Download presentation
Presentation is loading. Please wait.
Published byCharity Higgins Modified over 6 years ago
1
2/19/2019 3:59 PM The Department of Procurement (the “DOP”) on behalf of the Office of Enterprise Assets Management FC-10398, Citywide Electrical Repair and Maintenance Services Presentation Made By: Jessee R. Dagen, Esq., Contracting Officer Thursday, May 31, 2018 Location: Committee Room #2, 2nd Floor – 55 Trinity Avenue, SW Time: 10:30 am EDT © 2007 Microsoft Corporation. All rights reserved. Microsoft, Windows, Windows Vista and other product names are or may be registered trademarks and/or trademarks in the U.S. and/or other countries. The information herein is for informational purposes only and represents the current view of Microsoft Corporation as of the date of this presentation. Because Microsoft must respond to changing market conditions, it should not be interpreted to be a commitment on the part of Microsoft, and Microsoft cannot guarantee the accuracy of any information provided after the date of this presentation. MICROSOFT MAKES NO WARRANTIES, EXPRESS, IMPLIED OR STATUTORY, AS TO THE INFORMATION IN THIS PRESENTATION.
2
FC-10398, Citywide Electrical Repair and Maintenance Services
Welcome and Introductions Jessee R. Dagen, Esq., Contracting Officer City of Atlanta, Board of Ethics Mr. Carlos Santiago, Associate Ethics Officer Office of Contract Compliance Mr. Bruce Bell, Senior Contract Compliance Manager Office of Enterprise Risk Management Mr. Navarone Dozier, Risk Management Analyst Office of Enterprise Assets Management Vence Williams, Assistant Director Building Services James Buggs, Construction Project Manager Closing: Department of Procurement
3
FC-10398, Citywide Electrical Repair and Maintenance Services
Prohibited Contacts – “Black Out” Period Non-Authoritative Statements Plan Holders vs. Attendees at Conference Last Date for Addendum Questions: Monday, June 4, 2018, 1:00 p.m. EDT Proposal Due Date: Tuesday, June 19, :00 p.m. EDT
4
City of Atlanta Board of Ethics
Carlos Santiago Associate Ethics Officer
5
Office of Contract Compliance
Bruce Bell Senior Contract Compliance Manager
6
Office of Enterprise Risk Management
Navarone Dozier Risk Management Analyst
7
Office of Enterprise Assets Management
Summary of Services to be Performed Vence Williams, Assistant Director Building Services James Buggs, Construction Project Manager Opening the Floor for Questions & Answers (Statements Made in this Forum Today are Not Authoritative) All questions and responses provided are not considered authoritative until placed in writing to the attention of Jessee R. Dagen, Esq., Contracting Officer.
8
Contents of Proposals I. Informational Proposal
Proposals should include: I. Informational Proposal Volume I - Information drafted and provided by a Proponent Executive Summary Organizational Structure Resumes of Key Personnel Overall Experience, Qualifications and Performance on Previous Projects Management Plan and Service Approach Volume II – City of Atlanta Forms Required Submittals Appendix A– Office of Contract Compliance Forms Submit one (1) stamped “original” and seven (7) copies. 2 CDs - with one (1) CD, a duplicate of the “original” and one (1) CD, a redacted copy. Both in .pdf format II. Cost Proposal - Exhibit A.1 Submit one (1) stamped “original” and seven (7) copies in a separate sealed envelope. 2 CDs -with one (1) CD, a duplicate of the “original” and one (1) CD, a redacted copy. Both in .pdf format.
9
Next Anticipated Procurement Steps – After Proposal Due Date
Step 1: DOP will review Proposal(s) for Responsiveness Exhibit A.1 – Revenue Proposal Form 1 - Illegal Immigration Reform and Enforcement Act Forms (IIREA) Form 2 - Disclosure Form and Questionnaire and Authority to Transact Business Form 3 - Proponent Financial Disclosure Form Certification of Insurance Ability Form 4.2 – Certificate of Bonding Ability Form 5 - Acknowledgement of Addenda Form 6 - Proponent Contact Directory Form 7 - Reference List Form 8 – Proposal Bond (NOT APPLICABLE) Appendix A- Office of Contract Compliance Appendix C – IIREA Preview Participation Form (Optional) Step 2: DOP will submit only responsive proposals to internal City stakeholders to review for responsibility: Office of Contract Compliance: Appendix A Forms Office of Enterprise Risk Management: Form 3: Proponents’ Financial Disclosure Statements Office of Enterprise Assets Management
10
Part IV: Required Submittals
11
Form 1: Illegal Immigration Reform and Enforcement Act Forms
12
Form 2: Contractor Disclosure and Declaration Form
13
Form 2: Contractor Disclosure and Declaration Form
14
Form 3: Proponent Financial Disclosure
15
Form 3: Proponent Financial Disclosure
16
Form 4.1: Certification of Insurance Ability
17
Form 4.2: Certification of Bonding Ability
18
Form 5: Acknowledgement of Addenda
19
Form 6: Proponent Contact Directory
20
Form 7: Reference List
21
Form 8: Proposal Bond
22
Reminders Addendum Question Deadline: Proposal Due Date:
Monday, June 4, 2018, 1:00 p.m. EDT **QUESTIONS RECEIVED THEREAFTER MAY NOT BE CONSIDERED** Proposal Due Date: Tuesday, June 19, 2018, 2:00 p.m. EDT **ABSOLUTELY NO PROPOSALS WILL BE ACCEPTED AFTER 2:00 P.M.** Primary Point of Contact: Jessee R. Dagen, Esq., Contracting Officer
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.