Academy High School Update
A Report to the Board of Education Prepared by Facilities and Planning December 13, 2011
2
Current Project Status
Educational Specifications completed Preliminarily reviewed and approved by the California Department of Education Initial design development completed Basic site layout and building design features determined Property easement and utility connection layout work being formulated Street alignments and underground utility service discussions underway with City and County planning departments December 13, 2011 Academy High School Status Update
3
Next Anticipated Steps
Project funding requirements identified Traditional sources not readily available State building program and Measure L fund availability uncertain Alternate funding strategies being explored Project on hold until funding secured December 13, 2011 Academy High School Status Update