Presentation is loading. Please wait.

Presentation is loading. Please wait.

A Draft Funding Model for the SKA

Similar presentations


Presentation on theme: "A Draft Funding Model for the SKA"— Presentation transcript:

1 A Draft Funding Model for the SKA
A Scenario Based on US SKA RFI May 2009

2 What is a Funding Model? A coordinated, coherent and equitable plan for the allocation and optimisation of funds to construction, operation and ultimately decommissioning of the SKA

3 Scope An option based on the US SKA RFI*
Integrates US SKA RFI and Astronet Infrastructure Roadmap Phase 3 and decommissioning not in scope Assumes 2014 site infrastructure construction start * US SKA RFI submitted to the US Decadal Review Board in April 2009

4 Funding Proposal Construction Phase
Capital Cost €1670 M (Phase 1+Phase 2) Phase 2 - 1/3 Split among Europe, Rest of World and USA Phase 1 – Europe assumes 60% costs Phase 1 – Host assumes 20% costs Post PrepSKA Phase added Phase 1 Construction starts 2015 Contingency costs included [Insert link on wiki to view spreadsheet]

5 Timelines interposed Proposed SKA Timeline Feb 2009
Phase 1 funding request Phase 2 funding request External Engineering Review of design SSEC Site Rec SKA-mid+low Complete Phase 1 complete Prod. Readiness Review Pathfinder implementation Pathfinder operations Early Science SKA mid+low SKA Ops 06 | 08 | 10 | 12 | 14 | 16 | 18 | 20 | 22 | 24 | Concept Design System Design Detailed Design, Prod. Eng. &Tool’g Full SKA mid + low construction and commissioning Phase 1 Construction EC-FP7: PrepSKA System design Funding Governance Site Characterisation Mobilisation Infra Plan’g Concept design & for SKA-high System design SKA-hi SKA-high Construct US TDP SKADS Proposed SKA Timeline Feb 2009 06 | 08 | 10 | 12 | 14 | 16 | 18 | 20 | 22 | 24 PrepSKA Post PrepSKA €5 M Phase 1 Phase 2 SKA-high Construct Detailed Design €60 M Costed Design Timeline as described in the US SKA RFI Apr 2009

6 Construction Civil Works €170 M Main building Small buildings
Land acquisition Grading Water Roads Power supply and back-up Security Antennae foundations Power reticulation Antennae and RF Systems Antenna unit cost ~ €160 K Receivers unit cost ~ €40 K Signal Transmission €90 M Trenching Leasing dark fibre lines Monitor and control Clockwork distribution network Signal Processing €100 M Correlator Phase 1 Correlator Phase 2

7 Construction Software Development €100 M Observation preparation
Telescope operations Monitor and control Data handling, storage distribution Calibration and imaging Special data processing Customisable from existing applications Off-the-shelf applications Draws on existing code Requires 1000 Person years or people Computing Hardware €150 M Off the shelf ~ €30 M Exaflop scale computer ~ €100 M Data storage and distribution ~ €20 M Data Integration + Testing €70 M 100 people 7 years Project Management + Contingency project management 10% of direct costs Contingency 20% of direct costs

8 Operations US SKA RFI €150 M/yr: Astronet €10 M/yr for Phase 1
Power €50 M/yr Personnel €50 M/yr Materials & Services* €20 M/yr IFCI IWCI €30 M/yr * Includes leasing dark fibre lines Astronet €10 M/yr for Phase 1 €100 M/yr for Phase 2

9 Not Known Treatment of Pathfinders Phase 3 costs
Time Value of money, currency fluctuations in exchange rates, etc. Power costs

10 Issues Treatment of in kind contributions pre-construction
Selected site capex and opex impact Impact of different governance models Feasibility of capped costs approach


Download ppt "A Draft Funding Model for the SKA"

Similar presentations


Ads by Google