SOUTH SACRAMENTO COUNTY STREAMS GROUP UPDATE
Marshall Marik Project Manager South Sacramento Streams Group Sacramento District January 17, 2013
2
Morrison Creek Construction Along Union Pacific Railroad
Substantially complete except for the patrol road and final grading. Coordinating with State, SAFCA and City of Sacramento to provide information necessary for FEMA Letter of Map Revision.
3
Florin Creek Completed review of 35% plans.
Design scheduled to be completed in October Schedule dependent upon resolving conflicts with utilities and obtaining real estate rights for construction. Construction scheduled to start in May 2014.
4
Marshall Marik US Army Corps of Engineers 1325 J Street Sacramento, CA 95814-2922 (916) 557-7698