Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009
2
New roof going up (over rooms 4 and 5) If you look closely, you will see the old wooden shingles which were the original roof dating back to the late 1890s 1 st Oct 2009
3
Admin empty ready for refurbishment to begin by 19 th Oct 2 nd Oct 2009
4
New roof being added to original school building dating back to 1874 – 2 nd Oct 2009
5
Major roof works completed – 5 th Oct 2009
6
Internal Demolition Begins 6 th Oct 2009
7
Classrooms 6-9 Demolition continues Oct 2009 Rooms emptied, carpets, ceilings, all electrics wiring removed ready for 1 st storey construction and concrete slab floor
8
Racking construction for refurbishment storage 14 th Oct 2009
9
Demolition continues Oct 2009
10
Corporate Services area refurbishment 19 th Oct 2009 Windows removed Ceiling Fans replaced
11
Floor demolition 19 th Oct 2009
12
Graeme Connelly supervising wall demolition 21 st Oct 2009
13
Internal framing and windows being cut in 27 th Oct 2009
14
Framing and floors added 28 th Oct 2009 Staff inspections of works
15
Outside area demolition ready for major works to begin 29 th Oct 2009