Download presentation
Presentation is loading. Please wait.
1
Galt Court Water Main Replacement
Georgetown Village Community Woodbridge District Town Hall Meeting January 23, 2019 Service Authority Project Manager: M. Elena Herrera, P.E. Engineering Consultant: Pennoni Associates Inc. Contractor: AVES Construction
2
Agenda Project Background Purpose of Project
Project Layout and Limits of Construction Project Schedule Service Authority Commitments Q&A
3
Project Background The existing cast iron pipe water mains are dated from 1971. Since 2010 there have been over 10 water main breaks in Galt Court. April Pennoni Associates initiated design. Summer 2018 – Service Authority replaced all water meters in Galt Court. January 2019 – The Service Authority Board of Directors approved the construction contract with AVES Construction.
4
Purpose of the Project Improve system hydraulics and reliability
Improve customer level of service Improve safety of the community by adding a hydrant Relocate the water mains to minimize customer inconvenience Enhance system components such as meter assemblies
5
Project Layout and Limits of Construction
New Water Mains and Hydrant
6
Project Schedule On-site construction is scheduled to begin in spring 2019 150 days to final completion Dependent weather conditions Hour of construction will be limited to weekdays from 7:00am to 5:00pm
7
Service Authority Commitments
To restore area affected by construction to original or better condition. Includes pavement restoration of the court. To maintain road access at all times. Emergency services, trash, mail, school buses and other services. To communicate with HOA concerning project status. To respond to residents’ concerns. To notify customers about parking disruptions for daily operations. Customers will be notified a minimum of 24 hrs in advance. Reconnection last no longer than 4 hrs
8
Service Authority Commitments
To maintain water service. Except for interruptions during water service reconnection. Customers will be notified a minimum of 24 hrs in advance. No work will be performed outside of the hours of construction without prior authorization from the Service Authority. Daily clean-up by the Contractor is required. Service Authority Inspector on site daily and as necessary.
9
Service Authority Commitments Pavement Restoration
Area to be Repaved
10
Questions and Contacts
Project address Project website Service Authority Project Manager M. Elena Herrera, PE Phone: (703) Questions?