Boiler house and changing rooms refurbishment
CST Renewables LTD Boiler house and changing rooms refurbishment Project Overview Removal of two Ideal CX boilers, calorifier and associated plant and replace with instantaneous Rinnai water heaters and a Potterton system boiler. Convert gravity tank system to boiler house stored pumped system. The works for the project included: Installation of two Rinnai HDC 1500i and one Potterton Installation of two Grundfos booster tanks and two slave tanks Arrange new Gas meter and supply and install gas pipework Installation of new twin pipe heating circuit and radiators Complete controls and control panel manufacture and install Project Value: £30,000.00 Project Team Client: Maesteg Rugby Club Main Contractor: CST Renewables Ltd Consultant: N/A Project Manager: Mark Hillier-Rees Completion Date: August 2015 PROJECT PROFILE