Introduction Brief presentation of how we intend to execute the proposed project. Who were are Chris Saville Senior Site Manager John Chapple Design Manager
3
3D View of proposed development
4
Proposed Site Plan
5
Perspective Views - 1
6
Perspective Views - 2
7
Perspective Views - 3
8
Summary Programme of Construction Works
10
Phasing of Construction Work 1 – Temporary Parking 2 – New Extension 3 & 4 New Car Park and external areas
11
Phase 2 – New Extension PilingSteel Frame Roofing Windows Timber Cladding
12
Phase 2 – New Extension Drylining Ceilings Carpentry Mechanical PlantElectrical Installation
13
New Car Park
14
Phase 3 & 4 - Demolish Existing Building & complete external areas Demolition External Hard Landscaping Landscaping
15
Communication Chris Saville & Site Team First Point of Contact – Phone & Email Regular Co-ordination meeting with school designated reps Regular Newsletter to school and neighbourhood CCS – Project part of this scheme which independently inspects and scores the site
16
Finally Any Questions