1 Mario Bätz CERN ST-MO-TC ENGINEERING PROCESS MONITORING FOR CONTROL ROOM OPERATION GTPM Gestion Technique dune Panne Majeure

2 GTPM - Objectives n Improvement of collaboration and understanding PCR-TCR (roles & resp.) n Reduction of the SPS restart time after major breakdown n Monitoring documents for the SPS restart (logic of SPS restart, process description, instructions etc.) n A structured method, which can be generalized to future projects

3 Gestion Technique dune Panne Majeure - GTPM n Control Room Representatives –PCR, TCR, MCR, (CRN) n Control specialists –ST/MO, SL/CO, SL/OP,... n Equipment specialists –ST/EL, ST/CV, LHC/VAC, …

4 Accelerator Oriented Monitoring: Systems, Interaction & Data Electricity HT, MT, BT, Water Pumping Stations, Raw, Prim, Chilled, Demi,... Thermal Air-conditioning, Ventilation Vacuum Pumps, Pressures Access Technical breakdowns Monitoring Hardware, Software, network... SL timing, power supplies, magnets,... CPS GTPM Major breakdown (alarms, logbooks,…) System identification System interdependency Restart objectives...

5 Example SPS Restart Diagram

6 Example TCR Restart Diagram

7 Monitoring System n Dynamic restart diagrams –UMMIs in PVSS –Drivers for various data sources < TDS, electricity, vacuum, access, transfer lines, timing, power converters,... n SAME tools in PCR,TCR, MCR,…

8 PVSS Implementation

9 Added Value n All control rooms work with the same information n Breakdown impact at one glance -> faster situation assessment n Optimised restart strategy (priorities, order) n Shorter restart time n Visual system documentation for training

10 Outlook / next steps… n Use paper tools in operation this year n Assess improvement n Finish PVSS implementation n Formalise and document the method n MCR asked for same project shutdown 2001/2002 and 2002/203 n Promote results and method for LHC operation