Download presentation
Presentation is loading. Please wait.
1
Future Water Supply Evaluation
CITY OF SIOUX FALLS, SOUTH DAKOTA Future Water Supply Evaluation Presented to Sioux Falls City Council February 7, 2005
2
Future Water Supply Evaluation
Outline Future Water Supply Evaluation Overview of the Challenges Basis of Evaluation Summary of Alternatives Comparison of Alternatives Conclusions and Recommendations
3
Increased Water Demands
Overview of the Challenges Population Growth Increased Water Demands =
4
Susceptibility of Water Supplies to Dry Climate Conditions
Overview of the Challenges Susceptibility of Water Supplies to Dry Climate Conditions
5
Projected Water Supply Shortfalls
Overview of the Challenges Projected Water Supply Shortfalls 2012
6
Basis of Evaluation Planning Horizons 2062 2037 2012
7
Past Population Growth Trends
Basis of Evaluation Past Population Growth Trends 2004 Pop. 137,500 2.5% Average Growth 1900 Pop. 10,266 Actual Census Population YEAR
8
Population Projections
Basis of Evaluation Population Projections ,303 pop. ,024 pop. ,398 pop. 2.06% to 1.71% 2025 2062
9
*gpcd = gallons per capita per day
Basis of Evaluation Water Demand Projections 2002 Peak Day = 52.1 mgd (387 gpcd) 387 387 387 387 341 304 Water Demand (gpcd*) 195 155 Conditions *gpcd = gallons per capita per day
10
gallons per capita per day (gpcd)
Basis of Evaluation Water Demand Projections Projected Population Per Capita Demand Projected Demand X = # of people X gallons per capita per day (gpcd) = gallons per day
11
Water Demand Projections
Basis of Evaluation Water Demand Projections Basis of Water Treatment Planning Basis of Water Supply Planning
12
Projected Water Demand Shortfalls
Basis of Evaluation Projected Water Demand Shortfalls 2062 Water Demand 2037 Water Demand Available Supply Treatment Planning Supply Planning 151 135 72 86 60 96 69 Water Demand (mgd) 22 85 55 72 29 44 63 26 13 Average Dry Drought Conditions
13
Steps of Evaluation Process
Basis of Evaluation Steps of Evaluation Process Identification of Infrastructure Capacity Requirements 2037 Planning Horizon 2062 Planning Horizon Water System Concept Development Supply (surface water vs. groundwater) Transmission Pipelines Pumping/Storage Facilities Water Treatment Facilities Delivery to the Sioux Falls WPP Preparation of Opinions of Total Probable Project Costs Estimation of Incremental O & M Costs
14
Summary of Alternatives
Considered Alternatives Lewis & Clark Rural Water System (LCRWS) Missouri River Pipeline LCRWS w/ Limited Federal Funding Missouri River Pipeline w/ Consecutive Users LCRWS w/ Limited Expansion Capacity
15
Summary of Alternatives
Overview of LCRWS Project Initial Capacity 10 MGD System Expansion Program Funding Commitment
16
Summary of Alternatives
Missouri River Pipeline Concept Future Use Permit Water Supply Alternatives 1977 Gavin’s Point Dam
17
Comparison of Alternatives
Capital Cost Comparison (2004 Dollars)
18
Comparison of Alternatives
PRESENT WORTH Annual Debt Payment Annual Incremental O&M Costs Total Annual Debt & O&M Costs ( ) LCRWS $548,550,000 $64,720,000 $202,590,000 $751,140,000 LCRWS w/ Limited Federal Funding $558,300,000 $760,890,000 LCRWS w/ Limited Expansion Capacity $570,760,000 $89,710,000 $244,600,000 $815,360,000 Missouri River Pipeline $703,240,000 $44,560,000 $149,780,000 $853,020,000
19
Conclusions and Recommendations
A water supply shortage is projected by year 2012 and will become more pronounced with anticipated community growth Securing near-, mid-, and long-term supplemental water supplies is recommended The LCRWS Alternative is least costly on a present worth analysis basis Continued participation in the LCRWS Project is recommended Interim financing may be necessary to receive initial water service from LCRWS
20
Conclusions and Recommendations
The initial capacity received from LCRWS is projected to meet water supply demands through year 2016 Additional capacity may be available through expansion of the LCRWS and is more cost-effective than independent supplemental water supply strategies A commitment from LCRWS regarding the magnitude and timeline of additional capacity should be obtained as soon as possible Eventually, an independent supply from the Missouri River will be required Due to uncertainties of expanding the LCRWS, planning efforts to obtain supplemental capacity from the Missouri River should be initiated
21
Questions?
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.