Presentation is loading. Please wait.

Presentation is loading. Please wait.

Risk Assessment Contingency Endgame

Similar presentations


Presentation on theme: "Risk Assessment Contingency Endgame"— Presentation transcript:

1 Risk Assessment Contingency Endgame
John N. Galayda – Director of LCLS Construction March 30, 2009

2 Risks Technical Injector through undulator system, risks are understood and controlled Electron beam systems performing well X-Ray systems construction complete Thoroughly tested functionality prior to delivery Risks associated with damage to optics Attenuator, sacrificial test coupons, spare mirrors Early & ongoing testing of B4C damage threshold

3 Risks Schedule Attempting to advance the schedule for AMO experiments compared to baseline schedule Accelerate commissioning of upstream hardware Accelerate installation Not a concern for CD-4 Hutch construction schedule is on critical path to CD-4, with 108 days float to CD-4 Space renovation schedule has less float, 83 days float to CD-4 Schedule for contingency allocation Get bids for space renovation by end of April

4 Risks Cost Space renovation Overruns late in the project
Perform a bottoms-up cost estimate on all remaining work (Nov08) Perform monthly EAC and contingency analysis FEE & AMO installation Perform a readiness review Monitor detailed installation planning schedule Owner-directed changes (hutches) Perform cost estimates at 30%, 60% & 90% Design-to-cost A/E contract Space renovation Scope of re-habilitation of Bldgs 28 & 750 is controllable GMAX for new space

5 Cost Risks Change orders for TCCo subs are largely negotiated
$600K return on allowances $200K unused field change order BA Claims ($4.6M) still the biggest risk Accruals for claims have been established and subjected to external review Enact endgame plans for construction budget Revise accruals when new information is obtained FEH Hutches – Today’s presentation Space renovation is last major CF cost driver We had kept $2.5M in the baseline for claims. Based on accrual review we are keeping $1.4 in the baseline. I am not optimistic that our position on the claims will be simply accepted by the contractor.

6 Safety Risks New work planning process
LCLS personnel are experienced and well-trained New civil construction contractors onsite LCLS experience, lessons learned X-ray commissioning Readiness Process

7 January Contingency Analysis

8 Scope Restoration Candidates

9 LCLS End-Game Timeline
Design LCLS Office Space w/Options OPA Review (DC) Turner Punchlist Done Turner Constr Comp CD-4 (7/31/2010) Award LCLS Office Space now Construct LCLS Office Space A S O N D J F M A M J J A S O N D J F M A M J J 2008 2009 2010 ETC Complete w/SXR Construct H4 & H5 H4 & H5 BO Design H4, H5 H6 1st Light in FEH 1st Light in FEE X-Rays in NEH Award H4 & H5 H6 TBD Timeline allows endgame scope decisions to be made sequentially. Final scope contingency (space renovation) includes options.

10 Decision Timeline

11

12

13

14 Stability is not so far from the goal (~10%)
Normalized phase space centroid jitter after BC1 (~4% of rms beam size) RMS AxN = 3.9% RMS AyN = 3.4% Stability is not so far from the goal (~10%) 1-s beam size D. Ratner … near end of linac (10-15% of rms beam size) RMS AxN = 14% RMS AyN = 9% DE/E jitter  0.03% DQ/Q jitter  1.5% Q = 0.25 nC

15 Measuring Bunch Arrival Time Jitter
S-band (2856 MHz) BPM V(t) Q = 0.25 nC TCAV ON TCAV OFF BPM Y Position (mm) slope = mm/deg Now measure BPM jitter both with transverse RF OFF, and then ON (at constant phase) Dt  ±0.6 ps 9 mm rms 110 mm rms Timing Jitter (w.r.t. RF) = (110 mm)/(2.34 mm/deg) = deg  46 fsec rms

16 Other Commissioning Results
Measured effect of vacuum chamber wake fields- good agreement with predictions

17 Trajectory is Straight Enough for 1.5 Angstom

18 Diagnostics Working Well
3 nanoradian kick easily discerned Submicron motion of electrons easily discerned

19 Predicted X-Ray FEL power, computed from electron beam properties
M. Xie method, with wakes FEL Power 3D Gain Length Predicted X-Ray FEL power, computed from electron beam properties

20 Measurements and Simulations for 20-pC Bunch at 14 GeV
sz  1 mm ? 8 kA? LiTrack (no CSR) Photo-diode signal on OTR screen after BC2 shows minimum compression at L2-linac phase of deg. PRELIMINARY gex  0.4 mm at sz  1 mm Y. Ding 1.5 Å, 3.61011 photons Ipk = 4.8 kA ge  0.4 µm Horizontal projected emittance measured at 10 GeV, after BC2, using 4 wire-scanners. LCLS FEL simulation at 1.5 Å based on measured injector beam and Elegant tracking, with CSR, at 20 pC.

21 15 Å, 1.2 fs 20-pC Bunch at 4.3 GeV, 15 Angstrom
Approaches a Longitudinally Coherent Single Spike z = 25 m (power profile at z = 25 m varies from shot to shot due to noisy startup) Y. Ding 15 Å, z = 25 m, 2.41011 photons, Ipk = 2.6 kA, ge  0.4 µm 1.2 fs LCLS FEL simulation at 15 Å based on measured injector beam and Elegant tracking, with CSR, at 20 pC.

22


Download ppt "Risk Assessment Contingency Endgame"

Similar presentations


Ads by Google