18/01/2019 Richard Bayfield

28 Kings College Conference July 2005
18/01/2019 Richard Bayfield

29 Kings College Conference July 2005
Finally Project successes due to: Synthesis not Analysis Notes at 18/01/2019 Richard Bayfield


Download ppt "NEC - Compensation Events Programme & Delay Issues"

Similar presentations


Ads by Google