January 26, 2019
2
Highline High School Burien, WA
Contact Margot vanSwearingen, Project Manager Skanska USA Building
3
Highline High School– Scope Letter
Project Team Highline Public Schools Vanir Project Management Bassetti Architects PCS Structural Metrix Engineers (Mech) Hargis (Elec) AHBL (Landscape) Sitewise (Civil) PLA Designs (Theater) JLR Design Group (Food Service) Skanska USA Building Sr. Superintendent: John Amdal Project Executive: Dan Curtiss Project Manager: Margot vanSwearingen MC/CM Partner: Holmberg Co. EC/CM Partner: Premier Power
4
Highline High School– Scope Letter
Project Details GC/CM Project Current Phase: 75% Construction Documents, Submitted for Bldg Permit Budget: $108 Million Construction Duration: July 2019 – June 2021 Building Size: 256,409 SF Students Served: 1500 Students Full Demolition of the Existing Buildings – existing PAC and Stadium to remain Aggregate Piers at Building Footprint Masonry Salvage / Reinstall at portion of North facade Offsite Tennis Court Facilities at the Sunnydale School site.
5
Site Location Highline High School
6
Highline High School Site Plan Overview Existing Site Future Site PAC
Stadium Stadium Existing Site Future Site
7
Highline High School– Scope Letter
Building Design Highline High School– Scope Letter A B Commons D C
8
Building Design Highline High School
9
Building Design Highline High School
10
Building Design Highline High School
11
Building Design Highline High School
12
Building Design Highline High School
13
Building Design Highline High School
14
Highline High School– Scope Letter
Bid Packages & Timelines Highline High School– Scope Letter Group 1: Early Works (PAC & Stadium Severing) & Early Procurement Bid Package Issue Date: February 25, 2019 Approx. Bid Date: April 2, 2019
15
Highline High School– Scope Letter
Bid Packages & Timelines Highline High School– Scope Letter Group 1: Earthwork & Equipment Bid Package Issue Date: February 25, 2019 Approx. Bid Date: April 2, 2019
16
Highline High School– Scope Letter
Bid Packages & Timelines Highline High School– Scope Letter Group 1: Superstructure & Masonry Bid Package Issue Date: February 25, 2019 Approx. Bid Date: April 2, 2019
17
Highline High School– Scope Letter
Bid Packages & Timelines Highline High School– Scope Letter Group 1: Envelope Bid Package Issue Date: February 25, 2019 Approx. Bid Date: April 2, 2019
18
Highline High School– Scope Letter
Bid Packages & Timelines Highline High School– Scope Letter Group 2: Finishes Bid Package Issue Date: April 8, 2019 Approx. Bid Date: May 16, 2019
19
Highline High School– Scope Letter
Bid Packages & Timelines Highline High School– Scope Letter Group 2: Finishes Bid Package Issue Date: April 8, 2019 Approx. Bid Date: May 16, 2019
20
Highline High School– Scope Letter
Electrical Subtier Packages Highline High School– Scope Letter Electrical Vendor Packages Package 1: Floor Boxes and Cable Tray Package 2: Gear Package Package 3: 3rd Party Testing Package 4: Lighting Package 5: Generator & ATS Electrical Subtier Turn-Key Packages Package 1: Solar Array System Package 2: Audio/Video Systems Package 3: Telecom & DAS Package 4: Intercom Package 5: Security Systems Package 6: Fire Alarm & Rescue Assistance
21
Highline High School– Scope Letter
Additional Opportunities Highline High School– Scope Letter Negotiated Support Services Final Cleaning Jobsite Office Janitorial Temporary Site Fencing Site Security Camera Scaffolding Survey & Layout Office Supply Misc. material supply: Wood, hardware, consumables, small tools Site Temporary Signage Safety Supply Lump Sum Subtier Opportunities Site Permanent Fencing Site Signage & Striping Building Signage
22
Bidding Details
23
Builder’s Exchange of Washington
Bid Advertisements Plan Centers Builder’s Exchange of Washington
24