Download presentation
Presentation is loading. Please wait.
1
AFRD2 Managed Recharge Expansion Projects
MP 28 Hydro Plant Bypass – Completed Nov 20th November 4th December 11th January 5th IWRB Cost $45,000
2
AFRD2 Managed Recharge Expansion Projects
MP 31 Expansion - est. Completion Fall 2016 Maximize the Recharge Site 2014/2015 avg. diversion = cfs Pool depth = 18 ft 2015/2016 avg. diversion = 196 cfs Pool depth = 22 ft Potential Improvements – 300 cfs Construct a more robust check dam Larger turn out gates to the facility
3
AFRD2 Managed Recharge Expansion Projects
MP 31 Recharge Site November 18th November 30th November 30th December 18th
4
AFRD2 Managed Recharge Expansion Projects
Concrete Flume November 6th January 14th November 9th
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.