MQY as Q5 in the HL LHC era Glyn Kirby MQY 001 bat 927
2
Overview MQY parameter list Proposed change to LHC circuit
High Energy in test station comparison Test station modification PSU’s set up, current leads 3 or 4, protection. Test plan Typical out of balance powering
3
MQY parameters Operating Temp 4.5 K 1.9 K Nom Gradient 160 T/m 200 T/m
Nom Current A A Inductance 74 mH/aperture Twin aperture clear 70mm diameter Overall length 3.64 m Mass 4.3 tones
6
Proposed change to LHC circuit and operation
7
Comparing Quench Energy’s
MQXC KA, 688 kJ HQ KA, kJ MQY 4.5 K , kA, 482 kJ/ap kJ T/m MQY 1.9 K , ultime performance 110% of nominal gradient, 5.0 kA and 220 T/m, kJ /Ap kJ
8
Operating Area 5000 A, 5000A 2000 kJ 1.9K 958 kJ 4.5K 4500 A, 2250 A
936 kJ 50% diff HQ 750 kJ 934 kJ 90 % diff field measurement ? 3600 A 5030 A
9
HQ test
10
Standard Circuit in LHC
Std PSU in LHC is limited to I2=50% I1
11
SM18 Test set up ? Ideal set up 4 current leads Two dumps Two switches
QPS set up ? PSU A PSU A Or use quench heaters to protect magnet
12
Test cycles 50% A1/A2 MAX A1-A2 90% A1/A2
Example of the type of cycle we will need. Slow ramp rates 3.8 A/s ~ 20 mins ramp. Staircase with field measurement every 500 A in both apertures 1 hr flat top at max field / current configuration Check joints, may need to open up part of the joint box to get V-taps in? Three machine cycles!
13
MQY Test project MQY ? Mount current lead-box on magnet, for independent powering? Electrical testing Quench heaters (insulation , discharge) Magnet Ground insulation Field Measurements ? Cold testing.
14
Cold testing Set up rotating field probes in both apertures?
Std. electrical checks. Cool down 4.3 tonnes larger than MQ. 3 days? Set up QPS Test field measurement. 1 day, may be more? Training 1.9 K, 4 quenches a day ? 2 days 50% and 90% A1/A2 at 4.5 kA 2.25 kA & ?/? Field measurement with 50% diff. 2 days QLIQ test , reconfigure onto one PSU. ? Simulation needed! Warm up, thermal cycle ?. Total 12 to 15days
15
Conclusions / Comments
Two power supplies, control set up needed High energy , carful pre testing to predict pressure and limit it! Field measurement two rotating probes, or only measure one aperture, or thermal cycle to be abler to measure both apertures at all currents. Two to three week testing >>>>>>>>>>>>>>>> Joint tests after siting in air for 7 to 10 year’s? open joint box and have a look! Should we also test MQM?