ISPA Measure 2002 BG 16 P PE 010 Targovishte Wastewater Collection and Treatment, Republic of Bulgaria
2
Works Contract Construction of WWTP Targovishte
Commencement Date: 15th May 2007 Completion Date: 14th December 2011 Physical Execution: % Financial Execution: % (actually paid 84 % following retaining of so-called ‘Retention Money’ and deduction of ‘Delay Damages’)
5
Rehabilitation of main sewers in Targovishte town, construction of sewerage and re-construction of water-supply networks in Vabbel Quarter, north of Al. Stamboliiski str. Commencement Date: th December 2009 Completion Date: st January 2011 Physical Execution: % construction works (95 % compared to initial figures, but actually 100 % executed) Financial Execution: ,6 %
6
Main Collector – Branch 3
Sewerage network Vabbel quarter Water-Supply network Vabbel quarter
7
Billboard and Publicity Leaflet
9
Compliance with Article 8 of the Financing Memorandum
Art. 8.3.a) The condition defined in the article is considered as fulfilled with EC’ s letter No dated 24th January, 2012. Art. 8.3.b) The condition defined in the article is considered as fulfilled with EC’ s letter No dated 21st December, 2010. Art. 8.3.c) The condition defined in the article is considered as fulfilled with EC’ s letter No dated 14th January, 2011.