Presentation is loading. Please wait.

Presentation is loading. Please wait.

Cost Containment Working Group Board Update

Similar presentations


Presentation on theme: "Cost Containment Working Group Board Update"— Presentation transcript:

1 Cost Containment Working Group Board Update
January 24, 2019

2 Main Drivers of Cost and Delay Unbalanced risks
Initiative announced in June 2018 Main Drivers of Cost and Delay Unbalanced risks Layers of bureaucracy and red tape Weak project management Goal: Deliver projects on time and on budget

3 June Recommendations 1. Rebalancing Risk 2. Red Tape
More design-build 3rd Party Dispute Resolution Use incentives & penalties Expand competition 2. Red Tape Cut change order processing time Cut submittal processing time Simplify specifications 3. Project Management Appoint project CEOs Aggressively manage scope expansion Better cost forecasting

4 Rebalancing risk – design-build contracts
More projects done as design-build Bridges & Tunnels – seven D-B projects in 2018 for $251 million Metro-North – four D-B projects kicked-off in 2018 worth $580 million; three more coming in 2019 worth over $130 million. NYCT – 19 stations done with design-build under enhanced station initiative LIRR – using D-B for 14 station enhancements & one traction power substation; 2 more substations in 2019

5 Rebalancing risk – contract dispute resolution
Using neutral third parties to resolve disputes, not MTA employees MNR not using MTA employees as arbiters on all contracts In 2019, all new construction contracts over $50 million will adopt independent / neutral third party model

6 Rebalancing risk – other contract reforms
Reducing financial risk Bond requirements – Going forward, payment bonds will be cut in half on contracts exceeding $250 Million Faster payments – reduce internal payment cycle to 21 days Partial payments – even when some items are in dispute

7 Rebalancing risk – smarter risk allocation
Sharing risk drives lower bids Track outage – MTA and contractors each responsible for own performance Utilities – contractor not liable for delay caused by utilities Hazardous materials – allocated contingency for unknown risks Unexpected subsurface conditions – risk is shared

8 Cutting red tape – change order processing time
66% drop 192 562

9 Cutting red tape – NYCT process improvements
NYCT attacking red tape on many fronts Rewriting 50+ design specifications 40% increase in track outage for capital projects Streamlined cost forecasting – Sea Beach subway station 13% increase in NYCT work train locomotive availability 30% increase in flat car availability Better management eliminating flagger shortages New NYCT executive committee meets bi-weekly to resolve scope and schedule issues

10 Stronger project management – project CEO
Strong project leadership controls scope creep Project Leads for projects over $50 million at B&T MNR using Project Lead for $365 million Harmon Shop Phase 5 Stage 2 LIRR using Project Lead for Jamaica Capacity Improvements Phase I ($301 million, in construction) and Phase II (in design) Agencies revising project management policies & job descriptions for project leads

11 MTA needs a culture change around capital projects
Incremental Progress MTA needs a culture change around capital projects Memo from the Chairman Agencies asked to report by April 1 Make progress on multiple fronts

12 Additional cost issues to be addressed
Next steps Additional cost issues to be addressed Utilities – MTA only agency that pays utility relocation costs Labor costs & work rules – MTA should have a seat at the table Force account – internal labor (flaggers, design review, inspection, etc.) drives project costs MWBE contracts – administer effectively to grow expertise and capacity to deliver Project management – external consultant costs

13 Questions


Download ppt "Cost Containment Working Group Board Update"

Similar presentations


Ads by Google