Civic Association Information Meeting
THE VIEWS AT CLARENDON Civic Association Information Meeting
3
Team Introduction Doris Topel-Gantos – Bozzuto Development Company
Vicki Vaughn – Chesapeake Community Advisors Mike Green – Bozzuto Construction Company Mark Weisner – Bozzuto Construction Company Dale Leidich – MTFA Architecture
4
Community Liaison Mark Weisner – Senior Project Manager
○ ○ A phone number will be provided at a later date.
5
Construction Hours Weekdays - 7:00 am – 6:30 pm
Weekends & Holidays - 10:00 am – 6:30 pm Holidays are defined as Martin Luther King Day, Presidents Day, Memorial Day, Independence Day, Labor Day, New Year’s Day, Columbus Day, Veteran’s Day, Thanksgiving, and Christmas.
6
Construction Hauling Route
Construction traffic will be routed around the perimeter of the site with access from Wilson/Clarendon.
7
Parking Plan
8
Project Site: 1210 N. Highland Street
Parking Plan Project Site: 1210 N. Highland Street
9
Offsite Parking Locations
Parking Plan Offsite Parking Locations
10
Parking Plan
11
Parking Plan Metro Locations
12
Projected Schedule ●Start – November 2009
●Abatement - Month 0 thru Month 2 ●Demolition – Month 3 ●Excavation – Month 4 thru Month 7 ●Vertical Construction– Month 8 thru Month 24 ●Site Construction – Month 0 thru Month 4 & Month 20 thru Month 24 ●Lease-up starts – Fall 2011
13
Future Deliverables ●MOT Plan – Upon Arlington County approval
●Temporary Pedestrian & Vehicular Circulation - Upon Arlington County approval ●Final Site Plan & Landscape Plan – Upon Arlington County Approval
14
South Elevation