Gep/SANE this week – quick overview
Time Activities 3/31 – 4/2 SANE tests Beam centering Detector checkout 4/2 Energy change 3 pass More SANE detector studies GEp optics runs 4/3 GEp3 running – beam energy TBD Currently: E=5.717 GeV, 5 pass Polarization ~80% (expected)
2
Gep/SANE this week – details
Time Activities Friday Complete tracker installation Trigger work Target cooldown - successful Hall C readiness checklist Saturday, Sunday Additional detector and software work and wait for beam Monday Beam centering Detector checkout
3
Beam centering studies
Carbon hole at x=0.7mm, y=+2.0mm Centering with dummy target gives x~0.0mm