Pavement Improvement Plan
Determine current pavement condition. Identify and prioritize needed repairs. Coordinate with RIDOT projects. Assess available funding. Select repairs to fit budget framework. Prepare bid documents and advertise.
3
Current Pavement Condition
4
Pavement Management Program
Initial inventory and condition survey prepared by Beta Group in 2007. All roads are rated with 100 best. Database maintained and kept up to date by Engineering Department. Software automatically predicts pavement condition based on model of deterioration over time.
5
RSR (Road Surface Rating)
Network RSR = 69
6
Network Backlog (2009) Repair Method Length (mi) Estimated Cost %
Reclamation 3.92 $1,372,830 2.77 Mill & Overlay 9.52 $2,415,781 6.72 Level & Overlay 55.24 $6,321,261 39.00 Crack Seal 41.29 $227,191 29.15 Defer 31.67 $0 22.36 Total 141.65 $10,337,062 100.00
7
Network Backlog By Repair
8
RIDOT Planned Projects
9
RIDOT Projects
10
RIDOT Projects Route 91 1R, Contract 1 - High Street (Route 3) to Larry Hirsch Lane Route 91 1R, Contract 2 – Larry Hirsch Lane to Church St. (Route 216) Shore Rd. Resurfacing – Ocean View Hwy. to Post Rd. Weekapaug Bridge Elm St. & Beach St. (Main St. to Clark St.) Railroad Ave., Dixon St., & West St.
11
Available Town Funds General Fund FY2009 - $450,000
Water Fund FY $750,000 (Transmission Main Project) General Fund FY $200,000 Total $1,400,000
12
Proposed Town Projects
13
Town Projects Total = 7.75 Miles
14
Westerly 2009 Projects General Fund ($650,000 budget)
Crack Sealing – $50,000 (Various Roads) Level & Overlay - $110,000 (Pound Rd., Hiscox Rd. & Wampanoag Ave.) Mill & Overlay - $370,000 (Bellevue Ave., John St., Narragansett Ave., Raymond St., & Ward Ave.) Total - $530,000 est.
15
Westerly 2009 Projects Water Fund ($750,000 budget)
Mill & Overlay - $460,000 est. (Terrapat Dr., Perkins Ave., Pond St., Pierce St., Industrial Dr., Narragansett Ave., & Summer St.)
16
2009 Road Improvements Predicted RSR = 71
17
RI – LEAP Funds (Local Equity Aid Program)
$358,000 (Federal) + $150,000 (State) = $508,000 Total Cross St. Pavement & Sidewalks = $525,000 est.
18
Additional Planned Projects
Old Hopkinton Road Canal St./White Rock Road Rehabilitation Bay Street Drainage/Pavement Restoration Bradford Streetscape Project Misquamicut Drainage Extension Chip Sealing Program