1 CONTROL OF BUILDING SITES
THREE TIER CONTROL THREE TIER CONTROL SITES CONTROL OF BUILDING

2 THREE TIER CONTROL Primary: the network of control points coordinated in all three dimensions to give a fixed overall reference framework for the works Secondary: local control points for construction or baselines established for structures Tertiary: points set out at the actual positions for construction or at suitable offset positions.

3 Primary Control Points
These are the Master control points set out from national reference points Form a closed loop Built in redundancies for checking Set out by specialist surveyors Position and Level known Official National Survey points Primary site control points

4 Secondary Control Points
These form the control points for setting out base lines and sites grids. Set out from the Primary control points May have associated level value

5 Tertiary Control Points
These are the points you will be setting out Relate to construction elements Set out so dimensional checks can be made.