TAB Data Center Renovation Project Planning for Transition of Summer 2013 February 21, 2013 TAB Atrium
2
Thank you for your help so far… We have begun Phase 1 of our construction Moving a 30-ton cooling capacity roof top unit on Saturday, February 16 2
3
Then Now 3
4
Where were we before this journey began? Physical Servers: 409 Virtual Servers: 93 All old architecture going to Quad switches Prior to fiber optic New Architecture and TSSDC as additional Data Center Data from May 2011 Does not include HPC or Storage
5
We made progress along the way… Physical Servers: 291 Virtual Servers: 288 (combined TAB/TSS) New Architecture in place Old Architecture still exists for many things Data from May 2012 Does not include HPC or Storage
6
Where are we now in TABDC? Physical Items: 210 55 in New Architecture 155 in Old Architecture Of those, 80 are slated for retirement or virtualization Virtual Servers: 285 (plus 185 in TSSDC) 239 in New Architecture 46 in Old Architecture* Data from January 2013 Does not include HPC or Storage
7
What does that look like graphically? 7
8
Physical layout of TAB Data Center 8
9
Proposal you saw last June 9
10
Actual plans based on modifications Phase 1 Phase 2 10
11
Construction Timeline Roof, electrical, floor work all underway now on Left Side Current Stage = Demolition Construction crews on hand next several Saturdays to minimize disruptions during normal working hours Communications to inhabitants of TAB on a bi- weekly basis with look ahead for major milestones 11
12
IT Timeline Current construction timeline is 4 weeks to move everything from Right side to Left side once we are delivered a completed Phase 1. Target late June. 4-6 weeks prior, we hope to have shared access to install cabinets and cabling, burn in new equipment (May 1-June 15). Split redundant network during this time* Target date for Retirements and Re-IP = April 30 –Months of May and June are filled with obstacles due to Academic calendar 12
13
Targets for end of Phase 1 210items to move: Servers, Storage, Network, HPC, Mainframe First pass discussion, Technology Services identified: –52 items that could be retired outright –28 items that could be virtualized –55 items that are already New Architecture and can move easily –10 items for Storage (actual size 6+ cabinets) Leaves 68 items that need to be Re-IPed intoNew Architecture 13
14
Why? All equipment is being re-racked into new standardized racks. –Minimizing number of items to move or addressing beforehand means we can meet our 4-week window. Knowing what is going where allows us to plan our equipment purchases for networking and allocate power efficiently. 14
15
15
16
Not Shown: HPC, Mainframe w/Storage, Tape Backup (~7 cabinets) Items currently in TABDC slated for retirement/virtualization 16
17
Thank you for your help so far… …interesting times still ahead! 17