Download presentation
Presentation is loading. Please wait.
1
Project management (seminar)
Resource analysis Project management (seminar)
2
Introduction Sometimes one or more resources (especially skilled workers) are equally or more important than time. According to priority, there are: time-limited and resource-limited projects. Priority can change over time but it is not wise to have double priorities. Basic tools came from production engineering: loading (resource allocation)
3
Resources Definition: anything that is scarce and required for any activity in the project. Resources are constraints for the project. Resources can be: Non-storable: has to be renewed for each period e.g. work Storable: depleted only by usage (remains available if not used) e.g. money The most common resource typology, the 4Ms: Men Machines Money (cost) Material Other
4
Loading (resource allocation)
The assignment of work to a worker, a machine or a unit (generally: to a workstation) in time. A workstation can be: underloaded (load < capacity) fully loaded (load = capacity) overloaded (load > capacity) Fully loading is nearly impossible to reach except in flow production. Underloading is the most common, because it respects time. Overloading leads to be late.
5
Defining resources for projects
SOW WBS Task list Resource needs given in resource-hours (e.g. man-hour, machine-hour) Two forms of resource specification: Rate-constant (can be changed to a constant function/pattern): constant usage rate defines the duration, too Total constant: to finish the activity
6
What to do with non-linear duration-resource functions?
Use a computer Focus on quasi-linear parts of the functions
7
Capacity Be realistic:
Usual efficiency Estimated absenteeism, sickness, holidays Existing commitments Ancillary tasks and their resource needs Any additional constraints (like methodology) and limitations (like work contracts) Also calculate with the possibilities (cost, time, trade-offs) to increase capacity
8
Optimum seeking procedures
Constraints: Resource-limited projects Time-limited projects Resource-limited AND time-limited projects (question of priority) Methods: Linear programming Levelling Allocation Smoothing
9
Linear programming Successful only for small networks (up to about 200 activities) Need for precise data
10
Levelling (simplest technique)
Need for a previously produced starting schedule. Attempts to level out peaks and valleys in resource requirements by rescheduling some activities. Difficulty of interactions between activities.
11
Allocation (for resource limited cases)
Allocation of resources ‘Splitting’ an activity: stopping an activity, which is currently in progress, by the removal of its resources for use on an activity of higher priority. Two procedures for allocation: Serial: if only a few activities are able to be split Parallel: if many activities are splitable; more complicated method that needs more time and data
12
Allocation when resources are limited: serial procedure
All activities in the project are ranked using constant priority rule, BEFORE scheduling takes place. The most frequently used rule: ascending order of the LSTs with a tiebreaker of the ascending order of total floats (a kind of ‘urgency’). Activities are scheduled in the above order at the earliest possible point in time consistent with the availability of resources and the precedence requirements. Step-by-step process: Draw the network diagram for the logical connections Compute the activity times and total floats Plot a Gantt or time-scaled network in tandem with a resource-histogram
13
Allocation when resources are limited: parallel procedure
Only those activities which are able to start, by virtue of preceding activities being complete, are ranked in priority order using a constant rule at any scheduling period. Activities are considered sequentially (sub-lists). Unscheduled activities are retained and ranked in the next period with new activities.
14
Resource limits are: XX: 5; YY: 6; ZZ: 7
START A 4 B 1 C D 3 G F 5 E H K J 6 I 8 L FINISH Resource limits are: XX: 5; YY: 6; ZZ: 7 We are scheduling per time-periods. A period is defined by preceding activities being complete (a period ends when this changes). At the 1st day 3 tasks can be started. They must be ranked 1st by LST and 2nd by float. Only a limited resource use is allowed per day, thus some activities must be postponed to the next day due to this limit. The same process (dependency check, ranking, limit check) is repeated for the 2nd calendar time when and so on… A Gantt-chart or of a time-scaled network must be created in tandem with the calculation.
15
The time-limited case Balancing the S-curve with milestones:
Forcing early activities to start sooner
16
Smoothing (time limited case)
The aim is to produce a feasible schedule within the time constraints & provide as smooth a resource requirement profile as possible. Informational needs of smoothing: Start time and timeframe (TPT or deadline) Priority order of the resources required Prioritising activities and selecting them in order for scheduling (critical activities have supreme priority). Finding the best place for the activity (placing). Repeat the process with the next activity.
17
Prioritising activities
Considerables: Resource type(s) and importance (resource priority) Total work content (resource units per time multiplied with the duration for all resources used on the activity) Available float Formula if no initial scheduling exists: (Total work content) / (Float remaining) In descending order (greatest first).
18
Placing The best position is the one that gives the lowest usage increase in the time span of the activity. Two ways of finding this position: Visual Sum of squares: Calculate the sum of squared resource needs of each period within the questionable time frame (between the ES and LF time of the given activity) for every possible positioning Choose the position with the lowest value
19
Exercises
20
Defining resources for projects
SOW WBS Task list Logical connections (PNT) Gantt chart and histogram Levelling
21
Using the bar chart Set up and analyse the network
Assign the resource data to the activities Draw the Gantt chart Aggregate each resource time period by time period throughout the total project Cumulating (Summation or S Curve): Use levelling the load for optimization
22
Network with single resource data
2 10 8 a (1) 2 START (0) e (1) 10 13 3 FINISH (0) 13 d (2) 2 7 3 5 10 b (4) 5 10
23
Aggregation with a bar chart (single resource, earliest start)
activity 1 2 3 4 5 6 7 8 9 10 11 12 13 a b c d e Res. aggr. Cum. res. 19 28 37 42 47 50 53 56 57 58 59 Resource units 11 10 9 8 7 6 5 4 3 2 1 12 13 Time
24
Aggregation with a bar chart (single resource, latest start)
activity 1 2 3 4 5 6 7 8 9 10 11 12 13 a b c d e Res. aggr. Cum. res. 20 29 38 47 56 57 58 59 Resource units 11 10 9 8 7 6 5 4 3 2 1 12 13 Time
25
The S Curve analysis The minimum slope level is the less ‘critical’ from the viewpoint of availability
26
S Curve of the example
27
Scheduling with constraints
Three approaches: Allocation: Activities are scheduled so that an initially defined limit of resources or time is not exceeded. Levelling: A previously generated schedule must be given. Then it levels out the peaks and troughs without changing the TPT. Smoothing: A start time, a TPT and resource priorities are required.
28
Other possibilities Alternative resources Alternative methods
Alternative sequences (if there is no technical dependency)
29
Levelling the load We must have a starting allocation of activities over time and a resource constraint (previous example). Resource units 11 10 9 8 7 6 5 4 3 2 1 12 13 Time Resource units 11 10 9 8 7 6 5 4 3 2 1 12 13 Time Trying to keep the original TPT unchanged means that critical activities should not be moved. Thus try to move activities with free float.
30
Solution There are only 2 activities with free float: b & d
Which one to move and to where? Moving activity d 3 days in advance is eliminating the peak. Resource units 11 10 9 8 7 6 5 4 3 2 1 12 13 Time
31
activity 1 2 3 4 5 6 7 8 9 10 11 12 13 a b c d - e Res. aggr. Cum. res. 17 24 31 36 41 46 51 56 57 58 59
32
S Curve
33
Effect of levelling New „activity”: waiting for the resource (it is a lag, not a true activity) c (3) 2 10 8 a (1) 2 START (0) e (1) 10 13 3 FINISH (0) 13 d (2) 5 10 b (4) 5 Changes: new precedence relationship, floats, late start and finish times
34
Network with single resource data
2 10 8 a (2) 2 START (0) e (1) 10 13 3 FINISH (0) 13 d (2) 2 7 3 5 10 b (4) 5 10 Resource limit: 5
35
Network with multiple resource data
c (3A) 2 10 8 a (2A) 2 e (3B) 10 13 3 START (0) FINISH (0) 13 d (2B) 2 7 3 5 10 b (4B) 5 10 f (3A) 5 8 10 13 3 Resource limits: 5A, 5B
36
Reading Lockyer – Gordon (2005): Chapter 17 & 18
37
Thanks for your attention
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.