QXF schedule and milestones
P. Ferracin July 2nd, 2014
2
SQXF 3D CAD model P. Ferracin 02/07/2014
3
Critical milestones Schedule presented at Daresbury
Short model program: 5 CERN-LARP models, Start winding in 02-03/2014 Support structure available and qualified by early 2015 First magnet test in 05/2015 (3 LARP coils, 1 CERN coil) Long model program: 2 (CERN) + 3 (LARP) models, Start winding: LARP in 01/2015, CERN in 09/2015 Paolo Ferracin 08/05/2014
4
SQXF plan and schedule (Slide presented at Daresbury)
Definition of cable geometry in 06/2013 Update of coil design in 07/2013 Coil parts fabrication/optimization in progress Decision on end parts for first set of coils: 12/2013 End spacer turn-around: ~2 months Coil tooling Procurement Parallel coil fabrication LARP-CERN CERN: 1 Wind&Curing + 2 React&impreg LARP: 1 Wind&Curing + 2 React&impreg Winding and curing tooling by 11/2013 Reaction and impregnation tooling by 02/2014 Fabrication of full practice coil starts, both at CERN and in the US, in 02/2014 Fabrication of second set of coils starts in 03/15 (LARP), 05/15 (CERN) Possibility of fine tuning cable geometry by 06/2014 G. Ambrosio and P. Ferracin 13/11/2013
5
SQXF Status and milestone
From conceptual to engineering design: 03/13 Coil winding started in 03/14 Cu coil at CERN Nb3Sn coil by LARP P. Ferracin 02/07/2014
6
SQXF plan and schedule (Slide presented at Daresbury)
First “real” or “mirror” coil (#3) to completed by CERN in 12/14 (#1 or #2) to be completed by LARP by 9/14 G. Ambrosio and P. Ferracin 13/11/2013
7
SQXF plan and schedule (Slide presented at Daresbury)
Support structure fabricated and qualified by 02/15 First magnet assembly in 03/15 1 coil from CERN First test by 06/15 P. Ferracin 02/07/2014
8
SQXF plan and schedule (Slide presented at Daresbury)
Start winding LARP in 01/2015 CERN in 09/2015 First “real” or “mirror” coil LARP in 10/2015 CERN in 08/2016 First long prototype test LARP in 11/2016 CERN in 11/2017 P. Ferracin 02/07/2014
9
Long model program Plan and schedule
G. Ambrosio and P. Ferracin 13/11/2013