Annual Review - Methodology Statements
Transmission Workgroup 7th June 2012
2
IECR – Incremental Entry Capacity Release ECS – Entry Capacity Substitution
National Grid is required to review the IECR and ECS methodologies each year The annual review of these methodologies will commence in June 2012 National Grid requests that any issues with the methodologies which may require review and revision to the statement(s) are notified to National Grid via by the 5th July 2012 Issues to be sent via to or Formal consultation on any proposed changes to the Methodology Statements will begin approx September 2012 Currently, we anticipate making changes to better align capacity release timescales to the requirements of the planning Act. There may be a requirement to consider the possible outcome from RIIO and how these changes are to be reflected as part of the methodologies.