SANE – the last few days Time Period Activities 10/24-10/25
Hall C dump work Inspection of as-welded clearances (ATLis 7843) Certification 10/25-10/26 Beam setup and start commission Identify various startup problems (MPS BCM readback, BTA, ROC14, Analyzer etc.) Target (transfer lines, lifter) 10/27 Hall in restricted access Target work (lifter, rails) Helium bag DAQ, SEM Helicity Reporting Delay: NO DELAY Beam polarization: not at this energy
2
SANE – the next few days HMS commissioning Expect solid target to be available this evening SEM commissioning Energy measurement Commissioning with polarized target Currently expect this on Wednesday Still need Jlab to sign up for tonight’s and Wednesday owl shift leader