CHPE308 Chapter Seven (Textbook) Estimation Of Capital Cost

Similar presentations


Presentation on theme: "CHPE308 Chapter Seven (Textbook) Estimation Of Capital Cost"— Presentation transcript:

1 CHPE308 Chapter Seven (Textbook) Estimation Of Capital Cost

2

3

4 Estimating Purchased Equipment Costs
Vendor quote Most accurate based on specific information requires significant engineering Use previous cost on similar equipment and scale for time and size Reasonably accurate beware of large extrapolation beware of foreign currency Use cost estimating charts and scale for time Less accurate Convenient

5 Effect of Size (Capacity)
(7.1) Cost Exponent Equipment Cost Attribute - Size Cost Re-arrange the equation 7.1 to: (7.2) See Table 7.3 for values of n

6

7 Effect of Size (Capacity) Figure 7.1
CEPCI: Chemical Engineering Plant Cost Index

8 Effect of Size (Capacity) cont.
Typically: n = 0.4 – 0.8 Often n ~ 0.6 and we refer to Eq.(7.1) in this case as the six-tenths rule. Assume all equipment have n = 0.6 in a process unit and scale-up using this method for whole processes

9 Also see example 7.4

10 7.3 Another way of scale up:
Equation 7.2 can be rearranged to the following form: 7.3 If equation 7.3 is plotted on log-log scale curve will have negative slope as shown in Figure The negative slope means that as the capacity of Equipment increases, its cost per unit of capacity decreases.

11 Another way of looking at economy of scale

12 100 m2 Exchanger is not twice as expensive as a 50 m2 exchanger
Extra Example A New Plant Ordered a Set of Floating Head Heat Exchangers (Area = 100 m2) cost $92,000. What would the cost be for a similar Heat Exchanger if the Area = 50 m2 and n = 0.44 ? 100 m2 Exchanger is not twice as expensive as a 50 m2 exchanger  Economy of Scale

13

14

15 Time increases – cost increases (inflation)
Effect of Time Time increases – cost increases (inflation) Inflation is measured by cost indexes - Figure 7.3 or Table 7.4 Chemical Engineering Plant Cost Index (CEPCI) Marshall and Swift Process Industry Index

16 Figure 7.3

17

18

19 Equation for Time Effect
C = Cost I = Value of cost index 1,2 = Represents points in time at which costs required or known and index values known

20 Example Cost of vessel in 1993 was 25,000, what is the estimated cost (using CEPCI) now (2007) if CEPCI = 500)?

21 Example 7.6

22 Example 7.6 solution

23 Example: Accounting for Time and Size

24 Example- Solution Must First Bring Costs to a Common Time A = 70

25 Example– Solution (cont’d)

26 Example 4 How much ($) would the new vessel cost? Date Vessel Capacity
Purchased Cost (pounds sterling = £) Exchange Rate 1993 75 £ 7,800 $ 1.40/£ 1998 155 £ 13,800 $ 1.65/£ 2007 120 $ 2.00/£ CEPCI 359 390 500 Key here is to scale with time in pounds and then convert to US dollars at the end – this assumes that the CEPCI is similar in the UK as in the US How much ($) would the new vessel cost?

27

28 Total Cost of Plant Purchased cost – equipment free on board (f.o.b.)
Installed cost – Often 3 to 8 times higher than purchased cost

29 Installed Cost of Equipment (Table 7.6)
1. Direct Project Expenses Equipment Material for installation Labor for installation 2. Indirect Project Expenses Freight, insurance, and taxes Construction overhead Contractor engineering expenses

30 Installed Cost of Equipment Table 7.6 (cont’d)
Contingency and Fee Contingency Contractor fee Auxiliary Facilities Site development Auxiliary buildings Off-sites and utilities

31

32 Example 7.7: The capital cots of a 30,000 metric ton/year isopropanol plant established in 1992 was $ 23 Million. Estimate the capital cot of a new plant with production rate 50,000 metric ton/year in 2007 (assume CEPCI = 500)?

33

34 Purchased Cost of Major Equipment From Preliminary PFD
(Pumps, Compressors, vessels, etc.) Total Module Cost Disadvantage: Can’t accurately account for the common problems of special material of construction and high operating pressures.

35 Example 7.8

36 Module Factor Approach
Common for New Chemical Plant –Accepted as preliminary cost estimation. Table 7.8 Direct, Indirect, Contingency and Fees are expressed as functions (multipliers) of purchased equipment cost at base conditions (1 bar and CS) Each equipment type has different multipliers. Deviation from base condition (1 bar & CS) are handled using factors that depend on: The specific equipment type. The specific system pressure The specific material of construction Details given in Appendix A

37 Module Factor Approach
Bare Module Factor (sum of all multipliers) Bare Module Cost Purchased Equipment Cost for CS and 1 atm pressure - Appendix A FBM = B1 + B2FpFM Fp = pressure factor (= 1 for 1 bar) FM = material of construction factor (=1 for CS) Please check Appendix A (all figures and Tables)

38 Bare Module Factor (at 1bar& CS)

39

40

41

42

43 Figure A.18

44 Module Factor Approach
Figure A.18

45 Case Study Repeat Example 7.10 considering the following:
Operating pressure 12 bar. Floating head, shell & tube constructed using stainless steel (SS)

46 Pressure Factors Equ 7.9

47 Module Factor Approach – Pressure Factors
Equation 7.10

48

49 Effect of Materials of Construction and Pressure on Bare Module Cost
MOC Cp CBM 1 bar CS 25 K 82.3 K SS 68.3 K 154 K 100 bar 34.6 K 98.1 K 94.4 K 197.4 K This slides illustrates the effects of materials of construction and pressure on the bare module costs. This is also illustrated for 2006 numbers in Chapter 7, Examples 7.10 – 7.12

50

51

52

53

54 Example 7.14

55 Important new information :
Equation A.1 check the capacity parameter (area, diameter, volume) Pressure factor (Fp) fro vessels or towers can be calculated using both equation 7.10 or figure 7.6 Table A.5 there is different formula of bare module cost (CBM) for different equipment FBM for date in Figure A.6 (packing, towers, trays) can be directly calculated using identification number in Table A.6 See the difference between Table A.3 and A.6

56 Bare-Module and Total-Module Costs
BM – Previously Covered TM – Includes Contingency and Fees at 15% and 3% of BM

57 GR – grass-roots cost includes costs for auxiliary facilities
Grass-Roots Costs GR – grass-roots cost includes costs for auxiliary facilities Use base BM costs in GR cost (1 atm and CS) since auxiliary facilities should not depend on pressure or M.O.C. The auxiliary facilities such as roads, changing rooms, tank farms, offsites, utilities, etc. should not be a function of the operating pressure or MOC. Therefore the value for them is taken based on the base-case conditions (1 atm and CS).

58 Materials of Construction
Very important Table 7.9 – rough guide Perry’s – good source Based on the cost changes associated with changes in MOCs, it is very important to specify the MOC correctly.

59 Materials of Construction
Table 7.9

60 Materials of Construction
Table 7.9

61 Capcost Calculates costs based on input
CEPCI – use current value of 500 or latest from Chemical Engineering Program automatically assigns equipment numbers

62 Capcost There is a video showing how to use the capcost program. It is very straight forward – just follow the screens and fill in the numbers. A sequence for a shell and tube exchanger is shown on the next slide.

63 The input form requires a choice of MOC, operating pressures, required heat transfer area and number of shells. The program will calculate the base purchased cost (Cop) and the bare module cost CBM) for the equipment.

64 Once the information has been entered, the equipment list will be automatically updated with the correct equipment number and cost info. If the Utilities tab is pressed the CTM and CGR are given.

65 Once the information has been entered, the equipment list will be automatically updated with the correct equipment number and cost info. If the Utilities tab is pressed the CTM and CGR are given. Note that under the utilities column the word unspecified is written – this will be covered in the cost of manufacturing lecture. Additional equipment are added until all the major equipment are accounted for.

66 Summary In general, information about costs must be scaled for capacity and time using appropriate cost exponents and indices Total plant costs involve a variety of factors that vary with equipment type, operating pressure, and materials of construction. For additions to existing facilities, the total module cost should be used but for totally new projects grass roots costs are appropriate. Once the information has been entered, the equipment list will be automatically updated with the correct equipment number and cost info. If the Utilities tab is pressed the CTM and CGR are given. Note that under the utilities column the word unspecified is written – this will be covered in the cost of manufacturing lecture. Additional equipment are added until all the major equipment are accounted for.