Download presentation
1
AS-7 Construction Contracts
Book on how to play bridge 1. VSNL 2. Tough job done by ICAI for this AS. 3. For a specific unit or company but to come up with a complete code on treatment, etc. Paragraph with 2 appendices to explain. 5. In detail even whole day would be insufficient to discuss. Sunil Arora M.Com, FCA
2
Construction contracts
X & Co receives a contract for construction of a Fly Over in 2007 Work of the contract is being carried on during the FY ending 31/03/2007, 08 & 09 The contract is likely to be completed in the FY Should the profit be booked on completion of the contract in FY
3
Taxability of income Two options: Cases pertain to contractors
Project completion method % completion method from year to year Cases pertain to contractors Held: Income assessable on yearly basis Sri Sukhdeodas Jalan v. CIT 26 ITR 617 (Patna) Tirath Ram Ahuja Pvt Ltd v. CIT 186 ITR 428 (SC) CIT v. NM Associates 256 ITR 141 (Mad)
4
Accounting of contractor
Whether appropriate to wait till completion of the project? AS 7 : Construction Contracts prescribes treatment of revenue and costs associated therewith in the financials of the contractor AS 7 revised in 2002 and applicable for accounting periods commencing on or after 01/04/2003
5
OBJECTIVE Accounting treatment in the books of contractor.
Contracts span over a number of financial years. Allocation of contract revenue and contract costs to various accounting periods Uncertainty attached with the total contract
6
Recognition of Contract Revenue & Expenses
If outcome of Construction contract can be reliably estimated Revenue & Costs pertaining to the contract should be recognized by the stage of completion or % completion method Implication Total Revenue Total Costs - Profit ? Based on % of work completed Revenue, Cost, Profits, etc. up to the reporting date to be treated in F.S.
7
Stage of completion Advance / progressive payments received may not reflect the work performed How to ascertain stage of completion?
8
Issues Revenue from contract how ascertained?
How to ascertain cost of the contract ? Stage of completion of contract? How to deal with expected losses ? Various types of contracts? What is a reliable estimate of outcome of contract ? If reliable estimates not possible ?
9
Year wise allocation Contract revenue Contract cost
Stage of completion
10
Contract Revenue Consideration received or receivable
Due to uncertainties and events which occur during the contract; The estimates need to be revised The amount of revenue from a contract may increase or decrease from one period to the next
11
Contract Revenue Initial amount of revenue agreed
Variations in the contract Claims Incentive payments Cost escalations Penalties
12
Variations Instruction by the customer for a change in the scope of work Variation may increase or decrease the contract revenue Variation to be considered: It is probable that the costumer will approve the effect on revenue; and the amount of revenue can be reliably measured
13
Claims Amount which the contractor seeks to collect from the customer on account of changes, delays, errors, etc Revenue from claim is uncertain and depends on negotiations To be included: Negotiations have reached advanced stage It is probable that customer will accept the claim Amount can be reliably measured
14
Incentive payments Additional amounts if specified performance standards met or exceeded To be included: The contract is sufficiently advanced It is probable that the specified standard will be met or exceeded Incentive payment can be reliably measured
15
Cost escalations Whether escalation clause in the agreement legally enforceable against the customer Escalations can be related to the customer Escalations due to delay by the contractor It is probable that the escalation in cost will be realised from the customer Whether cost escalation can be reliably measured
16
Penalties Cause for the levy of penalty or deduction from the revenue
Status of penalty clause in the agreement It is probable that the penalty may be waived Penalty can be reliably measured
17
Contract Costs Costs that relate directly to the specific contract
Costs that are attributable to contract activity in general and can be allocated to the contract Other costs chargeable to the customer
18
Direct contract costs Site labour, supervision, etc Costs of material
Design & technical assistance Cost of moving plant, equipment, etc to & from the contract site Costs of hiring plant & equipment Depreciation? Cost of rectifications including expected warranty costs.
19
Allocation of general costs
Insurance Cost of design and technical assistance not directly related to a specific contract Construction overheads Borrowing costs as per AS 16 Allocation to be systematic & rational Basis of allocation to be consistent for all costs having similar characteristics
20
Contract costs Contract costs include costs for the period from securing the contract to the final completion Costs incurred for securing a contract are also included as a part of the contract costs; if they can be separately identified & reliably measured
21
Recognition of Contract Revenue & Expenses
If outcome of Construction contract can be reliably estimated Revenue & Costs pertaining to the contract should be recognized by the stage of completion or % completion method Implication Total Revenue Total Costs - Profit ? Based on % of work completed Revenue, Cost, Profits, etc. up to the reporting date to be treated in F.S.
22
Stage of completion Advance / progressive payments received may not reflect the work performed Proportion of costs incurred vis-à-vis total contract costs Surveys of work performed Completion of physical proportion of work
23
Costs incurred Only those costs which reflect the work performed
Advances to suppliers, sub contractors, etc Materials delivered not yet installed General procurement Specifically manufactured Whether vendor selection and issue of purchase order can be taken as stage of contract?
24
% completion method Contract costs are recognised as an expense in the period in which work is performed Costs which relate to future activity is recognised as an asset and classified as contract work in progress Revenue upto the stage of completion at the reporting date is recognised The estimates are revised, when necessary Need for revision does not indicate reliability of measurement
25
Stage of completion 31-03-07 31-03-08 31-03-09 Total revenue 250 300
400 Total cost 200 360 Cost incurred 80 125 288 Stage of completion 40% 50% 80% Revenue recognised 100 50 170
26
Reliable estimate of outcome
Fixed Price Contracts Cost Plus Contracts
27
Reliable estimates possible
Fixed Price Contracts Contract Revenue can be reliably measured Contract costs to complete the contract can be measured reliably Contract cost attributable to the contract can be clearly identified and reliably measured Stage of completion can be reliably measured Economic benefits will flow to the enterprise
28
Cost plus contract Contractor is reimbursed for defined costs plus % of these costs or a fixed fee Outcome can be reliably measured: Contract costs attributable to the contract clearly identified & measured Economic benefit associated with the contract will flow to the enterprise
29
Changes in Estimates With the progress of the contract, the estimates of costs & revenues to be revised Need for revision does not indicate that the outcome cannot be reliably measured Consolidated review on each reporting date Balance after deducting amounts recognised in the previous years to be treated in the FS
30
Outcome cannot be reliably estimated
Revenue to be recognized only to the extent of costs of which recovery is possible Costs to be recognized as an expense in the period in which incurred Applicable more in the early stages of contract.
31
Recognition of expected losses
Contract Costs > Total Contract Revenue Expected Loss ? Work commenced or not ? Stage of completion of Contract ? Profit from other contract not treated as single contract ?
32
Disclosure requirements
Contract revenue: Revenue recognised Method used Basis to determine stage of completion Contracts in progress: Aggregate amount incurred and recognised Advances received Retentions Amounts due from or to the customers
34
Other Issues Unertainty about collectivity of revenue already recognized Contact costs where recovery is improbable.
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.