Melbourne Main Sewer Replacement Project Briefing for Canoeing Victoria August 2008
February 22, 2019
2
Overview Introductions and purpose of meeting Project background
Broad scope of works, Project status and program Key work areas Yarra River crossing Communication during construction Next steps Melbourne Main Sewer Replacement 2
3
MMSR Project background
The existing Melbourne Main Sewer (MMS) serves CBD, Docklands and surrounding areas Increasing population growth combined with the age of MMS has affected ability to perform adequately Need to replace or refurbish the MMS identified under asset management processes Essential service to enable compliance with government policy, legislation & other obligations Project on Water Plan and Corporate Plan Project team established: Melbourne Water, Connell Wager (project manager), GHD (designer) and John Holland (constructor) Melbourne Main Sewer Replacement 3
4
Melbourne Main Sewer Replacement 4
5
Broad scope of work New 2.3km long gravity main sewer from CBD to Hobsons Bay Main Sewer to replace section of existing Melbourne Main Sewer: New main sewer - 1.8m dia Branch & reticulation connection works - for City West Water and South East Water Miscellaneous works (e.g. billing meter, penstock) De-commissioning of Melbourne Main Sewer & North Wharf Pumping Station Associated temporary works Melbourne Main Sewer Replacement 5
6
Melbourne Main Sewer Replacement 6
7
Project status Announced by State Government in June 2007
In principle support from key stakeholders (e.g. Port Phillip City Council, VicRoads, Parks Victoria) Communications and community relations activities commenced in mid-2007 John Holland awarded construction contract in July 2008 Commence construction in August 2008 Melbourne Main Sewer Replacement 7
8
Project program – milestones
Detailed design completed April 2008 Project approvals June 2008 Construction contract award July 2008 Commence construction August 2008 River crossing works – 2010 Commission new sewer and undertake reticulation – 2012 Project completion Melbourne Main Sewer Replacement 8
9
Key work areas Sites: Fennell Reserve shaft Swallow Street shaft
Johnston Street shaft South Wharf and North Wharf shafts Yarra River crossing Wurundjeri Way shaft Connection of CWW Dudley Street Replacement Sewer Reticulation works to connect Lorimer Street Branch Sewer Temporary Sewer Bypassing Arrangements North Wharf Pumping Station removal Melbourne Main Sewer Replacement 9
10
Yarra River crossing Construction via three stage Cofferdam
Upstream of Charles Grimes Bridge Commence from South Wharf adjacent Melbourne Convention Centre construction site to North Wharf west of Shed 5 Commence preparation works August 2008 Melbourne Main Sewer Replacement 10
11
Phase 1 Melbourne Main Sewer Replacement 11
12
Phase 2 Melbourne Main Sewer Replacement 12
13
Phase 3 Melbourne Main Sewer Replacement 13
14
Cross Section Melbourne Main Sewer Replacement 14
15
Key Points Works will take place on river
Two thirds will remain open and navigable to river traffic at all times River traffic management in place at all times Strict environmental controls Advance notification of works Minimal spoil disposal Melbourne Main Sewer Replacement 15
16
Communication during construction
John Holland to manage day-to-day communication involving construction activities 1800 number and project address Project website on Melbourne Water website Community forums Works bulletins Newsletters Fact sheets on key project elements Stakeholder briefings Melbourne Main Sewer Replacement 16
17
Next steps What agreements are required?
Protocol for seeking agreements On-going coordination arrangements Communication and information requirements' for Canoeing Victoria Melbourne Main Sewer Replacement 17
18
Melbourne Main Sewer Replacement 18