Koji Ueno National Taiwan U. 2003/2/13 @PSROC
Status of SVD2 upgrade Koji Ueno National Taiwan U.
2
Outline Features of SVD2 Flex saga Schedule & accident Conclusion
Smaller beam pipe & more Si layers TTM( see Jerry’s talk) & Flex: done by NTU. Flex saga Low yield & spares Schedule & accident Beam pipe was broken Conclusion
3
Features of SVD2 Smaller beam pipe R = 2 cm --> 1.5 cm.
Originally 1 cm was planed. More silicon layers 3 --> 4. Originally 5 layers were planed. Radiation-hard front-end electronics. Up to 10 MRad is tested OK. Z trigger. Necessary to remove a beam-gas event.
4
Belle SVD2 246 Double-sided Silicon Strip Detectors (DSSDs).
Each DSSD has 512 z strips and 512 phi strips. Total no. read out is 250 k. It is reduced to 110 k by ‘ganging’. Ganging is done by FLEX.
5
SVD2 system
6
SVD1.x dose
7
TTM & Flex NTU is responsible for TTM & Flex. TTM see Jerry’s talk.
We finished them in spring, 2002. They are now used in 1/10 system without a problem. We need a spare Flex and SVD to prepare for an “accident”.
8
Z-R trigger
9
Efficiency for 3-out-of-4 layers
10
Ganging in FLEX. FLEX DSSD Wire-bonding on Si and FLEX pads. Z strip
Read out Signal Signal
11
Ghost track due to ganging
12
Flex saga Flex task was supposedly easy.
Flex was in a crisis a year ago: low yield, bad wire-bonding, repair etc. Laser beam was used to repair shorted lines to meet a deadline. Only small no. of companies can make a Flex in the world. Exchange of Flex info. among Belle, D0 and CDF.
13
Laser surgery of shorted wire
The shorted wire is fixed by laser.
14
Wire-bonding 25 mm wire for bonding.
15
SVD2 schedule
16
Integrated luminosity
17
Peak luminosity of Belle & BaBar
18
Space Shuttle Columbia accident
19
SuperKamioka in repair
20
Broken beam pipe
21
Installation of 1.2 SVD HOM resonant heating Installation of 1.4 SVD Trouble of He cooling system
22
The SVD2 first cosmic ray muon event
Nov. 15, 2002
23
Conclusion SVD2 upgrade has a successful 1/10 system test. Has seen the 1st CR event. It is likely installed in summer, 2003. It aims for a higher luminosity. We have to prepare a spare SVD and a spare Flex for an accident.