Chatham-Kent Health Alliance Facility Renewal and Capital Infrastructure Needs Tri Board Meeting October 26, 2010
2
Facility Renewal and Capital Infrastructure Needs October 2010 Chatham-Kent Health Alliance is a partnership of 3 hospital corporations: Public General ( PGH), St. Josephs Hospital ( SJH) and Sydenham District Hospital (SDH). Request to review current state and capital needs for facility upgrades PGH – dates back to 1954 SDH – dates back to 1955 Both facilities have reached a critical point in their life expectancy and are in need of major investment to maintain patient and staff safety.
3
Facility Renewal and Capital Infrastructure Needs October 2010 !magine redevelopment project is 10 plus years away Inadequate resources available over the years to support infrastructure upgrades Sydenham and Public General buildings are outdated and do not meet code in many areas, (i.e. building, medical gas, fire codes, etc.)
4
Facility Renewal and Capital Infrastructure Needs October 2010 Costs are estimates Many upgrades cannot be done in isolation of one another Any changes to current systems will require all code upgrades Significant capital facility upgrades will require Ministry approval Cannot bring certain systems up to code given building structure limitations Does not include capital needs for the SJC or offsite properties, i.e. 47 Emma, MHA, adjacent houses. Multi-year coordinated plan and dedicated annual resources required to proceed with any upgrades
5
Facility Renewal and Capital Infrastructure Needs October 2010 References used: Cohos Evamy Facility Audit Report July 2009 Honeywell Energy and Facility Renewal Report 2009 Emergency Department Hay Study 2009 (LHIN study) Asbestos Audits – Advanced Environmental Corporation 2007 Stantec Facility Audit Report SDC 2005 Applied Building Sciences LTD Facility Audits – 2002 & 2004 PGC and SDC Additional Inspections, i.e. Medical Gas, Fire Marshall, HIROC, Roofing Inspections, etc. External Contractors and CKHA Engineering Staff
6
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus
7
Roofing Cost Estimate $1,000,000 Multi-Year project will be complete 2010-2011 $ not included in total request
8
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Roof Replacement Plan
9
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Windows Cost Estimate $ 1,500,000 Connected to envelope deterioration project Add: Building Envelope Asbestos Abatement
10
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Exterior Window
11
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Interior Window
12
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Building Envelope Cost Estimate $ 1,500,000 + Connected to Window deterioration project Add: Window Replacement Asbestos Abatement
13
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Heat Loss from Building Envelope
15
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Balconies Cost Estimate $330,000 Deterioration to the point of unsafe Do not meet code Currently locked for safety, no access Add: Building Envelope repair if balconies need to be removed
16
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Exterior Balcony
18
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Fire System Upgrade Cost estimate $ 1,000,000 Does not meet code Currently equipped with smoke and heat detectors Must bring up to code when doing any renovation (only 2 sprinklers at present time) Add: Structural changes (Ceiling heights) Asbestos abatement Electrical upgrade
19
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Elevators Upgrade Cost Estimate $ 250,000 Interior Upgrades 2010 – floors, walls, lighting Control Systems need complete upgrade Only one elevator accommodates a stretcher Add: Electrical system upgrade Asbestos abatement
20
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Elevator Mechanical Room
21
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Elevator Control Panels
22
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Ventilation System Upgrade Cost Estimate $5,000,000 - $7,000,000 End of life, does not meet code Current ceiling heights do not allow for proper replacement to meet code Add: Structural Changes (ceiling heights) Electrical upgrade Fire system upgrade Medical gas system upgrade Asbestos abatement
23
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Operating Room Air Handler Manual controlled, No humidification – original unit
24
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus General Air Supply – East Wing Dampers are not working, over 15 years ago 35% of coils were removed do to coils were leaking (frozen), no humidification Never reinstalled
25
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Medical gas system upgrade Cost Estimate $ 500,000 System does not meet code, any changes to the system will require the entire system be brought up to code Add: Structural changes (walls and ceilings) Asbestos abatement
26
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Asbestos Abatement Cost estimate $ 2,000,000 Must be factored in to any and all changes to SDC Add: Structural changes (walls and ceilings)
27
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Sanitary and Storm drain piping Cost Estimate $ 3,000,000 Does not meet code (Asbestos piping) Current piping is all cracked Requires major demolition to access prior to any potential repair Add: Structural changes (walls and ceilings) Asbestos abatement
28
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Plumbing Stack – Deteriorated Sewer Piping
29
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Deteriorated/ Cracked Piping all located in brick pipe chase
30
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Discovery of Sewer Piping Installation, after leak investigation
31
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Waterlines Cost Estimate $ 2,000,000 Does not meet code (galvanized piping) Current piping is corroding Risers are located in brick pipe chases Add: Structural changes (walls and ceilings) Asbestos abatement
32
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Hot Water Supply Line Corrosion
34
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Discovered During Recent Repair - Laundry
35
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Boilers - Replacement Cost Estimate $ 200,000 End of life RFP issues September 2010 for replacement of one boiler Add: Electrical upgrade Asbestos abatement
36
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Steam and Hot Water Boilers
37
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Deteriorated Boiler Tubing
38
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Chiller Replacement Cost Estimate $ 275,000 End of life Supplies only the OR Add: Electrical upgrade Asbestos abatement
39
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Operating Room Chiller
40
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Heating system upgrade (Radiant heating) Cost Estimate $ 210,000 End of life Add: Structural changes (walls and ceilings) Asbestos abatement There is an in-floor heating system on the first floor in part of the emergency, ambulatory care department and both side of the hallway in the West wing. Source of leak cannot be located as system is buried in concrete. This system is shut down and not in use.
41
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Electrical system upgrade Cost Estimate $ 1,000,000 System is obsolete Does not meet code Switched are no longer manufactured Add: Structural changes (ceilings and walls) Asbestos abatement
42
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Old Electrical Panels
43
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus OR Upgrades Cost Estimate $ 1,000,000 Does not meet current code and standards Consideration should be given to closing this section if continues to function as regular OR Add: Electrical upgrade Medical air systems upgrade Ventilation system upgrade Structural changes (walls and ceiling) Asbestos abatement
44
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Installation of negative pressure rooms Cost Estimate $ 500,000 Currently no negative pressure room Safety risk for airborne illness Current patients transferred to Chatham Add: Electrical system upgrade Medical air system upgrade Plumbing system upgrade Ventilation system upgrade Structural changes (walls and ceiling) Asbestos abatement
45
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Removal of Sewer tank Cost Estimate $ 40,000 – $ 50,000 Current Emergency Department partly build on a sewer holding tank 2010-2011 Capital plan – drain and connect to municipal line
46
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Structural/Building reinforcements upgrade Cost Estimate $ 2,000,000 Any changes in use or modification to the floor layout of the 1967 structure will require reinforcement of the structural system below the affected area. (Cohos pg. B-3)
47
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Renovation to patient rooms Cost Estimate $ 4,000,000 Current rooms do not meet code Washrooms are small and inaccessible Do not meet Infection Control standards – sinks are located outside of washroom Add: Plumbing upgrade Electrical system upgrade Ventilation system upgrade Medical air system upgrade Structural changes (walls and ceiling) Asbestos abatement
48
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Patient Washroom & Outside Sink
49
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus ED Renovations Cost Estimate $ 500,000 Emergency Department LHIN Hay study - physical plant is inadequate by current standards
50
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Accessibility Accessibility for Ontarians with Disabilities Act, 2005 (AODA) Unable to determine cost at this point Add: Structural changes (walls and ceilings)
51
Facility Renewal and Capital Infrastructural Needs October 2010 – Sydenham Campus We require an investment of approximately $27,000,000- $30,000,000 to maintain this facility in an acceptable state Costs are construction related costs only. Relocation, moves, temporary set ups etc. needs to be factored into to overall project Additional Engineering study required if direction is to proceed with only sections of the building upgraded as systems are interconnected Recommendation – dedicated resources to maintain facility while proceeding to fast track cost of a new facility
52
Facility Renewal and Capital Infrastructure Needs October 2010 – Public General Campus
53
Roofing Cost Estimate $ 500,000 Multi year roofing plan in place HIRF investment planned for 2010
54
Facility Renewal and Capital Infrastructure Needs October 2010 – Public General Campus Ventilation system upgrade Cost Estimate $ 4,000,000 End of life Does not meet code Current ceiling heights do not allow for proper replacement to meet code Add: Asbestos abatement Electrical system upgrade Structural changes (walls and ceiling)
55
Facility Renewal and Capital Infrastructure Needs October 2010 – Public General Campus Obsolete Air Handling Unit PG.A43 Induction unit, Perimeter heating and cooling Dampers not working (manual controlled)
56
Facility Renewal and Capital Infrastructure Needs October 2010 – Public General Campus Obsolete Air Handling Unit PG.A45 Part of Maternity SE/SW
57
Facility Renewal and Capital Infrastructure Needs October 2010 – Public General Campus Fire system and wiring upgrade Cost Estimate $ 295,000 Some PGC is already done from previous renovations Other does not meet code, must bring system up to code when doing any renovations Add: Structural changes (ceiling heights) Asbestos abatement
58
Facility Renewal and Capital Infrastructure Needs October 2010 – Public General Campus Building Envelope Cost Estimate $ 1,500,000 Moisture penetration from outside walls Repairs were done on South and South East walls Add: Asbestos Abatement
59
Facility Renewal and Capital Infrastructure Needs October 2010 – Public General Campus Exterior Pillar
60
Facility Renewal and Capital Infrastructure Needs October 2010 – Public General Campus Exterior Concrete Wall
61
Facility Renewal and Capital Infrastructure Needs October 2010 – Public General Campus Medical gas systems upgrade Cost Estimate $ 500,000 Some upgrades were done with previous renovations Does not meet code Any changes to the system will require the entire system be brought up to code Add: Structural changes (walls and ceilings) Asbestos abatement required system shutdown for changes
62
Facility Renewal and Capital Infrastructure Needs October 2010 – Public General Campus Elevator upgrades Cost Estimate $ 1,000,000 2 Elevators on the West wing 3 Elevators in the Centre 1 Elevator in centre is completely shutdown Add: Electrical system upgrade
63
Facility Renewal and Capital Infrastructure Needs October 2010 – Public General Campus Center Elevator Mechanical Room
64
Facility Renewal and Capital Infrastructure Needs October 2010 – Public General Campus West Elevator Mechanical Room
65
Facility Renewal and Capital Infrastructure Needs October 2010 – Public General Campus Asbestos Abatement Cost Estimate $ 2,000,000 Must be factored in to any and all changes to PGC Some areas amount and content is undetermined due to triple ceilings
66
Facility Renewal and Capital Infrastructure Needs October 2010 – Public General Campus West Mechanical Room – Interior Asbestos Walls
67
Facility Renewal and Capital Infrastructure Needs October 2010 – Public General Campus Structural/Building reinforcement upgrades Cost Estimate $ 2,000,000 Any building expansion or changes, the existing foundations will need to be under pinned and enlarged to accommodate the additional loads
68
Facility Renewal and Capital Infrastructure Needs October 2010 – Public General Campus Electrical system upgrade Cost Estimate $150,000 Replacements of obsolete panels Some areas were upgraded under previous renovations
69
Facility Renewal and Capital Infrastructure Needs October 2010 – Public General Campus Electrical Panels
71
Facility Renewal and Capital Infrastructure Needs October 2010 – Public General Campus Sanitary and storm sewer piping Cost Estimate $ 3,000,000 Current underground piping is deteriorated All underground piping repair need extensive construction to access (few have been done) Add: Asbestos abatement Structural changes (walls and ceilings)
72
Facility Renewal and Capital Infrastructure Needs October 2010 – Public General Campus Starting of Corrosion – Sewer Piping PGC
73
Facility Renewal and Capital Infrastructure Needs October 2010 – Public General Campus Sinks and toilet fixtures Cost Estimate $ 125,000 Infection controls issue as identified (overflow drains do not meet code)
74
Facility Renewal and Capital Infrastructure Needs October 2010 – Public General Campus Heating system upgrade (radiant heat) Cost Estimate $ 250,000 End of life Add: Asbestos abatement
75
Facility Renewal and Capital Infrastructure Needs October 2010 – Public General Campus Obsolete Terminal Induction Units - Patient Rooms – Original System 1969
76
Facility Renewal and Capital Infrastructure Needs October 2010 – Public General Campus Installation of additional Negative pressure room Cost Estimate $ 100,000 Infection control and safety risk for patient and staff Add: Structural changes (walls and ceiling) Electrical upgrade Medical air system upgrade sprinkler system upgrade Ventilation system upgrade Asbestos abatement
77
Facility Renewal and Capital Infrastructure Needs October 2010 – Public General Campus Medicine A/B, Patient room and washrooms accessibility Cost Estimate $ 300,000 Small, limited accessibility, patient and staff safety Changes needed to get patient beds into rooms Identified as safety issue at Executive Leadership Council Safety inspection
78
Facility Renewal and Capital Infrastructure Needs October 2010 – Public General Campus Accessibility Accessibility for Ontarians with Disabilities Act, 2005 (AODA) Unable to determine cost at this point Current building does not meet code under Accessibility legislation
79
Facility Renewal and Capital Infrastructure Needs October 2010 – Public General Campus We require an investment of approximately $16,000,000 to maintain this facility in an acceptable state Costs are construction related costs only. Relocation, moves, temporary set ups etc. needs to be factored into to overall project Additional Engineering study required if direction is to proceed with only sections of the building upgraded as systems are interconnected
80
Facility Renewal and Capital Infrastructure Needs October 2010 – Public General Campus Recommendation: Dedicated capital resources needed annually for next 5-10 years to maintain building to acceptable levels Continue to proceed with Master Program/ Master Planning costing out complete renewal replacement
81
Facility Renewal and Capital Infrastructure Needs October 2010 – Public General Campus Next Steps Priority list – safety issues and required capital Site visit with Engineers from Cohos Evamy October 28, 2010. Additional assessment and recommendations of capital projects as it relates to future development Clear vision of Sydenham site Contingency plans Dedicated capital
82
Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus and Public General Campus This report was prepared by: Beth Hall Director, Support Services Harrie Bos Manager, Engineering Services