Presentation is loading. Please wait.

Presentation is loading. Please wait.

Dennis Li - HKCIC Lecturer

Similar presentations


Presentation on theme: "Dennis Li - HKCIC Lecturer"— Presentation transcript:

1 Dennis Li - HKCIC Lecturer
Principles of NEC Dennis Li - HKCIC Lecturer

2 Lecture 3 Communication and Time
Periods for reply Communication protocols Managing time Programme management Extension of Time and prolongation cost Acceleration Completion

3 Communication

4 NEC ECC Clause 13 - Communications
13.1 Each instruction, certificate, submission, proposal, record, acceptance, notification, reply and other communication which this contract requires is communicated in a form which can be read, copied and recorded. Writing is in the language of this contract 13.2 A communication has effect when it is received at the last address notified by the recipient for receiving communications or, if none is notified, at the address of the recipient stated in the Contract Data.

5 NEC ECC Clause 13 - Communications
13.3 If this contract requires the Project Manager, the Supervisor or the Contractor to reply to a communication, unless otherwise stated in this contract, he replies within the period for reply. 13.4 The Project Manager replies to a communication submitted or resubmitted to him by the Contractor for acceptance. If his reply is not acceptance, the Project Manager states his reasons and the Contractor resubmits the commu­nication within the period for reply taking account of these reasons. A reason for withholding acceptance is that more information is needed in order to assess the Contractor's submission fully.

6 NEC ECC Clause 13 - Communications
13.5 The Project Manager may extend the period for reply to a communication if the Project Manager and the Contractor agree to the extension before the reply is due. The Project Manager notifies the Contractor of the extension which has been agreed. 13.6 The Project Manager issues his certificates to the Employer and the Contrac­tor. The Supervisor issues his certificates to the Project Manager and the Contractor. 13.7 A notification which this contract requires is communicated separately from other communications.

7 NEC ECC Clause 13 - Communications
13.8 The Project Manager may withhold acceptance of a submission by the Contractor. Withholding acceptance for a reason stated in this contract is not a compensation event.

8 Programme

9 Programme and Time Clause 31.2: The Contractor shows on each programme which he submits for acceptance the starting date, access dates, Key Dates and Completion Date, planned Completion, the order and timing of the operation which the Contractor plans to do in order to Provide the Works, the order and timing of the work of the Employer and Others as last agreed with them by the Contractor or, if not so agreed, as stated in the Works Information If programme not accepted:• Neither party clear on the Completion Date and contractor entitlement in terms of outturn cost• 25% of the cumulative Price for Work Done to Date deducted until first programme submitted showing the information the contract requires• Employer will in the absence of a newly accepted programme assess change (CE’s) on the last accepted programme • Important to both parties programme regularly accepted.• Otherwise enjoy the traditional end of project bun-fight to sort out the final account… Clause 64 Project Manager’s Assessment The Project Manager may make his own assessment of a compensation event for the reasons stated in Clause 64.1:• if the Contractor has not submitted a quotation within the timescale,• the Contractor has not assessed the compensation event correctly and does not instruct the Contractor to submit a revised quotation,• he has not submitted a programme or alterations to a programme which this contract requires him to submit or• If, the Project Manager has not accepted the Contractor’s latest programme for one of the reasons stated in this contract. Employer:• Review programme well within two week response period and give early comment • Aim for a one week response for programme acceptance where ever possible• Give clear specific detailed reasons why it is not accepted - only four reasons under the contract• Accept with comments – comments being minor issues that can be put right on the next programme issue Contractor:• Make sure your programme fully complies with clause 31.2 (and 32.1)• Show difference between planned completion/ Completion Date• Comprehensive programme narrative with each submission• Programme review meeting during acceptance period with PM• If no response to programme – call a meeting and try to bring it to a head

10 Programme and Time Clause 31.2:
the dates when the Contractor plans to meet each Condition stated for the Key Dates and to complete other work needed to allow the Employer and Others to do their work, provisions for float, time risk allowances, health and safety requirements, and the procedures set out in this contract Programme and Time If programme not accepted:• Neither party clear on the Completion Date and contractor entitlement in terms of outturn cost• 25% of the cumulative Price for Work Done to Date deducted until first programme submitted showing the information the contract requires• Employer will in the absence of a newly accepted programme assess change (CE’s) on the last accepted programme • Important to both parties programme regularly accepted.• Otherwise enjoy the traditional end of project bun-fight to sort out the final account… Clause 64 Project Manager’s Assessment The Project Manager may make his own assessment of a compensation event for the reasons stated in Clause 64.1:• if the Contractor has not submitted a quotation within the timescale,• the Contractor has not assessed the compensation event correctly and does not instruct the Contractor to submit a revised quotation,• he has not submitted a programme or alterations to a programme which this contract requires him to submit or• If, the Project Manager has not accepted the Contractor’s latest programme for one of the reasons stated in this contract. Employer:• Review programme well within two week response period and give early comment • Aim for a one week response for programme acceptance where ever possible• Give clear specific detailed reasons why it is not accepted - only four reasons under the contract• Accept with comments – comments being minor issues that can be put right on the next programme issue Contractor:• Make sure your programme fully complies with clause 31.2 (and 32.1)• Show difference between planned completion/ Completion Date• Comprehensive programme narrative with each submission• Programme review meeting during acceptance period with PM• If no response to programme – call a meeting and try to bring it to a head

11 Programme and Time Clause 31.2:
the dates when, in order to Provide the Works in accordance with his programme, the Contractor will need access to a part of the Site if later than its access date, Acceptance, Plant and Materials and other things to be provided by the Employer and Information from Others, for each operation, a statement of how the Contractor plans to do the work identifying the principal Equipment and other resources which he plans to use and Other information which the Works Information requires the Contractor to show on a programme submitted for acceptance If programme not accepted:• Neither party clear on the Completion Date and contractor entitlement in terms of outturn cost• 25% of the cumulative Price for Work Done to Date deducted until first programme submitted showing the information the contract requires• Employer will in the absence of a newly accepted programme assess change (CE’s) on the last accepted programme • Important to both parties programme regularly accepted.• Otherwise enjoy the traditional end of project bun-fight to sort out the final account… Clause 64 Project Manager’s Assessment The Project Manager may make his own assessment of a compensation event for the reasons stated in Clause 64.1:• if the Contractor has not submitted a quotation within the timescale,• the Contractor has not assessed the compensation event correctly and does not instruct the Contractor to submit a revised quotation,• he has not submitted a programme or alterations to a programme which this contract requires him to submit or• If, the Project Manager has not accepted the Contractor’s latest programme for one of the reasons stated in this contract.

12 Programme and Time Clause 31.3:
Within 2 weeks of the Contractor submitting a programme to him for acceptance, the Project Manager either accepts the programme or notifies the Contractor of his reasons for not accepting it. A reason for not accepting a programme is that The Contractor’s plans which it shows are not practicable It does not s how the information which this contract requires, It does not represent the Contractor’s plans realistically or It does not comply with the Works Information. If programme not accepted:• Neither party clear on the Completion Date and contractor entitlement in terms of outturn cost• 25% of the cumulative Price for Work Done to Date deducted until first programme submitted showing the information the contract requires• Employer will in the absence of a newly accepted programme assess change (CE’s) on the last accepted programme • Important to both parties programme regularly accepted.• Otherwise enjoy the traditional end of project bun-fight to sort out the final account… Clause 64 Project Manager’s Assessment The Project Manager may make his own assessment of a compensation event for the reasons stated in Clause 64.1:• if the Contractor has not submitted a quotation within the timescale,• the Contractor has not assessed the compensation event correctly and does not instruct the Contractor to submit a revised quotation,• he has not submitted a programme or alterations to a programme which this contract requires him to submit or• If, the Project Manager has not accepted the Contractor’s latest programme for one of the reasons stated in this contract.

13 Programme and Time Clause 32.1:
The Contractor shows on each revised programme The actual progress achieved on each operation and its effect upon the timing of the remaining work, The effects of implemented compensation events, How the Contractor plans to deal with any delays and to correct notified Defects and Any other changes which the Contractor proposes to make to the Accepted Programme. If programme not accepted:• Neither party clear on the Completion Date and contractor entitlement in terms of outturn cost• 25% of the cumulative Price for Work Done to Date deducted until first programme submitted showing the information the contract requires• Employer will in the absence of a newly accepted programme assess change (CE’s) on the last accepted programme • Important to both parties programme regularly accepted.• Otherwise enjoy the traditional end of project bun-fight to sort out the final account… Clause 64 Project Manager’s Assessment The Project Manager may make his own assessment of a compensation event for the reasons stated in Clause 64.1:• if the Contractor has not submitted a quotation within the timescale,• the Contractor has not assessed the compensation event correctly and does not instruct the Contractor to submit a revised quotation,• he has not submitted a programme or alterations to a programme which this contract requires him to submit or• If, the Project Manager has not accepted the Contractor’s latest programme for one of the reasons stated in this contract.

14 Programme and Time Clause 32.2:
The Contractor submits a revised programme to the Project Manager for acceptance Within the period for reply after the Project Manager has instructed him to, When the Contractor chooses to and, in any case, At no longer interval than the interval stated in the Contract Data from the stating date until Completion of the whole of the works. If programme not accepted:• Neither party clear on the Completion Date and contractor entitlement in terms of outturn cost• 25% of the cumulative Price for Work Done to Date deducted until first programme submitted showing the information the contract requires• Employer will in the absence of a newly accepted programme assess change (CE’s) on the last accepted programme • Important to both parties programme regularly accepted.• Otherwise enjoy the traditional end of project bun-fight to sort out the final account… Clause 64 Project Manager’s Assessment The Project Manager may make his own assessment of a compensation event for the reasons stated in Clause 64.1:• if the Contractor has not submitted a quotation within the timescale,• the Contractor has not assessed the compensation event correctly and does not instruct the Contractor to submit a revised quotation,• he has not submitted a programme or alterations to a programme which this contract requires him to submit or• If, the Project Manager has not accepted the Contractor’s latest programme for one of the reasons stated in this contract.

15 Example Programme 1 Activities Duration Commencement Activity 1
Planned Completion Completion Date Critical Path Terminal Float Risk Allocance Float Float

16 Definitions Critical Path is the longest sequence of activities in a project plan which must be completed on time for the project to complete on the due date. Float – The time by which an activity may be delayed without affecting the overall project duration. Terminal Float – the amount of float between planned completion and the Contract Completion Date Risk allowance – reasonable allowance to account for risks in Contractor’s programme

17 FLOAT AND OWNERSHIP Terminal float – belongs to the Contractor?
Time risk allowance – belongs to the Contractor Activity float / free float – belongs to the first to use it

18 Who owns the float?: Employer CE
© NEC Contracts Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 operation 1 operation 2 operation 3 CE001 operation 4 operation 5 planned Completion Completion Date ‘Operation 4’ has to start after CE001 2 weeks float

19 Who owns the float?: Employer CE
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 operation 1 operation 2 operation 3 CE001 operation 4 operation 5 planned Completion Completion Date Clause 63.3 A delay to the Completion Date is assessed as the length of time that, due to a compensation event, planned Completion is later than planned Completion as shown on the Accepted Programme 1 week float planned Completion is unaffected, the Employer takes advantage of the float

20 Who owns the float? Critical operations: 2 weeks float
© NEC Contracts Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 operation 1 operation 2 operation 3 operation 4 operation 5 planned Completion Completion Date Critical operations: 2 weeks float Non-critical operations:

21 Who owns the float?: Contractor delay
© NEC Contracts Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 operation 1 operation 2 operation 3 Contractor delay operation 4 operation 5 planned Completion Completion Date This affects the start date of ‘Operation 4’ 2 weeks float

22 Who owns the float?: Contractor delay
© NEC Contracts Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 operation 1 operation 2 operation 3 Contractor delay operation 4 operation 5 planned Completion Completion Date But……..what happens if both occur? No float remains The Contractor takes advantage of the float 22

23 Who owns the float? Critical operations: 2 weeks float
© NEC Contracts Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 operation 1 operation 2 operation 3 operation 4 operation 5 planned Completion Completion Date Critical operations: 2 weeks float Non-critical operations:

24 Who owns the float?: Employer CE
© NEC Contracts Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 operation 1 operation 2 operation 3 CE001 operation 4 operation 5 planned Completion Completion Date ‘Operation 4’ has to start after CE001 2 weeks float

25 It’s who gets there first!
Who owns the float? It’s who gets there first! © NEC Contracts Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 operation 1 operation 2 operation 3 CE001 operation 4 operation 5 planned Completion Completion Date 1 weeks float

26 It’s who gets there first!
Who owns the float? It’s who gets there first! Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 operation 1 operation 2 operation 3 CE001 operation 4 operation 5 planned Completion Completion Date Clause 63.3 A delay to the Completion Date is assessed as the length of time that, due to a compensation event, planned Completion is later than planned Completion as shown on the Accepted Programme 1 weeks float planned Completion is unaffected, the Employer takes advantage of the float

27 It’s who gets there first!
Who owns the float? It’s who gets there first! © NEC Contracts Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 operation 1 operation 2 operation 3 CE001 Contractor delay operation 4 operation 5 planned Completion Completion Date This effects the start date of ‘Operation 4’ 1 weeks float

28 It’s who gets there first!
Who owns the float? It’s who gets there first! © NEC Contracts Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 operation 1 operation 2 operation 3 CE001 Contractor delay operation 4 operation 5 planned Completion Completion Date

29 It’s who gets there first!
Who owns the float? It’s who gets there first! © NEC Contracts Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 operation 1 operation 2 operation 3 CE001 Contractor delay operation 4 operation 5 planned Completion Completion Date Not a race Shared float Importance of keeping the programme up to date Delay, no CE 29

30 Who owns the float?: Contractor delay
© NEC Contracts Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 operation 1 operation 2 operation 3 Contractor delay operation 4 operation 5 planned Completion Completion Date This effects the start date of ‘Operation 4’ 2 weeks float

31 Who owns the float?: Contractor delay
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 operation 1 operation 2 operation 3 Contractor delay operation 4 operation 5 planned Completion Completion Date No float remains The Contractor takes advantage of the float

32 It’s who gets there first!
Who owns the float? It’s who gets there first! © NEC Contracts Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 operation 1 operation 2 operation 3 CE001 Contractor delay operation 4 operation 5 planned Completion Completion Date CE001 must complete before ‘Operation 4’ can start

33 It’s who gets there first!
Who owns the float? It’s who gets there first! © NEC Contracts Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 operation 1 operation 2 operation 3 CE001 Contractor delay operation 4 operation 5 planned Completion Completion Date

34 It’s who gets there first!
Who owns the float? It’s who gets there first! © NEC Contracts Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 operation 1 operation 2 operation 3 CE001 Contractor delay operation 4 operation 5 planned Completion Completion Date planned Completion is now 1 week later

35 It’s who gets there first!
Who owns the float? It’s who gets there first! Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 operation 1 operation 2 operation 3 CE001 Contractor delay operation 4 operation 5 planned Completion Completion Date Clause 63.3 A delay to the Completion Date is assessed as the length of time that, due to a compensation event, planned Completion is later than planned Completion as shown on the Accepted Programme The CE will cover the one week effect.

36 It’s who gets there first!
Who owns the float? It’s who gets there first! © NEC Contracts Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 operation 1 operation 2 operation 3 Contractor delay operation 4 operation 5 planned Completion Completion Date What happens if the Contractor is already in delay and we notify a CE? i.e. planned Completion is after the Completion Date Delay

37 It’s who gets there first!
Who owns the float? It’s who gets there first! © NEC Contracts Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 operation 1 operation 2 operation 3 CE001 Contractor delay operation 4 operation 5 planned Completion Completion Date CE001 must complete before ‘Operation 4’ can start

38 It’s who gets there first!
Who owns the float? It’s who gets there first! Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 operation 1 operation 2 operation 3 CE001 Contractor delay operation 4 operation 5 planned Completion Completion Date Clause 63.3 A delay to the Completion Date is assessed as the length of time that, due to a compensation event, planned Completion is later than planned Completion as shown on the Accepted Programme 1 further week Delay The CE will cover the one week effect. 38

39 This belongs to the Contractor
Who owns the terminal float? © NEC Contracts Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 operation 1 operation 2 operation 3 operation 4 operation 5 planned Completion Completion Date How do we know? Which clause states this? This belongs to the Contractor Terminal float

40 Who owns the terminal float?
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 operation 1 operation 2 operation 3 CE001 operation 4 operation 5 planned Completion Completion Date This effects the start date of ‘Operation 3’ Terminal float

41 Who owns the terminal float?
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 operation 1 operation 2 operation 3 CE001 operation 4 operation 5 planned Completion Completion Date Terminal float

42 Who owns the terminal float?:
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 operation 1 operation 2 operation 3 CE001 operation 4 operation 5 planned Completion Completion Date Clause 63.3 A delay to the Completion Date is assessed as the length of time that, due to a compensation event, planned Completion is later than planned Completion as shown on the Accepted Programme Terminal float The CE will cover the one week effect.

43 Other Problems Concurrent delay
Employer’s risk event occurs after completion date Evaluate by planned progress? Actual Progress?

44 Bridge forms critical path (6 months to construct)
Approach Road has 66d of “float” 66d THE INITIAL PROGRAMME (Carefully planned and resourced)

45 1st window VO1 Increased depth: 20d additional excavation Subcontract award after 25d (5d late) Paving not commenced due to material shortage 20d delay due to VO1 SITUATION AS AT END OF FEB 07 (Close of First ‘Window’)

46 Events in First “Window” (Jan/Feb)
Day 1: Excavation starts; S/C bids compiled; Day 10: VO1 issued, increasing the depth of abutment foundations – 20d extra excavation required; Day 25: Road Subcontract awarded (NB. 5d late); Day 58 (End of window): (i) Abutments excavation almost completed; (ii) Road paving cannot be sourced (materials shortage)

47 Events in 2nd “Window” (Mar/Apr)
Day 60: Excavation of abutments completed; Day 75: Pavement laying commenced Day 90: Concreting of abutments completes slowly, taking 30d in total (so a 14d delay); Day 100: VO2 – major instruction for a further ½km of road, in difficult ground (on piles) – planned at 21d to source piling s/c, 30d to drive 30 piles, 20d to test, 30d to construct new road & drains, and 15d for street furniture. A total duration of 114d is required. Day 120 (End of window): No further delays, but due to massive VO2, the approach roads are now on the critical path

48 Slow Concreting of Abutments (14d delay)
2nd window Slow Concreting of Abutments (14d delay) 21d VO2 New 0.5km of road; in poor ground (on piles) 48d delay; (20d VO1, 14d slow abutments; 14d VO2) SITUATION AS AT END OF APR 07 (Close of Second ‘Window’)

49 Events in 3rd “Window” (May/Jun)
Day 121: Falsework erectors go on strike for the whole month of May Day 135: Contractor says that he will mitigate the delay by doubling up resources on the commissioning stage; Day 160: VO3 – 10 more piles instructed in the new piled approach section, these will take an extra 10 days to complete Day 181 (End of window): No further delays, but due to the month-long strike, the bridge has become once again more critical than the approach road

50 One month lost due to falsework s/c strike
3rd window One month lost due to falsework s/c strike Mitigation: commissioning now only 8d 21d VO3: Additional piles instructed at new road VO3 66d delay; (20d VO1, 14d slow abutments; 14d VO2; 25d strike; -7d mitigation) SITUATION AS AT END OF JUN 07 (Close of Third ‘Window’)

51 Events in 4th “Window” (Jul/Aug)
Day Day 243: Further problems with Falsework erectors – not all were pleased with strike settlement terms, and productivity suffers. Day 243 (End of window): No further delays; approach road completed bar for commissioning; but the elevated bridge concrete deck only managed completion at the very end of this period. The bridge thus remained more critical than the approach road throughout.

52 SITUATION AS AT END OF AUG 07 (Close of Fourth ‘Window’)
More than one further month lost due to poor falsework s/c productivity 21d 98d delay; (20d VO1, 14d slow abutments; 14d VO2; 25d strike; -7d mitigation; 32d poor falsework productivity) SITUATION AS AT END OF AUG 07 (Close of Fourth ‘Window’)

53 Events in 5th “Window” (Sep/Oct)
Day 270: VO4, some new road markings and revised drainage causes an extra 10d of work. Day 289 (End of project): The project completes on 16 October 2007, some 108 days late. Critical VOs:- VO1=20d, VO2=14d; VO4=10d: Total = 44d

54 New Road marking scheme
5th window 21d VO4 New Road marking scheme 108d -108 SITUATION AS AT END OF OCT 07 (Close of Fifth ‘Window’)

55 20d 14d 10d

56 As-Built Subtracted Analysis
Take the as-built programme, and subtract the delays which the contractor has suffered (which are not to his own default). This gives rise to a theoretical date, the date on which the contractor would have finished but for the delays The difference between the ABBF date, and the actual completion date represents the potential entitlement to EOT

57 AS-BUILT BUT-FOR / AS-BUILT SUBTRACTED ANALYSIS
VO1 21d VO2 VO3 VO4 -108 AS-BUILT BUT-FOR / AS-BUILT SUBTRACTED ANALYSIS

58 AS-BUILT BUT-FOR / AS-BUILT SUBTRACTED ANALYSIS
-78 AS-BUILT BUT-FOR / AS-BUILT SUBTRACTED ANALYSIS

59 As-Built Subtracted Analysis
The “longest path” is favoured Only the VOs on the longest path feature in the subtraction, irrespective of the contemporary criticality of other VOs Thus, VO1 (20d) and VO4 (10d) are those which, when subtracted, cause the ABBF date to be collapsed back in time. Thus the potential EOT entitlement here is 30d (cf. 44d in the windows analysis)

60 As-Planned Impacted Analysis
The initial programme (warts and all) is taken, and into it are impacted all of the delays which the contractor has suffered The impacts are ‘added’ into the initial network; sometimes this is done in ‘real time’, but this causes problems if the delays are caused late due to the contractor’s own problems (e.g. a VO instructed at a late stage merely because of earlier contractor’s delays);

61 THE INITIAL PROGRAMME (Carefully planned and resourced)

62 THE INITIAL PROGRAMME IMPACTED WITH VO1-VO4

63 As-Planned Impacted Analysis
The impacts take no account of progress, or of any of the contractor’s own defaults. The resultant date is again a theoretical date, perhaps best described as the date for which the contractor would have programmed if it had know about all of the additionally instructed work at the outset; If the VOs are impacted in chronological order, then they all figure in this example: VO1=20d; VO2=28d*; VO3=10d; VO4=10d: Total = 68d (cf. 30d ABBF, 44d windows analysis) * Net delay given initial float and the prior occurrence of VO1

64 City Inn v Shepherd Construction [Appeal: 2010]
CONCURRENT DELAY (Lord Carloway) The initial exercise to be carried out by the architect occurs upon the application of the contractor, who will have requested an extension of time by intimating, under clause 25.2, that the progress of the Works "is being or is likely to be delayed". He will claim that a Relevant Event has been the, or at least a, cause of the delay. The architect then has to decide whether he considers that the completion of the Works is likely to be delayed by a Relevant Event beyond the Completion Date (clauses and 2).

65 City Inn v Shepherd Construction [Appeal: 2010]
CONCURRENT DELAY (Lord Carloway) This provision is designed to allow the contractor sufficient time to complete the Works, having regard to matters which are not his fault (i.e. Relevant Events). This does not, at least strictly, involve any analysis of competing causes of delay or an assessment of how far other events have, or might have, caused delay beyond the Completion Date. It proceeds, to a large extent, upon a hypothetical assumption that the contract has proceeded, and will proceed, without contractor default. It involves an assessment, on that assumption, of the delay which would have been caused to the Completion Date purely as a result of the Relevant Event.

66 City Inn v Shepherd Construction [Appeal: 2010]
CONCURRENT DELAY (Lord Carloway) But the exercise remains one of looking at the Relevant Event and the effect it would have had on the original (or already altered) Completion Date. If a Relevant Event occurs (no matter when), the fact that the Works would have been delayed, in any event, because of a contractor default remains irrelevant. In that respect, the view of HHJ Seymour QC in Royal Brompton Hospital NHS Trust v Hammond & Others (No 7) [2001] 76 Con LR 148 (at para 31), that a Relevant Event falls to be disregarded if a pre-existing contractor default would nonetheless have caused the delay, appears to be in error.

67 Key Date 30.3 – The Contractor does the work so that the Condition stated for each Key Date is met by the Key Date. 25.3 – If the Project Manager decides that the work does not meet the Condition stated for a Key Date by the date stated and, as a result, the Employer incurs additional cost either in carrying out work or by paying an additional amount to Others in carrying out work on the same project, the additional cost which the Employer has paid or will incur is paid by the Contractor. The Project Manager assesses the additional cost within four weeks of the date when the Condition for the Key Date is met. The Employees right to recover the additional cost is his only right in these circumstances.

68 Cl Acceleration 36.1 – The Project Manager may instruct the Contractor to submit a quotation for an acceleration to achieve Completion before the Completion Date. The Project Manager states changes to the Key Dates to be included in the quotation. A quotation for an acceleration comprises proposed changes to the Prices and a revised programme showing the earlier Completion Date and the changed Key Dates. The Contractor submits details of his assessment with each quotation The Contractor submits a quotation or gives his reasons for not doing so within the period for reply.

69 Cl. 35 – Take over 35.1 – The Employer need not take over the works before the Completion Date if it is stated in the Contract Data that he is not willing to do so. Otherwise the Employer takes over the works not later than two weeks after Completion. 35.2 – The Employer may use any part of the works before Completion has been certified. If he does so, he takes over the part of the works when he begins to use it except if the use is for a reason stated in the Works Information or to suit the Contractor's method of working. 35.3 – The Project Manager certifies the date upon which the Employer takes over any part of the works and its extent within one week of the date.


Download ppt "Dennis Li - HKCIC Lecturer"

Similar presentations


Ads by Google