Evaluating Construction Methods for an Electrical Transition Compound Christopher OConnor Andrew Canniff
2
Abstract Evaluating Construction Methods Design Evaluation Criteria Cost Estimates Construction Schedules Environmental Impact Durability & Lifespan Required Maintenance Availability of Labor & Materials Recommendation Alternative Option
3
SK-1: Ground Floor Plan and Roof Plan
4
SK-2: Elevation
5
SK-3: Site Plan
6
Summary of Options Cast in Place Concrete Concrete Masonry Unit (CMU) Insulated Concrete Forms (ICF) Precast Concrete Structural Steel
7
Cast in Place Concrete Formwork Reinforcing steel (Rebar) Mix-designed concrete Pouring Stages Scaffolding and Bracing Weatherproofing
8
Concrete Masonry Unit (CMU) CMU Block Horizontal Bracing Vertical Reinforcing Steel (Rebar) Grouting Scaffolding and Bracing Weatherproofing
9
Insulated Concrete Forms (ICF) ICF Block Polystyrene Foam Insulation Acts as permanent formwork Mix-Designed Concrete Pouring Stages Vertical and Horizontal Reinforcing Steel (Rebar) Scaffolding and Bracing Weatherproofing
10
Precast Concrete Offsite Fabrication of Reinforced Concrete Panels Installation of Panels Bracing Weatherproofing
11
Structural Steel Offsite fabrication of beams, columns, and exterior steel panels Installation of steel elements Bracing Weatherproofing
12
Design Evaluation Criteria
13
Cast in Place Concrete Cost: $990,457.10 Construction Duration: 24.5 weeks
14
CMU Cost: $895,957.10 Construction Duration: 31 weeks
15
ICF Cost: $898,601.70 Construction Duration: 23.5 Weeks
16
Precast Concrete Cost: $1,147,957.10 Construction Duration : 22 Weeks
17
Structural Steel Cost: $929,674.85 Construction Duration: 20 Weeks
18
Final Design Evaluation Criteria
19
Comparison of Durations & Costs
20
Recommendations Structural Steel ICF
21
Acknowledgements DaBoys would like to sincerely thank all members of the Dartmouth Stantec Office for not only all of your assistance throughout this project but also making both of us feel right at home.
22
Questions?
23
Picture Reference http://www.baruzzini.com/images/large/image-12.jpg http://knoji.com/images/user/cmu-1.JPG http://heatherwestpr.com/blog/wp- content/uploads/2009/08/tufut.jpg?w=150 http://heatherwestpr.com/blog/wp- content/uploads/2009/08/tufut.jpg?w=150 http://www.idevelop.ie/ibuild/images/ICF.jpg http://media.treehugger.com/assets/images/2011/10/icfsketch.jpg http://www.actonprecast.com/admin/ktmlpro/images/uploads/C atello%20Pumphouse.jpg?0.7051663490068698 http://www.actonprecast.com/admin/ktmlpro/images/uploads/C atello%20Pumphouse.jpg?0.7051663490068698 http://www.designindustriesinc.com/Precast_Concrete_Wall_Install _1.JPG http://www.designindustriesinc.com/Precast_Concrete_Wall_Install _1.JPG http://3.imimg.com/data3/JJ/OG/MY-4119982/structural-steel- frame-commercial-building-250x250.jpg http://3.imimg.com/data3/JJ/OG/MY-4119982/structural-steel- frame-commercial-building-250x250.jpg http://ciabuildings.com/wordpress/wp- content/uploads/2011/02/PICT01861-550x412.jpg http://ciabuildings.com/wordpress/wp- content/uploads/2011/02/PICT01861-550x412.jpg