Scope, Requirements Deliverables & Schedule
Ritendra Bhattacharya & John Hogan LCLS-II Software Review November 14, 2018
2
Charge Addressed GENERAL COMMISSIONING
Is the documentation and coding maturity consistent with the schedule? Is the schedule compatible with the overall plan including Installation and Commissioning? Is the Control Team organized and staffed to successfully complete the project? COMMISSIONING Has JLAB developed a plan to perform commissioning? Have the required resources been identified? LCLS-II Software Review, November 14, 2018
3
Outline Scope System Definition Requirements Deliverables
Software & Documentation Schedule & Resources Organization Commissioning Plan – High Level Workshop scheduled 4-5 December 2018 LCLS-II Software Review, November 14, 2018
4
Scope of work for the Cryoplant software development
Gathering information for software development - Complete Preliminary software development – First draft complete Bench testing – In Progress Final software development – will be pre-released for commissioning On-site adjustment during commissioning – Final released to OPS This same software code is currently successfully running cryogenic plants following facilities: Jefferson Lab CEBAF – (CHL2) Oak Ridge National Lab – (SNS) NASA Houston – (Johnson Space Center) Michigan State University – (FRIB) Brookhaven National Lab - (RHIC)* * Process improvement – upgrade to “Ganni Cycle” LCLS-II Software Review, November 14, 2018
5
Five Primary Sub-systems
Scope - cont’d Five Primary Sub-systems Software is being developed in collaboration with SLAC software (EED) group. System PLC Software Local HMI EPICS Warm Compressors JLAB SLAC Gas Management Utility 4.5 K Cold Box 2 K Cold Box LCLS-II Software Review, November 14, 2018
6
System Definition System are defined using the P&IDs of each group of sub-systems with respect to control PLCs setup only. System Name P&ID Gas Management Main Compressor System Oil Removal System Cooling Water System Cooling Water System (for Turbines, DPs and CCs) Instrument Air System 4K Cold Box Main 4K Cold Box Test Main 4K Cold Box LHe Storage Dewar System 2K Cold Box 2K Cold Box with Cold Compressors Warm Compressor Skids LP Compressor MP Compressor HP Compressor System Name P&ID Utility Oil Processor Skid - TBD He Gas Distribution Sys. Cooldown/CleanUp Dist. Sys. He Gas Analyzer System Interface Box He Recovery System He Purifier System He Recovery Compressor Instrument Air Distribution Sys. He Gas Storage System LN2/GN2 Distribution System LN2 Dewar 20,000 GAL Guard Vacuum System LCLS-II Software Review, November 14, 2018
7
Requirements – Reference Documents
LCLS-II Software Review, November 14, 2018
8
Deliverables - Software
Following Deliverables (JLAB and SLAC) PLC Codes Local HMI display screens for touch panels EPICS control display screens and data acquisition Major Sub-Systems: Warm compressors systems Gas management system Utilities Infrastructure 4.5 K cold box 2 K cold box Deliver a cryogenic plant that can be manually operated to meet the performance requirements. LCLS-II Software Review, November 14, 2018
9
Deliverables - Documentation
The documentation deliverables are consist of the following: P&ID’s Wiring Diagrams Failure mode and effect analysis (FMEA) Functional narratives Software specifications Software testing procedure PLC Software Parallel support of integrated controls on site.. Sequence flow charts for the integrated software (by SLAC) Build on the work completed by Dayne Robinson for the cryomodules Will use this to develop integrated controls (CP-CDS-CM) Details Presented in Documentation Talk by C. Scanlon LCLS-II Software Review, November 14, 2018
10
Software Development - Schedule
System PLC - Draft Local HMI EPICS HMI Bench Testing Expected Pre-Commissioning Start End Warm Compressors 2017 May 2018 Jun 2018 Dec 2018 Jan 2019 May/Jun 2019 Gas Management Apr 2018 Nov 2018 Mar 2019 Utility Jul 2018 Feb 2019 4.5 K CB Aug 2018 Oct 2018 May 2019 Jul 2019 2 K CB Dec 2019 Software development schedule is consistent with the commissioning plan LCLS-II Software Review, November 14, 2018
11
P6 Schedule and Resources
Software development activities are resource loaded in project schedule. LCLS-II Software Review, November 14, 2018
12
P6 Schedule and Resources (cont’d)
Resources allocated for each development activity Float numbers need to be vetted with new installation schedule provided last week. LCLS-II Software Review, November 14, 2018
13
Organization and Resources
Principal EE (D. Arenius) CAM (J. Hogan) I&C Project Lead (R. Bhattacharya) EE (N. Sandoval*) EE Manager (R. Norton*) (C. Scanlon) (S. Shrishrimal*) Deputy CAM (M. Bevins) NOTES: *EE Part-time on LCLS II cryoplant project. Resources have been assigned and are periodically assessed to ensure schedule is held. Additional resources will be allocated to software development if needed to hold schedule. LCLS-II Software Review, November 14, 2018
14
LCLS-II Cryogenic Plant Commissioning – Workshop 4&5-Dec-2018 @Jefferson Lab
LCLS-II Software Review, November 14, 2018
15
LCLS-II Cryogenic Plant Commissioning (cont’d) Detailed act activity & staffing level requirements
I&C is integrated into commissioning plan Resources identified by skill set LCLS-II Software Review, November 14, 2018
16
Charge Response GENERAL
Is the documentation and coding maturity consistent with the schedule? Yes. Is the schedule compatible with the overall plan including Installation and Commissioning? Yes; new GC installation schedule needs to be vetted. Is the Control Team organized and staffed to successfully complete the project? Yes. Additional resources are available if required. COMMISSIONING Has JLAB developed a plan to perform commissioning? Yes; workshop scheduled for 04&05 Dec-2018 Have the required resources been identified? Yes. LCLS-II Software Review, November 14, 2018
17
THANK YOU FOR KIND ATTENTION
LCLS-II Software Review, November 14, 2018