2016 Attachment O True-Up Stakeholder Meeting Ameren Illinois Company
July 12, 2017
2
Purpose is to review AIC 2016 Transmission Rate True-Up Calculations
Agenda Purpose is to review AIC 2016 Transmission Rate True-Up Calculations Protocol Timeline ROE Complaint Cases and Impact on True-up calculations 2016 True Up Calculation Total Revenue Requirement Comparison – Projected vs Actual Summary of Revenue Requirements at 12.38% and 10.82% ROE Attachment O/Schedule 9 Weighted True-up Attachment GG/Schedule 26 Weighted True-up Attachment MM/Schedule 26-A Weighted True-up 2016 MVP Spend 2016 Significant Projects Placed In Service An additional meeting will held to review the 2018 Projected Transmission Rate calculations. Tentatively set for September 19, 2017.
3
(Forward-Looking Protocols)
Protocol timeline Date Schedule (Forward-Looking Protocols) June 1 Posting of annual true-up for prior year September 1 Deadline for annual true-up meeting Posting of net projected revenue requirement for following year October 15 Deadline for annual projected rate meeting November 1 Deadline for joint meeting on regional cost-shared projects March 15 Transmission Owners submit informational filing to the Commission
4
ROE complaints MISO ROE Complaints RTO Adder (ER15-358)
1st Complaint (EL14-12) Covers November 12, 2013 through February 11, 2015 FERC order received September 28, 2016; set the Base ROE at 10.32% Applicable going forward until 2nd complaint order 2nd Complaint (EL15-45) Covers February 12, 2015 through May 11, 2016 Initial decision issued June 30, 2016; recommended Base ROE at 9.70% Additional refunds will be required upon receipt of Final Order RTO Adder (ER15-358) FERC approved a 50 basis point adder for participation in an RTO Effective January 6, 2015, applicable to complaint case refunds after that date and going forward (i.e., total ROE is now 10.82%)
5
MISO ROEs for the 2016 True-Up
ROE complaints MISO ROEs for the 2016 True-Up 12.38% ROE for January 1 – September 27 10.82% ROE for September 28 – December 31 Refunds already provided for EL14-12 Two phase process Phase 1 related to ROE impact on projected rates for forward looking TOs and annual updates for historical TOs. These were settled in February 2017. 2013, 2014 & 2015 projected rates from 11/12/13 to 2/11/15 Phase 2 related to the ROE impact on true-ups calculations for forward looking TOs. These were settled in June 2017. 2013, 2014 & 2015 True-ups included in 2015, 2016 and 2017 projected rates Refunds for Schedules 7, 8, 26, 37, 38, 26A were completed by MISO Refunds for Schedule 9 were completed by Ameren Schedule 9 Refund amounts and supporting documents are posted on Ameren’s OASIS
6
Aic 2016 ROE Weightings 2016 ROE Weightings - Schedule 9, 26 & 26A Per FERC's 9/28/16 Order in EL14-12, the ROE was revised from 12.38% to 10.32% (plus adders as applicable) effective 9/28/16. The table below calculates the percentage of the year 2016 applicable to each ROE. These percentages are used to prorate the 2016 revenue requirement.. Schedule 9 Days in Month Total Peak Prorated Schedule 26 Schedule 26-A Total Effective In Month Peaks % Revenue Monthly % January 31 6,892 1,271,595 9.361% February 29 6,583 1,139,012 8.748% March 6,028 1,141,297 8.429% April 30 5,391 1,056,305 7.455% May 6,289 1,195,729 7.905% June 8,295 1,427,881 8.587% July 8,686 1,606,617 9.601% August 8,489 1,600,616 9.258% September 27 8,382 64,198 76.48% 1,423,760 77.37% 8.602% 77.09% September 3 October 6,539 1,084,005 7.776% November 5,546 1,017,862 7.684% December 6,823 19,747 23.52% 1,184,593 22.63% 6.593% 22.91% 83,945 100.00% 15,149,272 % 12.38% 10.82% Schedule 9 has been weighted based on the actual 2016 Load in the AMIL pricing zone Schedule 26 has been weighted on the actual Schedule 26 revenue related to the 2016 Projected revenue requirement Schedule 26-A has been weighted on the monthly percentage of applicable withdrawals from the prior year consistent with the monthly allocation of the total MVP revenue requirement September load and revenue split based on number of days (i.e., 27 days at 12.38% and 3 days at 10.82%)
7
AIC Revenue Requirement Comparison
Projected 2016 vs Actual 2016 (Complete 2016 True-ups calculations with ROE at % and 10.32% are included in the posted file.)
8
Aic 2016 rate base 2016 Projection 2016 Actual Change Percent 2.6
Page.Line 2016 Projection 2016 Actual Change Percent 2.6 Total Gross Plant 1,938,342,678 1,955,115,691 16,773,013 1% 2.12 Total Accum Depreciation 502,413,116 489,351,078 -13,062,038 -3% 2.18 TOTAL NET PLANT 1,435,929,562 1,465,764,613 29,835,051 2% 2.18a 100% CWIP RECOVERY 42,507,018 32,909,248 -9,597,771 -23% ADJUSTMENTS TO RATE BASE N/A 2.20 Account No. 282 -388,199,066 -402,659,776 -14,460,711 4% 2.21 Account No. 283 -7,813,781 -9,938,863 -2,125,082 27% 2.22 Account No. 190 54,136,112 45,856,129 -8,279,983 -15% 2.23 Account No. 255 2.25 Land Held for Future Use 2,363,868 2,466,349 102,481 2.26 CWC 5,834,598 6,038,490 203,892 3% 2.27 Materials & Supplies 12,101,199 14,469,755 2,368,556 20% 2.28 Prepayments 1,491,166 1,554,677 63,511 TOTAL ADJUSTMENTS -320,085,904 -342,213,241 -22,127,337 7% 2.30 TOTAL RATE BASE 1,158,350,676 1,156,460,620 -1,890,056 0%
9
Aic 2016 expenses 2016 Projection 2016 Actual Change Percent O&M 3.1
Page.Line 2016 Projection 2016 Actual Change Percent O&M 3.1 Transmission 47,078,280 55,509,642 8,431,362 18% 3.1a Less LSE Expenses 1,495,616 1,650,984 155,368 10% 3.2 Less Account 565 13,231,075 19,509,499 6,278,424 47% 3.3 A&G 14,176,890 13,874,977 -301,912 -2% 3.4 Less FERC Annual Fees N/A 3.5 Less EPRI, ect. 362,566 200,919 -161,646 -45% 3.5a Plus Trans. Reg. Comm. Exp 510,870 284,703 -226,167 -44% 3.8 TOTAL O&M 46,676,783 48,307,921 1,631,137 3% 3.12 TOTAL DEPRECIATION 35,645,227 36,407,698 762,471 2% TAXES 3.13 Payroll 892,102 737,783 -154,319 -17% 3.16 Property 1,216,554 1,284,806 68,252 6% 3.18 Other 421,926 342,506 -79,420 -19% 3.27 Income ROE 43,674,692 43,701,611 26,919 0% TOTAL TAXES 46,205,273 46,066,705 -138,568 TOTAL EXPENSES 128,527,284 130,782,324 2,255,040 Income Taxes based on 12.38% ROE were 49,941,009 for projected and 49,971,931 for actuals resulting in Total Expenses of 134,793,601 for projected and 137,052,645 for actuals.
10
Aic 2016 Capital structure (12.38% and 10.82% ROE)
% ROE Page.Line $ % Cost Weighted 4.27 Long Term Debt 2,436,021,670 47% 0.0570 0.0267 4.28 Preferred Stock 61,721,350 1% 0.0490 0.0006 4.29 Common Stock 2,698,856,348 52% 0.1238 0.0643 4.30 Total 5,196,599,368 100% 0.0916 % ROE 2,427,922,000 0.0568 0.0266 61,632,375 0.0491 2,706,457,409 0.0645 5,196,011,784 Change in Return 0.0010% % ROE 0.1082 0.0562 0.0835 % ROE 0.0564 %
11
Aic 2016 total revenue requirement
12.38% ROE Page.Line Projected Actual Change Percent 2.30 TOTAL RATE BASE 1,158,350,676 1,156,460,620 -1,890,056 0% 4.30 Rate of Return 9.16% 0.00% 3.28 Return 106,113,678 105,952,605 -161,073 Total Expenses 134,793,601 137,052,645 2,259,043 2% 3.29 TOTAL GROSS REV. REQ. 240,907,279 243,005,249 2,097,970 1% 3.30 Less ATT. GG Adjustment 14,686,344 15,166,954 480,610 3% 3.30a Less ATT. MM Adjustment 11,861,659 11,111,510 -750,149 -6% 3.31 GROSS REV. REQ. UNDER ATT. O 214,359,276 216,726,785 2,367,510 10.82% ROE 8.35% 96,728,874 96,555,663 -173,211 128,527,284 130,782,324 2,255,040 225,256,158 227,337,987 2,081,829 13,650,271 14,112,771 462,500 10,855,997 10,184,621 -671,377 200,749,890 203,040,596 2,290,706
12
Aic 2016 Net revenue requirement for Schedule 9
12.38% ROE Page.Line Projected Actual Change Percent 1.1 Gross Revenue Requirement 214,359,276 216,726,785 2,367,510 1% 1.6 Total Revenue Credits 13,373,302 11,346,144 -2,027,158 -15% 1.6a Historic Year Actual ATRR 139,652,172 0% 1.6b Projected ATRR from Prior Year 130,545,024 1.6c Prior Year ATRR True-Up 9,107,148 1.6d Prior Year Divisor True-Up (2,971,336) 1.6e Interest on Prior Year True-Up 743,038 1.7a NET REVENUE REQUIREMENT 207,864,823 212,259,491 4,394,668 2% 1.7b Prairie Power N/A 1.7 AIC Adjusted Revenue Requirement 10.82% ROE 200,749,890 203,040,596 2,290,706 194,255,438 198,573,302 4,317,864 . Prior year true-ups shown above represent the 2014 revised true-up at 10.32% ROE as a result of the Order in Docket EL The 2014 true –up at 12.38% ROE was originally included in 2016 rates.
13
Attachment O, GG & MM Revenue Requirement Summary
12.38% ROE Projected Actual Change Percent Total Revenue Requirement 240,907,279 243,005,249 2,097,970 0.9% Less Attachment GG Rev Req 14,686,344 15,166,954 480,610 3.3% Less Attachment MM Rev Req 11,861,659 11,111,510 -750,149 -6.3% Gross Attachment O Rev Req 214,359,276 216,726,785 2,367,510 1.1% Less Revenue Credits 13,373,302 11,346,144 -2,027,158 -15.2% Plus Total Prior Year True-up 6,878,850 0.0% Net Attachment O Rev Req 207,864,823 212,259,491 4,394,668 2.1% 10.82% ROE 225,256,158 227,337,987 2,081,829 13,650,271 14,112,771 462,500 3.4% 10,855,997 10,184,621 -671,377 -6.2% 200,749,890 203,040,596 2,290,706 194,255,438 198,573,302 4,317,864 2.2% Shaded cells used in True-up calculations Prior year true-ups shown above represent the 2014 revised true-up at 10.32% ROE as a result of the Order in Docket EL The 2014 true –up at 12.38% ROE was originally included in 2016 rates.
14
Aic 2016 attachment o true up for Schedule 9
Attachment O 2016 True-up calculation (Schedule 9) 2016 Rev Req at 2016 Weighted Calculation of 2016 Weighted Attachment O Rev Req 12.38% 10.82% Rev Req Net Actual 2016 Rev Req (Actual Attach O, Pg 1, Line 7) $212,259,491 $198,573,302 Percent of Actual Revenue Requirement at ROE 76.48% 23.52% Weighted Net Actual 2016 Rev Requirement $162,336,059 $46,704,441 $209,040,500 Net Projected 2016 Rev Req (Projected Attach O, Pg 1, Line 7) $207,864,823 $194,255,438 Percent of Projected Revenue at ROE Weighted Net Projected 2016 Rev Requirement $158,975,017 $45,688,879 $204,663,896 Under/(Over) Collection of 2016 Weighted Net Rev Req $3,361,042 $1,015,562 $4,376,604 Historic Year Actual Divisor for Transmission Owner (Attach O, Pg 1, Line 15) 6,995,394 Proj'd Yr Divisor for Transmission Owner (Projected Attach O, Pg 1, Line 15) 7,118,197 Difference between Historic & Projected Yr Divisor 122,804 Prior Year Projected Annual Cost ($ per kw per yr) $ $ Percent of Revenue Received at ROE Weighted Prior Yr projected Annual Cost ($ per kw per year) $ $6.4186 $ Under/(Over) Collection of 2016 Divisor True-up $3,530,885 Total Under/(Over) Recovery $7,907,489 Monthly Interest Rate (Over collection = FERC rate, Under collection = company rate) 0.0537% Interest For 24 Months $101,912 Total 2016 Attachment O True-up Under/(Over) Recovery $8,009,401
15
Aic 2016 attachment o true up for Schedule 26 & 26-A
Attachment GG 2016 True-up ( Schedule 26) 2016 Rev Req at 2016 Weighted Actual Calculation of Weighted Rev Req for 2016 True-up 12.38% 10.82% Rev Req Actual Attachment GG Rev Req for True-Up Year (Actual Attach GG, pg 2, col 10) 1 $15,166,954 $14,112,771 Percent of Actual Revenue Requirement at ROE 77.37% 22.63% Weighted Actual Attachment GG Rev Req for 2016 True-Up $11,734,672 $3,193,720 $14,928,392 Actual Attachment GG Revenues Received for 20161 $14,774,285 Under/(Over) Recovery of 2016 GG Rev Req $154,107 Monthly Interest Rate (Over collection = FERC rate, Under collection = company rate) 0.0537% Interest For 24 Months $1,986 Total 2016 Attachment GG True-up Under/(Over) Recovery $156,093 1 Amount excludes True-Up Adjustment, as reported in True-Up Year projected Attachment GG, page 2, column 11. Attachment MM 2016 True-up (Schedule 26-A) 2016 Weighted Actual Rev Req Calculation of Weighted Rev Req for Revised 2016 True-up Actual Attachment MM Rev Req for True-Up Year (Actual Attach GG, pg 2, col 14) 1 $11,111,510 $10,184,621 77.09% 22.91% Weighted Actual Attachment MM Rev Req for 2016 True-Up $8,565,863 $2,333,297 $10,899,160 Actual Attachment MM Revenues for 20161 $10,755,044 Under/(Over) Recovery of 2016 MM Rev Req $144,116 $1,857 Total 2016 Attachment MM True-up Under/(Over) Recovery $145,973 1 Amount excludes True-Up Adjustment, as reported in True-Up Year projected Attachment MM, page 2, column 15.
16
Aic 2016 attachment gg True-up for Schedule 26
AIC 2016 Weighted Attachment GG True Up by Project 2016 Attachment GG True-Up Adjustment - Weighted ROE Company Name: AIC True-Up Year: 2016 (a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) Actual Projected Attachment GG True-Up Applicable MTEP Annual Revenues Adjustment Interest Total Line Project Revenue Allocated Principal Rate on No. Name Number Requirement 1 to Projects 1 Under/(Over) [Col. (d), line 1 x (Col. (e), line 2x / Col. (h) x Col. (i) p 2 of 2, Col. 102 Col. (e), line 3)]2 Col. (g) - Col. (f) Line 5 x 24 months 2 Col. (h) + Col. (j) 1 Actual Attachment GG revenues for True-Up Year 1 $ ,774,285 2a Wood River-Roxford kV line 728 $ ,665 $ ,942 $ ,715 $ (15,227) 0.0537% $ (196) $ (15,423) 2b Sidney-Paxton 138kV Reconductor 18 miles 870 $ ,523 $ ,560 $ ,948 $ (26,612) $ (343) $ (26,955) 2c Coffeen Plant-Coffeen, North - 2nd. Bus tie 2829 $ ,231 $ ,882 $ ,245 $ (21,637) $ (279) $ (21,916) 2d Latham - Oreana 8.5 mile 345kV line 2068 $ ,453,281 $ ,530,320 $ ,439,878 $ (90,442) $ (1,166) $ (91,608) 2e Brokaw-S. Bloom 345/138kV Trans & 345kV line 2069 $ ,418,811 $ ,517,390 $ ,535,858 $ ,468 $ $ ,706 2f Fargo-Mapleridge-20 mile 345kV line & New Sub 2472 $ ,519,369 $ ,620,191 $ ,909,750 $ ,559 $ ,732 $ ,291 3 Subtotal $ ,451,880 $ ,774,285 $ ,928,394 4 Under/(Over) Recovery $ ,109 $ ,986 $ ,095 5 Applicable Interest rate per month (expressed to four decimal places) Interest Rate to be updated through July 2017 Amount excludes True-Up Adjustment, as reported in True-Up Year projected Attachment GG, page 2, column 11. 2 Rounded to whole dollars.
17
Aic 2016 attachment MM true-up for Schedule 26-A
AIC 2016 Weighted Attachment MM True Up by Project 2016 Attachment MM True-Up Adjustment – Weighted ROE Company Name: AIC True-Up Year: 2016 (a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) Actual Projected Attachment MM True-Up Applicable MTEP Annual Revenues Adjustment Interest Total Line Project Revenue Allocated Principal Rate on No. Name Number Requirement 1 to Projects 1 Under/(Over) [Col. (d), line 1 x (Col. (e), line 2x / Col. (h) x Col. (i) p 2 of 2, Col. 142 Col. (e), line 3)]2 Col. (g) - Col. (f) Line 5 x 24 months 2 Col. (h) + Col. (j) 1 Actual Attachment MM revenues for True-Up Year 1 $ ,755,044 2a Pana-Sugar Creek - CWIP 2237 $ ,220,811 $ ,053,511 $ ,755,088 $ (298,423) 0.0537% $ (3,846) $ (302,269) 2b Pana-Sugar Creek - Plant in Service $ ,725,322 $ ,520,015 $ ,453,499 $ (66,516) $ (857) $ (67,373) 2c Sidney-Rising - CWIP 2239 $ ,307 $ ,647 $ ,859 $ ,212 $ $ ,408 2d Sidney-Rising - Plant in Service $ ,258 $ ,520 $ ,751 $ ,231 $ ,459 $ ,690 2e Palmyra-Pawnee - CWIP 3017 $ ,663,313 $ ,538,011 $ ,137,726 $ (400,285) $ (5,159) $ (405,444) 2f Palmyra-Pawnee - Plant in Service $ ,248,640 $ ,079,243 $ ,560,372 $ ,129 $ ,201 $ ,330 2g Fargo-Galesburg-Oak Grove - CWIP 3022 $ ,968 $ ,162 $ ,499 $ (9,663) $ (125) $ (9,788) 2h Fargo-Galesburg-Oak Grove - Plant $ ,009 $ ,670 $ ,065 $ ,395 $ $ ,980 2i Pawnee-Pana - CWIP 3169 $ ,041,175 $ ,740 $ ,312 $ (143,428) $ (1,849) $ (145,277) 2j Pawnee-Pana - Plant in Service $ ,459 $ ,525 $ ,991 $ ,466 $ ,251 $ ,717 3 Subtotal $ ,631,262 $ ,755,044 $ ,899,162 4 Under/(Over) Recovery $ ,118 $ ,856 $ ,974 5 Applicable Interest rate per month (expressed to four decimal places) Interest Rate to be updated through July 2017 Amount excludes True-Up Adjustment, as reported in True-Up Year projected Attachment MM, page 2, column 15. 2 Rounded to whole dollars.
18
AIC 2016 MVP SPEND Ameren MVPs Ameren Name 2016 CAPEX MTEP #s
MTEP Description Illinois Rivers $53.03 million 2237 Pana - Mt. Zion - Kansas - Sugar Creek 345 kV line 2239 Sidney to Rising 345 kV line 3017 Palmyra-Quincy-Meredosia - Ipava & Meredosia-Pawnee 345 kV Line 3169 Pawnee to Pana kV Line Spoon River $0.77 million 3022 Fargo-Galesburg-Oak Grove 345 kV Line
19
2016 Significant transmission projects added to plant
Project Name Total Cost Illinois Rivers Connections (MVP) $69.1 Fargo - Mapleridge $53.5 Grand Tower - Makanda $23.0 Brokaw - Gibson City $15.0 Sidney - Eugene $10.5 Macomb West Tap $9.9 E Quincy - Hamilton $8.4 N Decatur - Latham West $8.3 Keemin Substation $7.4 Mattoon W - Murdock $6.9 CIP V5 $6.0 Jacksonville - Meredosia $5.9 Canton S - Ipava S $5.8 Mt. Zion Substation $5.6 Madison Industrial - Madison State St $5.1
20
Additional information
Additional questions can be sent to Ameren at: MISO Web Links Transmission Pricing - Attachments O, GG & MM Information Ameren OASIS MTEP 16 MTEP 17 Schedule 26 & 26-A Indicative Charges